When Conveyances Go Wrong Tony Cahill Legal Author and Commentator TABLE OF CONTENTS About the author ..................................................................................... iii 1 Introduction ......................................................................................................... 1 2 Issues regarding formation of the contract .......................................................... 1 3 Remedies for breach of contract – eleven general principles ........................................................................................................................... 4 4 Some applications of the principles .................................................................... 7 4.1 The standard contract for sale and breaches of contract........... 7 4.2 Additional provisions and the obligation to complete ............. 8 4.3 The recipient’s position when confronted with a notice to complete ............................................................................................... 9 5 Cases on notices to complete and notices to perform ....................................... 11 6 Relief against forfeiture and section 55(2A) Conveyancing Act 1919 ................................................................................................... 22 7 Caveating in disputed conveyancing transactions ............................................. 39 –i– – ii – ABOUT THE AUTHOR Tony Cahill started practice in 1981. After 13 years with a medium-sized city law firm, he commenced practice on his own account at Chatswood until June 2002. Tony is currently undertaking a ‘sabbatical’ from private practice to concentrate on projects in continuing professional education. Tony is a member of the Law Society’s Property Law and Office of State Revenue Liaison Committees, and has served on the Costs Working Party. He has been a member of the Re-Draft Committees for the 2000 and 2004 editions of the Contract for the Sale of Business, and the Contract for the Sale of Land since the 1992 edition. He was the co-author, with Paul Gibney and Russell Cocks, of the first NSW edition of 1001 Conveyancing Answers. In 2006 Tony became a coauthor of Conveyancing Service NSW published by LexisNexis Butterworths. Tony is a part-time lecturer at the Sydney and Northern Sydney Institutes of TAFE in various law subjects. – iii – – iv – When Conveyances Go Wrong Tony Cahill ____________________________________________________________ 1 Introduction The aim of this paper is to consider some of the issues arising out of vendor-purchaser disputes, resulting from a failure to complete the contract in accordance with its terms. The session will look at the issue primarily from the perspective of a purchaser in breach. There are a number of reasons for this. In general: Purchasers will typically have more (and more complex) matters to attend to in the period leading up to settlement – not least being the massaging of an incoming mortgagee – and therefore, will be in breach more frequently than a vendor. The consequences for breach by a purchaser are typically more dramatic than the consequences of vendor breach. A vendor is more likely to “complain” about (for which read: take action relating to) a breach by the purchaser, than a purchaser take action in relation to a vendor breach. 2 Issues regarding formation of the contract A party seeking to enforce contractual rights must have an agreement capable of being legally enforced. This apparently trite statement of principle continues to be highlighted in cases dealing with vendorpurchaser disputes. The usual (some might say “notorious”) practice in New South Wales, where parties intend to enter into an agreement to sell and purchase land, is for two copies of the contract to be prepared which are in identical form (Allen v Carbone (1975) 132 CLR 528 at 533), with one copy is signed by the vendor and the other copy by the purchaser. The parts are subsequently exchanged, so that the vendor will hold the copy of the contract bearing the purchaser’s signature and the purchaser will hold the copy bearing the vendor’s signature. A commonly quoted analysis of the significance of exchange is contained in the judgment of Lord Greene MR in Eccles v Bryant [1948] Ch 93 at 99: –1– When Conveyances Go Wrong Tony Cahill ... there is a well-known common and customary method of dealing, namely by exchange, and anyone who contemplates that method cannot contemplate the coming into existence of a binding contract before that exchange takes place. It was argued that exchange is a mere matter of machinery, having in itself no particular importance or significance. So far as significance is concerned, it appeared to me that not only is it not right to say of exchange that it has no significance, but it is the crucial and vital fact which brings the contract into existence. As for importance, it is of the greatest importance, and that is why in past ages this procedure came to be adopted by everybody as the proper procedure. In dealing with contracts for the sale of land, it is of the greatest importance to the vendor that he should have a document signed by the purchaser and to the purchaser that he should have a document signed by the vendor. That statement has been approved by the High Court in Brien v Dwyer (1978) 141 CLR 378 at 391; 22 ALR 485 at 495; 53 ALJR 123. When parties propose to enter into a contract for the sale of land by the customary procedure of exchange there is a strong (though not irrebuttable) presumption that the parties do not contemplate the coming into existence of a binding contract before exchange takes place (GR Securities Pty Ltd v Baulkham Hills Private Hospital Pty Ltd (1986) 4 BPR 9315). The essential characteristic of exchange of contracts is that each party will have a document signed by the other party in their possession and control (or the possession and control of their representative such as their legal adviser). One rationale is that it is important that a party to a contract knows what the party’s obligations are. While it is clearly desirable that the counterparts of the contract be identical, this is not an essential requirement, and a valid contract may be made by exchange of copies which are not identical: Sindel v Georgiou (1984) 154 CLR 661; (1984) 58 ALJR 515. In Sindel the property was passed in at auction, and negotiations in the auctioneer’s office led to a consensus between the parties. The counterpart signed by the purchaser had details of the purchaser’s name, the price and the deposit inserted, but for some reason those details were not included in the counterpart signed by the vendor. The High Court found the exchange of contracts had been effective on the following basis (at [14] to [15]): 14. An unqualified acceptance of the proposition that delivery of two parts in identical terms is crucial to an effective exchange would exclude the parties’ intention as the governing or, even as a relevant, factor. The question whether the delivery of parts in identical terms is essential must ultimately depend on the parties’ –2– When Conveyances Go Wrong Tony Cahill intention. The answer to this question determines the manner in which the contract becomes binding. And as Lord Greene M.R. emphasised in Eccles v. Bryant (at p 99), the manner in which the contract is to be created so as to become binding is to be gathered from their intention, express or implied. In ascertaining their intention, we must take account of those factors which favour an insistence on documents in such a form as will evidence with certainty a contract and the terms of that contract, factors expressed and underlined by Lord Greene M.R. in Eccles v. Bryant (at p 99) and by Lord Denning M.R. in Harrison v. Battye (p.60). We must also take account of the real intention of the parties, giving due weight to their objective - the making of a binding contract by means of the exchange of parts. And if the parties, through negotiations between their solicitors, have agreed on the terms of their bargain and settle on an exchange of parts in order to seal that bargain, it would usually accord with their intention to treat the exchange as creating a binding contract, notwithstanding the lack of correspondence in the parts, so long as that lack of correspondence is capable of being remedied by rectification. It will be otherwise when it appears that the parties intend to be bound only by an exchange of parts in identical terms or when the prior negotiations do not completely settle the terms of the bargain and the parties look to the parts as exchanged to fix these terms. 15. This approach places less emphasis on the advantage of bringing into existence a document which establishes with certainty the terms of the contract and more emphasis on the intention of the parties in creating a contract by the ceremony of exchange, the terms of the bargain having already been determined. In such a case the importance of exchange lies not so much in the circumstance that it fixes the terms of the contract as in its function in fixing the existence of a binding contract, thereby terminating the period in which each party is free to withdraw from the negotiations. This concept of exchange enables the courts to do greater justice between the parties by precluding one party from acting on the footing that there is no binding contract when, as a result of an undetected error one part of the contract does not correspond with the other. On this view of exchange the availability of rectification is not a problem. The principle expressed above has its practical limits. In Longpocket Investments Pty Ltd v Hoadley (1985) NSW ConvR ¶55-244, there was a significant difference in the “subject to finance” clause in the respective counterparts. The purchaser’s solicitor sought the change, and the amendment was agreed to by the vendor’s solicitor after the vendor had signed the contract. The amendment was made on the counterpart signed by the purchaser, but not on the other copy. The Court of Appeal held that since the amendment was agreed to without the knowledge or authority of –3– When Conveyances Go Wrong Tony Cahill the vendor, it could not be said that the parties had agreed on the terms of the bargain. A more extreme example occurred in Parkin v Pagliuca [2008] NSWSC 168. In that case the counterpart signed by the purchaser contained two section 149 certificates, but the copy signed by the vendors contained only one (the transaction was a sale off the plan of a lot in a consolidated site). More critically, the counterpart signed by the vendors contained printed pages 3 to 11 of the 2000 edition of the contract; those pages were not included in the copy signed by the purchaser. Bryson AJ held that no contract had been formed, or alternatively that if a contract had been formed the purchaser was entitled to rescind any such contract due to the absence of the statutory cooling off notice. The vendors and the purchaser successfully cross-claimed against the solicitor who had been acting for both parties at the time of the attempted formation of the contract. The measure of the purchaser’s damages was, effectively, her costs of the proceedings (which were awarded against the solicitor on an indemnity basis); the damages sustained by the vendor were quantified in Parkin v Pagliuca [2008] NSWSC 827. 3 Remedies for breach of contract – eleven general principles Property practitioners frequently have cause to focus on those things which make real estate transactions “different” from typical contracts. In some respects this is not a bad thing – if selling or purchasing a house were essentially the same as selling a newspaper or a ham and tomato sandwich many real estate vendors and purchasers would feel extremely disinclined to engage a property professional (solicitor or estate agent) to assist them. For instance: We are acutely aware of the need to have a note or memorandum of the agreement sufficient to comply with the current statutory equivalent of the Statute of Frauds. [Most types of contract can be, and frequently are, verbal]. A large part of the “paperwork” associated with real estate sales and purchases involves complying with, and testing, statutory disclosure and warranty. [For most species of contracts, an obligation of disclosure is extremely limited or non-existent, and relevant statutory warranties are, more often than not, capable of –4– When Conveyances Go Wrong Tony Cahill being counted on the fingers of one hand – for example, the implied terms under the Sale of Goods Act 1923). We emphasise the importance of exchange of contracts as the usual method of formation of real estate contracts. [Contracts in general are most frequently formed by the less complicated “offer and acceptance” model]. Despite the importance of these matters, it is worth recalling that vendorpurchaser transactions are a species of contracts, and many of the issues which arise in those transactions are resolved, not by reference to some “real-estate-centric” rule, but rather by use of general contractual principles. Focusing, in particular, on contractual disputes and remedies, it is worth revisiting these statements of principle: (A) The usual remedy for breach of contract is the common law remedy of damages. (B) Damages in contract law are compensatory rather than punitive in nature – the aim of damages in contract law is to put the innocent party in the position they would have been in if the contract had been performed (to the extent that money can do that). (C) Damages in contract law will, subject to some narrow exceptions, not be available for emotional trauma, disappointment and distress, but only for pecuniary losses. (D) Not every pecuniary loss will be recoverable. A plaintiff can recover damages of a type that would “usually” flow from a breach of that type. A plaintiff can also recover damages of a type that are “unusual” but were anticipated by the parties at the time the contract was formed. By contrast, damages that are both “unusual” and “unanticipated” are too remote to be recovered (Hadley v Baxendale (1854) 156 ER 145; Victoria Laundry (Windsor) Ltd v Newman Industries Ltd [1949] 2 KB 528). (E) Parties can include a term in their contract agreeing on the amount of damages that will flow from breach (an “agreed damages” or “liquidated damages” clause). If that clause is a genuine preestimate of the loss that will flow from breach, that clause will be enforceable. If, by contrast, the quantification of loss is not a genuine pre-estimate, but has the purpose or effect of “forcing” a –5– When Conveyances Go Wrong Tony Cahill party to complete (an “in terrorem” clause), that clause will be unenforceable as a penalty (Dunlop Pneumatic Tyre Co Ltd v New Garage and Motor Co Ltd [1915] AC 79). (F) A plaintiff must take all reasonable steps to mitigate their loss. (G) In addition to the remedy of damages, a plaintiff may seek relief in equity. The most usual equitable remedy sought for breach of contract is specific performance (sometimes it may be more appropriate to seek an injunction restraining a breach of contract). (H) The common law remedy is available as of right. The equitable remedies are discretionary. Factors that go to judicial discretion include laches; clean hands; and, most significantly, the issue of whether damages would or would not provide an adequate remedy to the plaintiff. Where the subject matter of the contract is unique, it is likely that damages will not be an adequate remedy. (I) Depending on the seriousness of the breach, the innocent party may have the right to rescind or terminate the contract. The usual test of whether the right to terminate exists is whether the contractual term is categorised as a condition (right to terminate exists), a warranty (damages only), or an innominate or intermediate term (whether the breach acts as a condition or a warranty depends on how seriously the innocent party is affected by the breach). (J) A party who purports to terminate for breach and is found not to have the right to terminate will be regarded as having repudiated the contract. The “non-terminating” party can choose to accept the repudiation and claim damages, or to reject the repudiation and seek to enforce the contract. Unreasonable delay, without more, will generally not be sufficient to constitute repudiation (Neeta (Epping) Pty Ltd v Phillips (1974) 131 CLR 286; Laurinda Pty Ltd v Capalaba Park Shopping Centre Pty Ltd (1989) 166 CLR 623). (K) These general principles need to be considered in the light of statutory modifications to the law of contract – for example, Trade Practices Act 1974, Contracts Review Act 1980, Fair Trading Act 1987. –6– When Conveyances Go Wrong Tony Cahill 4 Some applications of the principles 4.1 The standard contract for sale and breaches of contract There are numerous provisions in the standard contract for sale of land which are capable of being (and are, from time to time, in fact) breached. Some include: Payment of the deposit on time (particularly in an era of increasing use of “staggered” deposits – the 0.25% then 9.75% approach). Submission of a transfer within the time specified in the contract. Sending of a section 109 certificate in strata matters. Delivery of vacant possession. The purchaser being a foreign investor caught by clause 22 of the contract. And most importantly: Failure to complete within the time specified in the contract. Practitioners could no doubt add to this list. Most of those provisions are best categorised as warranties rather than conditions – although note that clause 22 is an essential provision, and the provision about payment of deposit is also essential, with the rider that the right to terminate is lost once the deposit is paid properly. Notably, the time for completion is, by virtue of clause 15, a “fixed but inessential” time. This last point has occasionally led to a comment by those who should know better that “the contract says six weeks, but you really have eight weeks”. The logic being that because the time nominated for completion is not of the essence, there will be a period of time after the expiry of the due date (usually a minimum of fourteen days) before anything “nasty” happens. If “nasty” is defined as the termination of the contract, and (where the purchaser is in breach) loss of the deposit, and exposure to a claim for unliquidated damages or for expenses on re-sale, that is arguably correct. If “nasty” is defined as ANY unpleasant or financial consequences, that is, on general contractual principles, not correct – see principles D and I above. Contracts for the sale of land are not somehow exempt from the principle that breach of a non-essential term grounds a claim for damages – for High –7– When Conveyances Go Wrong Tony Cahill Court authority see Legione v Hateley (1983) 57 ALJR 292; Louinder v Leis (1982) 56 ALJR 433. 4.2 Additional provisions and the obligation to complete Absent an additional provision in the contract, a breach by one party of the obligation to complete by the completion date will give rise to an entitlement to unliquidated damages, and may entitle the innocent party to issue a notice to complete (if that party is otherwise entitled to do so), requiring the party to complete within a specified time (which must be reasonable in the circumstances existing at the time of issue of the notice) from service of the notice. It has been said that a notice to complete makes the time for performance of the obligation to complete “essential” where previously it had been “inessential”. Another way of looking at the consequences is to provide evidence that a party who has failed to comply with the terms of such a notice has repudiated their obligations under the contract. Many practitioners (particularly those acting for vendors) regard the terms of the standard contract as providing insufficient protection or clarity. In particular, the prospect of suing for unliquidated damages is unattractive. The calculation and specifying of a “reasonable” time for compliance with a notice to complete is uncertain. Hence the use of arguably the most commonly encountered additional provisions – one specifying that a stated number of days (14 seems popular) will be reasonable and sufficient time for compliance with a notice to complete, and another quantifying the damage suffered if completion does not occur by the due date (the latter clause frequently, and rather unfortunately, described as a “penalty interest” clause). Given the popularity of these clauses, why are they not incorporated into the standard contract? Courts have consistently stated that where the contract states a time for completion, the reasonableness of the time allowed is to be assessed not at the date of the contract, but at the date of service of the notice – see, for instance, Michael Realty Pty Ltd v Carr [1977] 1 NSWLR 553; Georgiou v Sindel (1982) NSW ConvR 55-074; Zaccardi v Caunt [2008] NSWCA 202. Any attempt in the printed form of contract to state a single reasonable time appropriate to all transactions in which the contract will be –8– When Conveyances Go Wrong Tony Cahill used would be unlikely to be successful, and at worst, may be positively misleading. The frequently encountered “special conditions” about liquidated damages almost invariably deal only with the consequences of delay by the purchaser, and say nothing about what should happen if the vendor is guilty of the relevant delay. To some extent it is understandable that a clause inserted by a vendor’s practitioner will focus on the situation where the vendor suffers detriment. It is also fair to say that it is frequently far easier to quantify a vendor’s loss on delay (by reference to the cost of continuing to service an existing mortgagee, or the lost opportunity to invest funds), than to assess the purchaser’s loss if the vendor delays (indeed, it would be common for a purchaser to be financially better off by reason of a vendor delay in settlement). The drafters of the standard contract have not been able to devise a clause in the printed form which provides an appropriate balance between the interest of vendor and purchaser, and in particular, sets out an appropriate remedy for a purchaser confronted with a delaying vendor. (Any suggestions in that regard are encouraged!). 4.3 The recipient’s position when confronted with a notice to complete Cases about the validity of, and responses to, notices to complete continue to dot the litigation landscape. First, some general pointers which may provide an aide memoire to issuers and recipients alike: Clause 15 of the standard contract does not attempt to codify the law of notices to complete. The general law, largely developed through the courts of equity, is incorporated into the contractual provision. A notice to complete is a species of the wider class: a notice to perform (or, as it has been described by Young CJ in Equity, as a quasi-notice to complete). The notice to complete should only be used where the issuing party is seeking the other party perform their contractual obligation to complete. If a party is seeking to ensure that the other party performs any other contractual obligation, the appropriate machinery is via a notice to perform. –9– When Conveyances Go Wrong Tony Cahill The distinction can be significant because a series of cases have held that issue of a notice to complete may be read as a waiver of what would otherwise be rights of the issuing party (see Falconer v Wilson [1973] 2 NSWLR 131). A notice to complete is a two-edged sword. The issuer should be certain that they will be ready to complete in accordance with the terms of the notice, otherwise the other party may (with a sigh of relief, perhaps) rely on the issuer’s notice to terminate the contract (Castle Constructions Pty Limited v Fekala Pty Limited [2002] NSWSC 76). Where a date for completion is stipulated in the contract, and one party fails to complete without the consent of the other party, the notice to complete can be issued as soon as the stipulated date has passed (Louinder v Leis (1982) 56 ALJR 433). On the other hand, if the originally stipulated date has passed by mutual agreement, a notice cannot be issued unless there has been a new date fixed for completion first, and that date passes. Furthermore, the party fixing the new date must allow a reasonable time for the other party to get ready to complete – that “reasonable” time will probably be at least five working days (Strickland v Grieve (1996) NSW ConvR 55-762; Castle Hill Tyres Pty Ltd v Luxspice Pty Ltd (1996) 7 BPR 14,959). The issuer must, at the time of giving the notice, be free of any relevant default. Ideally, there should be no default at all by the issuer at the time the notice is issued. If the default is such that it is not causing the other party’s failure to complete, it will be sufficient that the default is cured by the time appointed for completion under the notice (McNally v Waitzer [1981] 1 NSWLR 294 – payment of a land tax liability). The issuer must be ready, willing and able to proceed to completion (as distinct from complete). The notice must allow a time for compliance that is reasonable at the time the notice is given. Additional clauses in contracts “deeming” a specified number of days to be reasonable will not be conclusive (although they may be helpful) – not least because the relevant time to assess the notice is when it is issued, not when the contract is formed. There is High Court authority that “strong – 10 – When Conveyances Go Wrong Tony Cahill circumstances” would need to exist to justify a notice giving less than 14 days to comply (Sindel v Georgiou cited earlier). Time is calculated not from the date of issue of the notice, but from the date it is served within the meaning of the contract (Zaccardi v Caunt [2008] NSWCA 202). The notice must state with reasonable explicitness: what is required to be done (that is, to complete), and also what will happen on non-compliance. The onus of proving the validity of a notice to complete lies with the party purporting to terminate for non-compliance with the notice (Lavery v Nelson (1984) NSW ConvR 55-169). The recipient of the notice should firstly consider its validity, and promptly raise any doubts about validity with the issuer. Where the recipient may be unable to comply with the notice, they should also consider whether they are able to make a proposal to the issuer to mitigate any losses the issuer is suffering from (for example, interest foregone on the balance of the price if issued by the vendor, or accommodation costs if issued by the purchaser). Such a proposal may not only lessen the likelihood of the issuer proceeding to the next drastic step, but might also be relevant to the exercise of any judicial discretion – for example, a purchaser seeking relief against forfeiture of their interest under the contract, or statutory relief such as an order for the refund of deposit under section 55(2A) Conveyancing Act 1919. 5 Cases on notices to complete and notices to perform In Alexus Pty Ltd v Pont Holdings Pty Ltd [2000] 10 BPR 18,371; [2001] ANZ ConvR 159; [2001] NSW ConvR 55-964; [2000] NSWSC 1171; [2001] ACL Rep (Issue 1) 355 NSW 7, the issue was compliance with a special condition 45, together with handwritten amendments somewhat inelegantly added (and apparently without the knowledge of the chief executive of one of the parties). To borrow the terminology of Young J (as then he was), the clauses are set out “warts and all” below: 45. The vendor warrants that it will obtain approval from the Waterways Authority to install and construct a second jetty to the – 11 – When Conveyances Go Wrong Tony Cahill foreshore of the common property and will cause the owner’s corporation to grant and mark exclusively the use of the second jetty to the purchaser and that the by-law required to pass the exclusive use to the purchaser will be secured prior to completion on this contract in favour of the purchaser by procuring an irrevocable power of attorney from the owners of Lot 1 & 2 in the strata plan. Such by law passed in the same manner and agreed for the benefit of the proprietor of Lot 1 in the Strata Plan in accordances with annexure A of this contract. (The handwritten document): Special condition No 45 The vendor & purchaser agreed that in the event of the vendor obtain approval of the water way authority for the installation & construction of a second jetty that the vendor will cause the owners corp the pass a by law convert exclusive use of the 2nd jetty to the purchaser & subject to such approval the purchaser should then pay vendor 1,250 an additional $50,0000 - above that contract price. The vendor and successor agreed that the exclusive use of the second jetty shall will be carried out in the same manner as the exclusive use by-law which the vendor as contractor & undertaken to give the purchaser lot (1) the sp. in accordance with annexure (A) of this contract. Neither the strata by-law nor the approval from Waterways was forthcoming. The vendor issued three consecutive notices to complete, and eventually purported to terminate, pursuant to the third notice. The purchaser denied the validity of each of the notices on the basis that the vendor was not at any time ready to complete because of non-compliance with the “jetty and by-laws” provisions. The vendor then sought declarations that the contract had been validly terminated, and mesne profits. The purchaser lodged a cross-claim originally seeking rectification of the contract to effect a reduction in the price if the jetty could not be obtained. Relatively late in the litigation, the relief sought in the cross-claim was changed to specific performance. His Honour first considered the characterisation of clause 45 (as amended by the handwritten clause) [at 15 to 19]: 15. “Warranty” is a word with a breadth of meaning. In Finnegan v Allen [1943] KB 425, 430 Lord Greene MR said: – 12 – When Conveyances Go Wrong Tony Cahill ‘Warranty’ is one of the most ill-used expressions in the legal dictionary, but in its essence it is contractual in nature ... 16. The ordinary meaning of “warranty” is “promise” and one should not confuse this ordinary meaning with the subsidiary meaning of a term of a contract which is not as fundamental as a condition. In Oscar Chess Ltd v Williams [1957] 1 WLR 370, 374 Denning LJ said: I use the word ‘warranty’ in its ordinary English meaning to denote a binding promise. Everyone knows what a man means when he says ‘I guarantee it’ or ‘I warrant it’ or ‘I give you my word on it’. He means that he binds himself to it. That is the meaning it has borne in English law for 300 years ... During the last 50 years, however, some lawyers have come to use the word ‘warranty’ in another sense. They use it to denote a subsidiary term in a contract as distinct from a vital term which they call a ‘condition’. In so doing they depart from the ordinary meaning, not only of the word ‘warranty’ but also of the word ‘condition’. 17. Accordingly I do not favour Mr Cashion SC’s contention that in special condition 45 the word “warrants” leads to the view that the vendor’s obligation does not go to the heart of the contract, but is a subsidiary term of the contract. In my view it has its ordinary meaning which is “promise”. However, ordinarily a promise given by warranty is of an existing fact, such as that beans are of best quality or that a ship is seaworthy. Here, the promise is that the vendor will obtain an approval. Ultimately all this means is probably that it would be more difficult to establish a breach. The jetty was included as part of the property sold, the vendor has promised to see that it is properly and lawfully constructed and, were it not for the handwritten insert, in my view if the vendor could not fulfil that promise it might not be in a position where it could it was ready, willing and able to complete the contract so as to be able to give a notice to complete. 18. The next question then is does the insertion of the handwritten document alter the position? The intent of the insertion is that if the vendor fulfils its promise the purchaser is to pay a further $50,000 (although the insertion contains an additional zero, the intention is fairly clear). Does the insertion mean that the parties have agreed that if the warranty is not fulfilled the only consequence will be that the vendor does not obtain the additional $50,000? 19. The use of the past tense in the insertion and the heading on the insertion being “Special Condition No 45” show that the parties intended that the handwriting was not an additional condition but was explanatory of what they had already agreed in the words of special condition 45. It does not seem to me that it was intended to abrogate anything that the purchaser was to obtain under – 13 – When Conveyances Go Wrong Tony Cahill special condition 45. In my view it is insufficient to transmute the vendor’s obligations in such a way that it can demand completion, merely forfeiting the $50,000 bonus. This is reinforced by the fact that the jetty is included in the contract. His Honour went on to consider a lengthy line of cases as to the ability of a party to give a Notice to Complete where that party is not ready, willing and able to complete [paragraphs 20 to 28]. His Honour held the final purported Notice was invalid, and so the vendor’s claim had to fail. The case of Park v Brothers [2001] NSWSC 88; [2001] ACL Rep (Issue 5) 355 NSW 21; (2001) NSW ConvR 55-973 concerned a contract to purchase a farming property at Hay for a price of $3,350,000. The purchaser was obliged, under the contract, to make a payment of $150,000 in relation to water rights. The purchaser had occupied the property and undertaken farming before contracts were exchanged – special conditions in the contract reflected this arrangement. That payment had to be made on or before 7 October 2000; the due date for completion was 7 December 2000. (The chronology in the judgment is a little confusing – the date of the contract is expressed to be 25 January 2001, but the due date for certain contractual obligations are dates in 2000). Payment of the water levy was not made by 7 October. On 23 November the vendor’s solicitors wrote to the purchaser’s solicitors refusing a requested variation of the contract and reminding them of the due completion date. The matter was not ready to settle on 7 December. On 12 December the vendor issued a Notice of Rescission for breach of the term regarding payment of the water levy. His Honour Mr Justice Young held that the contract was still on foot. The key issue in the decision was whether the time stated in the “water payments” special condition was essential or not. His Honour found that it was not (at paragraphs 34 to 38): 34 Section 13 of the Conveyancing Act 1919 provides that a time condition must now be construed in equity the same way as it was before 1919. This means that the onus is on the person alleging that time is essential to show that this is so; see eg Tilley v Thomas (1867) LR 3 Ch App 61, 67. 35 There are some indications that the parties intended time to be essential, the most obvious being the provision that the vendor could issue a notice of rescission. However, the great bulk of the indications are the other way. First, there is the provision in standard condition 21.6. Then there is the fact that the payment of $150,000 was a very small matter, comparatively speaking, in a contract of over $3 million. Thirdly, there was a provision for – 14 – When Conveyances Go Wrong Tony Cahill interest for a default in special condition 9. Fourthly, the parties obviously intended that the purchasers should go into immediate occupation and sow crops. A provision for automatic termination at the will of the vendor, for the non-payment of about 4% of the total purchase price, is hardly likely to be in their contemplation. 36. Thus in my view, on its proper construction, time was not of the essence in special condition 22.4. 37. It was open, of course, for the vendor to give a quasi notice to complete making time of the essence before doing this particular act. The vendor did not do that. Mr Rogers says that requiring a notice to complete in these circumstances would defeat the whole purpose of special condition 22.4. With respect, I cannot see how this is so. 38. That seems to me to be the end of the case because if the vendor was not entitled to rescind on 12 December 2000, then the contract is still on foot. The purchasers want it specifically performed and it is just a matter of standing the matter over to deal with any other problems and then making the appropriate order for specific performance. His Honour then went on to consider the meaning of the word “rescission”. Both Counsel submitted the word in the special condition was to be given the same meaning in printed condition 19. His Honour was not entirely convinced that the submissions were correct (see the discussion at paragraphs 41 to 54 of the judgement). Furthermore, a conversation between the parties in mid-October, and the letter from the vendor’s solicitors on 23 November, constituted a waiver by the vendor. An appeal to the Court of Appeal by the vendor as to quantum was successful in reducing liability to about one-third of the original award – Brothers v Park and Anor [2004] NSWCA 241. The issue of quantum was further ventilated in the High Court, resulting in the restoration of the original orders at first instance – Park v Brothers [2005] HCA 73. In Nelson v Bellamy [2000] NSWSC 182 (3/3/2000, per Simos J), the plaintiff claimed that by contract for sale of land dated 19 September 1996, she agreed to sell and the defendant agreed to purchase a property at Wamberal for a price of $285,000. There was a 10% deposit, and completion was conditional upon registration of a plan of subdivision that was, in effect, a dual occupancy subdivision. The plan was registered, the defendant notified and the due date for completion passed. A Notice to Complete was issued on behalf of the vendor, with a nominated date of 19 February 1997. Completion did not occur in accordance with the Notice. – 15 – When Conveyances Go Wrong Tony Cahill The plaintiff further claimed that on 20 February 1997 the purchaser repudiated the contract by purporting to terminate it. The plaintiff accepted this purported repudiation, and filed proceedings seeking damages. The purchaser’s defence alleged a failure to provide vacant possession as contemplated by clause 17.1 of the contract (presumably the 1996 edition). The purchaser also mounted a cross-claim, alleging breaches of the Fair Trading Act 1987 by the vendor. The alleged breaches are set out in the judgement [at paragraph 6]: (a) that the second dwelling in the course of construction on the land had been sold to a purchaser ‘off the plan’ for about $335,000.00 and that the difference in price arose because the second dwelling included a swimming pool; (b) that construction of the dwelling, the subject of the contract, on the land would be completed by about December 1996 and that the second dwelling would be completed by about January 1997, by which time the driveway to the land would be commenced and completed by about March 1997; (c) that the cross-defendant would supply and install wrought iron gates on the land, as depicted in a plan produced to the crossclaimant by the cross-defendant, such gates to incorporate a sail pattern to match the canopy at the front of the house and to have the words ‘Villa Tuscany’ incorporated into the metal work of the gates and that such gates would be delivered and installed by the end of September 1996; (d) that an iron gate would be installed by the cross-defendant in a gap in the brick boundary wall to the land and that such gate would match the gates referred to in paragraph 4(c) and that such gate would be delivered and installed by the end of September 1996; (e) that door handles for the internal doors and window latches for the windows had already been purchased by the cross-defendant and would be left in the house; (f) that a range hood would be supplied and installed by the crossdefendant in the kitchen of the dwelling and that it would be large and of solid stainless steel construction, that it would be delivered to the site within one week following the cross-claimant’s inspection of the property and installed above the gas hotplate in the kitchen and that a cupboard in Lupus Blue’ would be installed to the side of the range hood. As to the issue of vacant possession, the offending “rubbish and materials” particularised by the defendant was: 1 large wooden pallet, 3 wooden brick pallets, quantity of concrete blocks, quantity of pine board flooring off cuts, quantity of timber off cuts, 1 circular pole, broken concrete blocks, quantity of loose dried – 16 – When Conveyances Go Wrong Tony Cahill cement, quantity of other builder’s rubble and used materials and two ‘for sale’ sign boards. On this issue, Simos J held for the vendor [at 30-31]: 30. The parties agreed that the relevant test to be applied was that stated in Cumberland Consolidated Holdings Limited v Ireland (1946) KB 264 at 271, namely, that in order to constitute a breach of a vendor’s obligation to give vacant possession material left on the property must be “an impediment which substantially prevents or interferes with the enjoyment of the right of possession of a substantial part of the property.” 31. In my opinion, the items referred to above which were present on the property at the relevant time were not, within the meaning of the relevant principle, “an impediment which substantially prevents or interferes with the enjoyment of the right of possession of a substantial part of the property.” It appears that the total cost of removing the offending items would have been of the order of $600. The contract also provided that the vendor would undertake certain works at or prior to completion. Special conditions 23 and 26 (reproduced at paragraph 70 of the judgement) provided: 23. Prior to completion the vendor is to install in a proper and workmanlike manner and supply the following which are to be included in the purchase price: (a) Supply and installation of one cream aluminium window to the pantry room 600 x 1000. (b) Supply and installation of one stainless steel Extractor fan above gas hotplate with blue kitchen cupboard to match existing kitchen in Lupus Blue. (c) Supply and installation of kitchen cupboards to under ISLAND BENCH, to match existing kitchen as follows: (i) under sink cupboards with doors; (ii) open corner supports for garbage bin; (iii) open shelf for microwave; (iv) 26. partion shelf for dishwasher side, dishwasher not supplied. (d) Supply and install kikuyu turf to area on patio of approximately 4 metres x 3 metres. (a) Prior to completion the vendor agrees to do the following works in a proper and workmanlike manner, complete the top capping to top of courtyard walls, increase the height of the common courtyard wall by 40cm or two blocks, subject to council approval, which will be applied for by the vendor as soon as possible after the date of this – 17 – When Conveyances Go Wrong Tony Cahill contract, will install washout blocks in the east and south walls with finishing and pointing to suit (not rendered), will removal masking paper around windows in bedroom 2 and will install a window in the pantry, will complete internal painting to internal walls around doors and windows, will detail silicone around basin in bathroom, will complete painting around vanity basin in bathroom, will affix handles to dressing table in bedroom 1 and will apply finish to timber cupboards in bedroom 1, to fill the gap between roof and wall on northern wall in main bedroom above robe to prevent egress of water and animals and complete painting of gap between the brickwork and tiles in the north wall of bedroom 1. His Honour characterised these provisions as warranties rather than conditions or innominate terms, based on the well-established principles in cases such as Tramways Advertising Pty. Limited v Luna Park (NSW) Ltd. (1938) 38 SR(NSW) 632; DTR Nominees Pty. Limited v Mona Homes Pty. Limited (1978) 138 CLR 423 and Hongkong Fir Shipping Co. Limited v Kaasaki Kisen Kiasha Limited (1962) 2 QB 26. It follows that, to the extent any of these obligations was not performed (and there were detailed findings that some, but not all, of the matters were not performed by the vendor), they did not justify the purported termination by the purchaser. It follows that the vendor validly terminated the contract. His Honour then considered the authorities [paragraphs 142 to 145], and the competing merits [paragraphs 146 to 152], relating to a refund of the deposit to the purchaser under section 55(2A) of the Conveyancing Act 1919. His Honour’s decision [paragraphs 153 to 155] was in favour of the purchaser: 153. There is no doubt in my mind that both the plaintiff and the defendant suffered financial hardship arising from the fact that the contract, the subject of the present proceedings, was not completed on the date anticipated, the plaintiff much more so because of her more vulnerable financial position at and prior to the completion date. It cannot be suggested, however, in my opinion, that the defendant was in any way responsible for the plaintiff’s financial position prior to that date. In the same way, it cannot, of course, be suggested that the plaintiff was responsible for the defendant’s financial position prior to that date. 154. Moreover, in my opinion, it is also the case that the defendant cannot be regarded, for present purposes, as relevantly responsible for the plaintiff’s financial difficulties following the non-completion of the subject contract. It might have been otherwise if the defendant had refused to complete without any arguable basis for so refusing and if it had been established that her refusal to complete was coupled with an intention to cause the plaintiff damage or injury. It is plain, however, that such was – 18 – When Conveyances Go Wrong Tony Cahill not the case, even though the defendant has been unsuccessful in the final analysis in her attempt to establish her entitlement to refuse to complete. In those circumstances, in my opinion, for present purposes, the conscience of the defendant is relatively unaffected notwithstanding the somewhat technical nature of some of the arguments and alleged breaches on the part of the plaintiff propounded on behalf of the defendant. In the same way, however, it cannot be said, in my opinion, that the plaintiff’s conscience was in any way affected by the financial and other consequences for the defendant of the contract on being completed. So in that respect, in my opinion, for present purposes, it cannot be said that the conscience of the plaintiff was relevantly affected by any of those matters. 155. On the other hand, in my opinion, the plaintiff did resell the subject property at a very considerably higher price than the contract price albeit approximately one year later. Principally, by reason of that consideration, but also having regard to all the relevant circumstances of the case as adverted to above, I am of the opinion that it is just and equitable that the deposit should be repaid to the defendant. The “very considerably higher price” was of the order of 25% above the original contract price. His Honour then considered the various heads of recoverable damages [paragraphs 156 to 188]. Finally, His Honour considered the relevance of the Fair Trading Act 1987. His Honour ultimately found that the representations alleged were either true (and not misleading or deceptive), or on the probabilities, the recollection of the vendor as to what was said was to be preferred to the recollection of the purchaser. Of wider relevance is the threshold question of whether the conduct of the vendor was “in trade or commerce”. Reference was made to the decisions of Argy v Blunts & Lane Cove Real Estate Pty. Limited (1990) 26 FCR 112 and O’Brien v Smolonogov (1983) 53 ALR 107, which are frequently cited as authority for the proposition that a sale by a vendor of “non-business related” real estate will not be in trade or commerce. Interestingly, on this point, His Honour had this to say [at paragraph 200]: Although the matter is not free from doubt, I am of the opinion that the better view is that, as a question of fact, the sale of the subject property, and the representations alleged to have been made in connection therewith, were made in the course of trade or commerce within the meaning of the Fair Trading Act 1987. I am of this opinion, principally, because the sale of Villa Tuscany was not merely the sale of a private dwelling house in which the vendor lived, but was rather the sale of a dwelling which had been specifically built for resale at a profit, albeit – 19 – When Conveyances Go Wrong Tony Cahill that the profit was to be used to reduce the debts of the vendor (plaintiff), and that the vendor (plaintiff) did live in that property for a limited period of time, but always with the intention of living in the other building, namely, Villa Umbria permanently, or at least indefinitely. In my opinion, that part of the overall development of the single site into two properties, which involved the sale of one of those properties, namely, Villa Tuscany, at a profit, was, as a question of fact, carried out in the course of trade or commerce according to the ordinary meaning of those words and within the meaning of the Fair Trading Act 1987 because the transaction was of a commercial or business character. In my opinion, whilst repetitive conduct may well be characteristic of most trade or commerce, a single transaction of the nature of the present transaction may for present purposes, nevertheless be held, as a question of fact, to have occurred in the course of trade or commerce. The case of Australian Mortgage and Properties Pty Ltd v Baclon Pty Ltd and ors [2001] NSWSC 774; [2001] ACL Rep (Issue 10) 355 NSW 58 occupied seven hearing days (and six appearances in the Expedition List) before Austin J. In large part, the time occupied by this case appears to be due to the lack of legal representation, on behalf of the plaintiff, for most of the hearing. His Honour’s judgement contains a detailed exposition of what His Honour referred to as “a chequered history in a procedural sense” [at paragraphs 5 to 52], and constitutes a useful caveat for anyone who is minded to undertake Supreme Court litigation without full legal representation. By contract (2000 edition plus additional typed special conditions) dated 20 September 2000, Baclon agreed to sell to Australian Mortgage for a price of $1,395,000. Among the special conditions were what might be called “typical” clauses regarding a 14 day notice to complete and 12% interest on the balance of the price if late settlement occurred. The deposit (approximately 5% of the price) was released on exchange. The purchaser’s address was noted as being care of an accountant’s office. One other special condition is of significance. Special condition 12 was in the following terms: The Purchaser acknowledges that she is aware that a Development Application for the building of a 4 bedroom 2 storey residence has been approved by the Council of the Municipality of Woollahra and annexed hereto and marked with the letter ‘B’ is the Development Application No 5/00 dated 11 July 2000. The Purchaser acknowledges and agrees that she will accept the property subject to the aforesaid approval and will make no requisition, objection, claim for compensation or rescind or terminate this Agreement in respect of the said approval or any matter contained in the said annexure. – 20 – When Conveyances Go Wrong Tony Cahill His Honour noted that a section 66W certificate had been provided, although the form of certificate showed no indication that the purchaser was a company, and to whom on behalf of the company any explanation may have been provided [at 62]. The transaction also involved a deed of licence, also dated 20 September 2000. The terms are extracted at paragraphs 64 to 75 of the judgement. The property was to be occupied at no fee if completion of the purchase contract took place by 1 November 2000; thereafter an occupation fee of $200 per day was to apply. The first correspondence of significance occurred about four weeks after exchange, being a letter in which the vendor’s solicitors noted that requisitions had been waived and calling for a transfer and adjustments. Some time between that letter and 1 November, it appears an issue was raised by Mrs Howard, an undischarged bankrupt and the mother of a director of the purchaser company, about sighting the original of an earlier Development Application. Subsequently it was suggested on behalf of the purchaser that the failure to comply with this request meant the vendor was not ready, willing and able to issue a notice to complete. His Honour rejected this contention [at 83-86]. The vendor’s solicitors issued a Notice to Complete on 9 November 2000 and a second Notice to Complete on 6 December 2000. His Honour held that each notice was validly issued [paragraphs 89 to 109]. The significance of the second Notice may in part be explained by correspondence between the solicitors then acting for the purchaser and the vendor’s solicitor confirming that a document furnished by the vendor’s solicitors “satisfied the outstanding requisition” [at paragraph 97]. Late on 22 December 2000, the vendor’s solicitors prepared correspondence terminating both the contract for sale and the licence agreement. The contract-related letter was posted on 22 December 2000; the licence-related letter on 26 December 2000. It was a busy period – in fact the office of the vendor’s solicitor had intended to close for the Christmas break at noon that day. On 13 February 2001, the vendor purported to re-enter and take possession of part of the premises. His Honour found in favour of the vendor in relation to the re-entry. – 21 – When Conveyances Go Wrong Tony Cahill On 14 February 2001 the then solicitors for the purchaser made a proposal (rather sketchy in detail) to re-activate the matter and effect settlement. On 15 February 2001 the purchaser sought various orders in the nature of declaratory relief. The vendor cross-claimed seeking declarations as to the validly of its actions, and certain related orders. This action triggered various cross-claims by Mrs Howard against various parties, including her two children who were the directors of the purchaser. His Honour found in favour of the vendor on all points (including a claim for the balance of the 10% deposit recoverable by special condition in the event of default). As to the claims by Mrs Howard, all these failed. As to some of the claims, His Honour considered she did not have standing to seek the relief, and that section 36C of the Conveyancing Act 1919 did not assist her [paragraphs 146 to 148]. A lack of evidence of readiness, willingness and ability to complete the purchase contract was also fatal [at paragraph 150]. In addition to highlighting the risks of vendor-purchaser litigation without proper legal representation, and an analysis of the nature of requisitions, the case also flags the risks of permitting a purchaser to occupy under licence if the purchase does not proceed to completion. 6 Relief against forfeiture and section 55(2A) Conveyancing Act 1919 Section 55(2A) Conveyancing Act provides: (2A) In every case where the court refuses to grant specific performance of a contract, or in any proceeding for the return of a deposit, the court may, if it thinks fit, order the repayment of any deposit with or without interest thereon. This statutory provision is distinct from the long-standing jurisdiction of Equity to relieve against forfeiture of a party’s interest under a contract. The case of Kestral Properties Pty Ltd v Homes Corporation of Australia Pty Ltd [2000] NSWSC 1129; [2001] ACL Rep (Issue 1) 355 NSW 3 (29/11/00, Windeyer J) involved a rather unexceptional transaction. The plaintiff entered into a contract to purchase from the vendor/defendant property at Wollongong, under contract for sale dated 10 September 1999. The purchase price was $1,150,000. The contract provided for a deposit of 5 per cent (namely, $57,500) and, in addition, provided in special condition – 22 – When Conveyances Go Wrong Tony Cahill 15(b) that if the deposit agreed to be paid was less than 10 per cent, and the vendor became entitled to forfeit the deposit, the purchaser would, upon demand, pay to the vendor the difference between the amount that would have been 10 per cent and the amount actually paid, with the intent that the full 10 per cent of the purchase price would be forfeitable by way of deposit. The contract was terminated by the vendor for failure by the plaintiff to complete it on 3 December 1999, notice of termination being given on 6 December 1999. It had already been determined, as a separate preliminary issue, that the contract was validly terminated. The issue before His Honour related to a claim by the plaintiff purchaser that the deposit be returned to the plaintiff. His Honour found for the vendor. The key comments of His Honour are at paragraphs 13 to 16 of the judgement: 13. What has to be decided in a case such as this is whether or not it would be unjust and inequitable to allow the vendor to retain the deposit to which it is entitled under the terms of its contract. This is a matter entirely within the discretion of the Court but it must be found that, within those terms, that the vendors should not retain the benefit of the contract and should therefore not be entitled to forfeit the deposit. 14. There is no purpose in going through decided cases all of which depend entirely upon their own facts because it is an entirely discretionary matter. Nevertheless it is correct to say to that, in my view, all the principles are addressed in the decision of Justice Santow in Terry v Permanent Trustee Australia Limited (1995) 6 BPR 97544. One of the matters which is generally taken into account in considering these questions, apart from the question as to whether there is any sharp conduct or unfair taking of advantage by the vendor, is whether or not there is some evidence of a windfall which is available to the vendor as a result of the termination of the contract and therefore the ability to resell or perhaps develop. In this case there is no such evidence. 15. I accept that in the case where a contract is terminated and the property is sold almost immediately afterwards for an increased purchase price of perhaps 20 or 30 per cent then this is such an advantage to the vendor that it would be unjust to allow him or her to forfeit the deposit or retain the deposit and take the benefit of the windfall as well. There is no such evidence in this case. There is no evidence of unfair practice in my view. 16. The defendant vendor is entitled to enforce the contract and therefore to forfeit the deposit in accordance with the contract. It follows from that that the balance of the summons should be dismissed and that the cross-claimant should have the order which is sought under the cross claim. – 23 – When Conveyances Go Wrong Tony Cahill Another case in which the purchaser succeeded in an application under section 55(2A) is Kylsilver Pty Ltd v One Australia Pty Ltd (SC) [2001] NSWSC 226; (2001) 10 BPR 18,543; [2001] ANZ ConvR 362; (2001) NSW ConvR 55-971 [2001] ACL Rep (Issue 6) 355 NSW 27. The proceedings arose out of six separate contracts for sale of vacant suburban residential allotments. They were sold by the plaintiff to the first defendant, by separate contracts of sale exchanged on 23 February 1998. The plaintiff was a land developer and subdivider. The first defendant conducted a business of organising first home buyers (generally what the judgement described as “deposit challenged” purchasers) into homes by purchasing and reselling land to them and assisting them to organise finance and the services of a builder. The second defendant was the controller and a director of the purchaser; the third defendant, the spouse of the second defendant, was also a director. The contracts contained the following relevant special conditions: 16. In the event that the deposit paid by the Purchaser upon the exchange of this Contract is an amount which is less than ten percent (10%) of the purchase price, the Purchaser shall pay such further sum increasing the deposit to the amount which is ten percent (10%) of the purchase price upon completion or termination of this Contract. If this Contract is terminated, and the Purchaser fails to pay such further sum to the Vendor, the Vendor shall be entitled to recover it from the Purchaser as liquidated damages, in addition to any other moneys due and payable to the Vendor pursuant to any other provisions of this Contract. 17. Provided that the Purchser [sic] complies with all terms and conditions of this contract, the Vendor shall allow a rebate of the purchase price at settlement of Ten Thousand Dollars ($10,000.00). 18. Completion of this matter will take place on but not before 3rd July, 1998 or within three (3) calendar months of written notification by the Vendor’s Solicitors to the purchaser’s solicitors of registration of the plan of subdivision, whichever is the later. Each of the Glenwood contracts also contained a provision (clause 10) for the payment of 18 per cent interest if the contract was not completed on time and (clause 11) for the giving of a 14-day notice to complete if the contract was not completed by the completion date. Settlement did not occur within the time limited in the contracts. Notices to complete were issued by the vendor. There was an appointment made for – 24 – When Conveyances Go Wrong Tony Cahill settlement, but settlement did not occur apparently because of a dispute as to the applicability of the rebates. The vendor served notices of termination, and the purchaser treated those notices as a repudiation. The plaintiff subsequently resold the lots at a windfall profit of about $157,000. The vendor sued the purchaser in the District Court for the shortfalls in the deposit. The proceedings were removed to the Supreme Court. In the Supreme Court the purchaser filed a cross-claim seeking relief on five bases: 1. That the first defendant was induced to enter into the contracts by a misrepresentation to the effect that the rebate of $10,000 would be allowed on completion, whether or not there was compliance with the term of the contracts as to the date of completion. 2. Rectification to coincide with a pre-existing oral contract containing a term to the effect that the rebate of $10,000 would be allowed on completion, whether or not there was compliance with the term of the contracts as to the date of completion. 3. Conventional estoppel arising from the fact that the parties to the contracts proceeded on a common assumption that the rebate would be allowed on completion, whenever completion took place. 4. Estoppel because the first defendant proceeded under an assumption that the rebate would be allowed on completion, whenever completion took place, which assumption arose from or was induced by the conduct of the plaintiff. 5. Section 55(2A) of the Conveyancing Act 1919. His Honour found in favour of the purchaser on the section 55(2A) claim. The main points to note: His Honour followed the decision of McLelland CJ in Eq in Socratous v Koo (1993) NSW ConvR 55-685, to the effect that relief could be granted under the section as to the whole of the deposit even though the full 10% had not been paid [paragraph 13]. The Court followed the frequently quoted formulation of principle as expressed by Street CJ in Eq (as he then was), in Lucas & Tait (Investments) Pty Ltd v Victoria Securities Ltd [1973] 2 NSWLR 268 at 272 - 273: – 25 – When Conveyances Go Wrong Tony Cahill It is one thing to recognise that there is a wide discretion conferred upon the court under this section; it is another thing to determine the guidelines for the exercise of that discretion. The section was designed to provide relief to a purchaser against an unjust and inequitable consequence of forfeiture of a deposit. It is clear enough that at law a vendor’s right to forfeit a deposit to himself in the event of a purchaser’s default bears no necessary relation to the damages actually suffered by a vendor. At law a forfeited deposit could result in a vendor making a profit which in justice and equity he ought not to be permitted to enjoy at the purchaser’s expense. In a complementary sense, an order for the return of the deposit does not necessarily affect the vendor’s right to sue a defaulting purchaser at law and recover against him such damages as the vendor can prove. The jurisdiction under s55(2A) does not give to a court an overall discretionary supervision of monetary adjustments between parties to a contract under which a deposit was paid but which has been terminated. A vendor who forfeits a deposit in strict enforcement of his legal rights is not to be deprived of it under s55(2A) unless it is unjust and inequitable to permit him to retain it. If the court would not, in its discretion, specifically enforce the contract against the purchaser, then it may follow that it would be unjust and inequitable to allow the vendor to retain the deposit. In appropriate cases he should be left to prove the damages payable to him by the defaulting purchaser in accordance with the established rules governing the measure of damages, rather than simply pocketing the deposit, which might in some cases exceed the damages which would properly be recoverable by him at law. Equity has always looked with disfavour upon penalties or stipulations which result in a party to a contract making a profit at the expense of a defaulting party. It is clear that where the court in its discretion refuses specific performance, whether or not it also orders repayment of the deposit under s55(2A), it will still remain open to the vendor to sue the defaulting purchaser and recover against him whatever damages may be due to the vendor at law in the event of the contract having gone off through the purchaser’s breach. The ordinary principles of contract law and of damages stand untouched by this section except in so far as it operates to qualify the ordinary right of a vendor to forfeit and retain a deposit. Just as the judges whose words I have quoted declined to put a limiting gloss upon the scope of the section, I decline to state my view upon where the boundaries of the discretion are to be drawn. Specific instances of its application are to be found in the cases. They all, however, come under the general category of circumstances in – 26 – When Conveyances Go Wrong Tony Cahill which the court held it to be just and equitable to deny to the vendor the enjoyment of a forfeited deposit. Attempted classifications within this general category will tend only to obscure rather than to elucidate the approach to the exercise of this statutory discretion. The onus of proof lies on the purchaser [paragraph 14]. Having found in favour of the purchaser on this ground, His Honour considered it unnecessary to deal with the other grounds listed above. His Honour did, however, make some concluding comments which might be considered by those practitioners who enter into contracts involving rebate arrangements [at paragraph 17]: 17. The last argument of the plaintiff is that the discretion ought be exercised against the first defendant on a lack of clean hands basis: the inflation of the purchase price by $10,000 per lot was to deceive lenders. Whatever may be said of this conduct, which cannot be characterised as worthy, it did no harm to the plaintiff, which willingly participated in it for its own purposes (bearing in mind my acceptance of Mr Sayer’s version of the conversation of January 1998). I do not propose to refrain from exercising my discretion in the first defendant’s favour on this ground. Subsequently His Honour found the personal defendants not liable as indemnifiers: [2001] NSWSC 611. On 7 October 2003 the High Court handed down two important decisions on the principles governing whether relief against forfeiture should be available where a purchaser defaulted in performing an essential obligation under a contract. The cases are Romanos v Pentagold Investments Pty Ltd [2003] HCA 58 and Tanwar Enterprises Pty Ltd v Cauchi [2003] HCA 57. In each case the purchaser was unsuccessful. In each case there was a joint judgment by Gleeson CJ, McHugh J, Gummow J, Hayne J and Heydon J. Kirby J and Callinan J delivered separate, concurring judgments. A consideration of progress and reasoning in the courts below is useful. In Tanwar Enterprises Pty Ltd v Cauchi (2002) NSW Conv R ¶55-994 (NSWSC per Windeyer J); Tanwar v Cauchi (2003) NSW Conv R ¶56-048 (NSW Court of Appeal) the contract provided for a fixed but non-essential – 27 – When Conveyances Go Wrong Tony Cahill completion date with which the purchaser did not comply. The contract was first terminated by the vendor for non-completion by the purchaser in August 2000, but following negotiations the contract was reinstated. The parties entered into a deed varying the original contract. The deed relevantly provided: 1. The Notice of Termination dated 20th August, 2000 is withdrawn. 2. Completion of the sale to take place by 4.00 pm on Monday 25th June, 2001, time of the essence. 3. The Purchaser will pay to the Vendor on completion the moneys as set out in the annexed settlement statement (after making adjustments for outgoings). ... 6. The Purchaser acknowledges that the contents of this Deed are a final arrangement to complete the sale of the Property. If the Purchaser does not complete the sale in accordance with the provisions of this Deed the Purchaser will: (a) forfeit all moneys paid pursuant to the Contract for Sale and acknowledges the Vendor’s rights under clause 9 of the Contract for Sale; (b) withdraw any caveat against the property; (c) not commence any Court proceedings to dispute the Vendor’s termination of the Contract for Sale. The parties agreed to settle at the Office of State Revenue on the afternoon of the last day available, Monday, 25 June 2001. Tanwar’s sources of finance included foreign sourced funds to be provided by second mortgagees. Mr Cormack, of Corrs Chambers Westgarth, acted for those second mortgagees. He attended at the settlement meeting and informed the parties that his clients were unable then to proceed. Earlier on 25 June, Mr Cormack had become aware that the Singapore authorities were conducting additional checks on certain international money transfers; hence the delay. However, he told those present that the funds should be available on the next day. That came to pass and, on 26 June, the funds were received from Singapore into a trust account conducted by Mr Cormack’s firm. On that morning, Tanwar’s solicitor informed the vendors’ solicitor of this and that settlement could proceed. However, the vendors already had given instructions to terminate the contracts and confirmed those instructions when informed that the second mortgagees were now in a position to – 28 – When Conveyances Go Wrong Tony Cahill proceed to settlement. Thereafter, on the afternoon of 26 June, notices of termination were issued. At first instance, and in the Court of Appeal, the purchaser failed in an application for relief against forfeiture, and also in an application for a refund of deposit under section 55(2A) Conveyancing Act 1919. The purchaser appealed to the High Court. In Pentagold Investments Pty Limited & Anor v Romanos & Anor [2001] NSWSC 269; (2001) NSW ConvR 55-987; [2001] ACL Rep (Issue 6) 355 NSW 32 (Windeyer J, 12/4/01); [2001] NSWCA 425 (Court of Appeal, 12/12/01), Pentagold contracted to purchase three properties from Romanos. Clause 17 (presumably a Special Condition 17) of the contracts provided that a ten per cent deposit was to be paid to the purchaser, as to one-tenth upon exchange of contracts and as to nine-tenths upon approval of a Development Application for the site. Special Condition 19 provided that the purchaser would obtain Council approval for the erection of units on the properties. Clause 2 of the standard contract (which appears to be the 1996 edition) provided, inter alia, that time was essential in the payment of the deposit. The combined effect of Special Condition 9 and Clause 9 was to ensure that, in the case of a breach of the contract by the purchaser, the vendor was entitled to retain a ten per cent deposit. Contracts were exchanged on 15 September 1999 and one tenth of the deposit was paid then. The development application was approved on 24 November 2000, and the purchasers received notice of this on 1 December. Windeyer J found that between 1 and 11 December, there were discussions between the parties about release of part of the deposit in order to enable the vendor to purchase another property. On 19 December 2000, without having given any prior notice, the vendors gave notice to the purchasers terminating the contracts. On 20 December, the purchasers paid the balance of the deposits. The purchasers filed summons seeking declarations for specific performance of the contracts and relief against forfeiture. The trial judge dismissed the summons, but, pursuant to s55(2A) of the Conveyancing Act 1919, ordered the vendors to refund to the purchasers the whole of the deposit. During the course of hearing, the purchasers sought to have a letter written by their solicitor admitted into evidence to demonstrate that the failure to pay was the result of inadvertence, and to re-open their case so as – 29 – When Conveyances Go Wrong Tony Cahill to call the solicitor to give evidence on this point. The trial judge admitted the letter only as proof of the fact that it was written, and refused leave to re-open. The purchasers challenged the finding that a claim for relief against forfeiture had not been made out, and the decision on admission of the solicitor’s evidence. The vendors cross-appealed against the trial judge’s decision in relation to the Conveyancing Act. The Court of Appeal by majority (Sheller JA, Mason P agreeing; Giles JA in dissent) upheld the appeal, and found that relief against forfeiture should have been granted. The Court of Appeal further found that the trial judge had correctly exercised his discretion in not allowing the purchasers to reopen the case. The first question considered by Windeyer J was whether there was a breach of contract. The purchasers knew of the approval at about 5 pm on Friday 1 December 2000. His Honour considered (and this was not challenged on appeal) that the reference to payment “upon” notification of the approval must mean that the purchasers had to pay the balance of deposit within a practicable time of notification – so payment during the following business day would not have put the purchasers in breach. (Having said that, the provision in the contract about the time for payment of the balance of deposit may better have been expressed by nominating a specific number of days – and a time – following the purchasers becoming aware of the approval). The appeal contained a detailed analysis of the nature of a deposit. Reference is made to decisions such as Brien v Dwyer (1978) 141 CLR 378 – CA at 20-21. The main issue of the appeal was the availability of relief against forfeiture. The Court of Appeal analysed the principles in the High Court decisions of Legione v Hateley (1983) 152 CLR 406 and Stern v McArthur (1988) 165 CLR 489, among other cases. From these cases, the Court of Appeal usefully summarised the principles to be considered in relation to applications for relief against forfeiture. I quote from the judgement: 36. From these citations these material statements of principle can be derived: (a) on principle there is no reason why the grant of relief against forfeiture as preliminary to an order for specific – 30 – When Conveyances Go Wrong Tony Cahill performance should not be made if it will not cause injustice but will on the contrary prevent injustice; 37. (b) if there be fraud, mistake, accident, surprise or some other element which would make it unconscionable or inequitable to insist on forfeiture of the purchaser’s interest under the contract because he has not performed in strict accordance with its terms there is no injustice to the innocent party in granting relief against forfeiture by means of specific performance with or without compensation; (c) fraud, mistake, accident or surprise do not exhaust the scope of unconscionable or unconscientious behaviour; (d) where it is possible to state that the object of the transaction and of the insertion of the right to forfeit is essentially to secure the payment of money fraud, accident, mistake or surprise are not the basis of the jurisdiction and the circumstances which will suffice to support the grant of relief, despite the breach of an essential term, are not confined and it is not necessary for the party claiming relief to show unconscionable or unconscientious behaviour of an exceptional kind; (e) the entitlement to relief is not conditional upon unconscionable conduct on the part of the person against whom it is sought; (f) the general underlying notion is that a person should not be permitted to use or insist upon his legal rights to take advantage of another’s special vulnerability or misadventure for the unjust enrichment of himself. It is clear enough in the present case that cl 2, and particularly 2.3 and 2.5, of the contract were provisions designed to secure the payment of money or, put another way, secure a stated result, namely the payment of the deposit. The question is whether relief against the consequent forfeiture is dictated not by questions of unconscionability but by the function of the deposit, the fact that no notice of intended termination was given and the fact that the outstanding deposit was paid on the day after the vendors gave notice terminating. The further question is whether the answer is affected by the purchasers’ conduct. Was the deposit deliberately withheld or was payment overlooked? The Court found that, on the evidence before the trial judge, the last question could not conclusively be answered. The Court considered that the purpose of the forfeiture provision was to secure the payment of the deposit, and so once that payment was made, the object of the provision was achieved, and the vendor would suffer no loss if relief against forfeiture was granted [per Sheller J, at 47]. – 31 – When Conveyances Go Wrong Tony Cahill His Honour continued [at 49-53]: 49. The consequence of relief against forfeiture is to allow the purchasers their declaration for specific performance. By that the vendors obtain what they contracted for leaving aside any entitlement they may have for damages. The full deposit was paid by 20 December 2000. To refuse such relief would leave the vendors with land, which no doubt has increased in value and which now has the benefit of the development approval, and with the whole of the deposit. An additional reason why relief should be granted arises out of the circumstances in which the contract was terminated more than a fortnight after the breach by the purchasers of the essential term requiring the deposit to be paid on 4 December, and without any notice to the purchasers at that late point that the vendors proposed to rely on the breach unless the full deposit was paid within a reasonable time. ... 53. [I]n the present case the date, 4 December, on which Windeyer J found that the deposit should have been paid, had passed without any immediate notice of rescission. In my opinion, the failure of the vendors, after that date had passed, before terminating to give notice that non-payment within a specified reasonable time of the balance of the deposit would lead to termination is another factor which requires that relief be granted … The dissenting judge, Giles JA would have refused relief against forfeiture and would have refused the order under section 55(2A). From that decision the vendor appealed to the High Court. The appeal was upheld. A critical issue in Tanwar was the entry into the supplemental deeds. In a sense, the decision in Romanos is more instructive in the light of the differing views at various levels of the judicial hierarchy. The joint judgment in each case makes it clear that there will only be limited circumstances in which relief against forfeiture will be granted. In particular, a delay in receipt of funds as happened in Tanwar will not be sufficient grounds. A further illustration of the relevant factors in an application for relief against forfeiture (albeit in an urgent interlocutory matter) is the decision of Hamilton J in Montano Property Development Pty Ltd v 2-8 Property Pty Ltd [2002] NSWSC 435. In this case, interlocutory relief was granted to the plaintiff / purchaser arising out of the termination (and the immediate aftermath) of a contract for the sale of a $3 million property at Strathfield. The deposit was – 32 – When Conveyances Go Wrong Tony Cahill $140,000. The notice of termination on behalf of the vendor was faxed at about 5 pm on a Friday afternoon. The key factor in the grant of interlocutory relief was the behaviour of the vendor and its representatives in the period immediately following the sending of that fax. To quote from the judgment of Hamilton J, at paragraphs [3] to [5]: 3. The plaintiff’s solicitors did not actually see the notice of termination until the morning of Monday, 6 May 2002. During the weekend and on the Monday various representations were made to the plaintiff or its solicitors to the general effect that the sale should be treated as ongoing, although upon some conditions. In particular, the evidence shows that on the Monday morning it was represented to the plaintiff’s solicitors that the sale could continue, provided it was completed on Wednesday, 8 May 2002 and provided $20,000 was paid forthwith to the defendant. A cheque for $20,000 was delivered promptly, but it was then announced for the first time that what was required was a bank cheque, which should be available by noon. Bank cheques had to be obtained from Camden and could not be obtained by noon. It was represented that the sale could still continue, provided that they were made available later in the day. When they were brought from Camden in the afternoon the evidence appears to show that the plaintiff’s representatives were kept waiting in the defendant’s solicitor’s office, and only after some time told that the client now for the first time said that it would not accept the bank cheques and that the property had already been resold at 3.30 pm to another purchaser. This account of events in general terms is not only deposed to on behalf of the plaintiff, but is confirmed by a note made by the defendant’s solicitor’s conveyancing clerk, which has been put into evidence. 4. Although the statement that contracts had been exchanged with another purchaser at 3.30 pm on the Monday were repeated in a letter from the defendant’s solicitor’s firm, it appeared on the hearing before me that no new contract had in fact been exchanged up to the time of the hearing. The evidence at the hearing did not reveal the identity of the proposed new purchaser, the price of any new sale, or the terms of or state of the negotiations for that new sale. 5. On the basis of these events Mr McAvoy, of counsel for the plaintiff, put to me that the plaintiff had an arguable case for relief on a number of bases. Without dealing with all of Mr McAvoy’s contentions, or going into any of them in any detail, the case sought to be made out was that the defendant was in those circumstances estopped from relying upon the notice of termination. There was claimed to be an estoppel by representation or alternatively an estoppel by convention. I do not accept Mr McAvoy’s submission that the entire loss of bargain was a detriment shown to flow solely from the events of the Monday, but nonetheless it seems to me that there is an arguable – 33 – When Conveyances Go Wrong Tony Cahill case in favour of both an estoppel by convention and an estoppel by representation. A recent instructive case on the requirement that a party issuing a Notice to Complete be ready at the appointed time is Castle Constructions Pty Limited v Fekala Pty Limited [2002] NSWSC 76. The plaintiff, Castle Constructions Pty Limited, as purchaser and the defendants as vendors, entered into a contract on 28 June 2001 for the purchase and sale of property 7 Rowe Street, Eastwood. The (nonessential) due date for completion was 9 August 2001. The vendors were selling as mortgagees of the property exercising their power of sale under mortgage. Castle Constructions claims to have terminated the contract because the vendors did not complete in accordance with the requirements of a notice to complete served by the vendors. The plaintiff sought a declaration as to its proper termination and an order for the return of the deposit and damages. The defendant, by way of cross-claim, sought specific performance of the agreement. The plaintiff was successful (and an appeal against that decision was dismissed by the Court of Appeal on 7 August 2002). Unhappily, one of the 37 registered proprietors named as vendors in the contract died some two months before the date of the contract. Probate was granted about a week prior to exchange, and the executor was registered by transmission in about early August 2001. The contract had been signed on behalf of the vendors by their solicitor “as agent for the vendors”, which in part explains why the death of a co-vendor did not come to light earlier. The sequence of events leading up to the completion date – nominated in a notice to complete issued by the vendor – is critical, and is set out in Windeyer J’s judgment (at paragraphs [6] to [13]: 6. On 19 July 2001 Mr Carter, who was the solicitor acting for the vendors, wrote to Mr Germanos, the solicitor for Castle Constructions. That letter included the following: We look forward to your requisitions on title together with the memorandum of transfer in due course, bearing in mind that we have to obtain the signatures of numerous mortgagees, some of whom is (sic) interstate and some of whom live in the country. 7. On 7 August 2001 Mr Carter wrote again to Mr Germanos noting that the transfer document had not been provided and then saying: – 34 – When Conveyances Go Wrong Tony Cahill As we mentioned in our letter of 19 July, the transfer document will have to be executed by numerous mortgagees and accordingly require the transfer document as a matter of urgency. 8. On 14 August 2001, Mr Carter served a notice to complete, fixing 3.00 pm on 29 August as the time and date for completion making time of the essence as to both time and date. 9. The solicitor for Castle Constructions responded to this denying the ability to give the notice but this was not pursued other than to make a claim for compensation from the vendor for fixtures removed. On 27 August Mr Germanos forwarded to Mr Carter a draft settlement statement and a form of transfer for execution. Later that day he sent an amended transfer or more precisely amended annexures which contained the names of the vendor mortgagees and execution clauses for each of them. He did this stating that he had become aware that one mortgagee holding his interest jointly with his wife had died and notice of death registered and that the interest of Mrs Colburt now stood in the name of her executors. In fact the notice of death had been registered prior to the contracts being entered into at the auction sale, although the deceased joint holder was shown as one of the mortgagees but not as a vendor. This was a mistake of Mr Germanos, but the information as to the estate of Mrs Colburt was not due to any mistake of his. 10. Mr Carter, for the vendors acknowledged the letter by fax transmission on 27 August and gave directions as to payment of the balance of the settlement moneys apparently being satisfied with the purchaser’s figures. There was some further correspondence on 28 August about those figures and a claim for compensation and it is apparent that Mr Germanos accepted the claim by Mr Carter for interest. 11. By a separate letter dated 28 August Mr Carter wrote to the purchasers care of their solicitors referring to the notice to complete and then saying: We hereby advise that we waive the requirement for your client to complete at 3.00 pm on Wednesday 29 August 2001 at the offices of Nugent Wallman & Carter, solicitors at 388 Edgecliff Road, Woollahra. The vendors now require you to complete the contract for sale of land at 7 Rowe Street Eastwood NSW being Folio Identifier 10/785746 at 3.00 pm on Wednesday 12 September 2001 at the offices of Nugent Wallman & Carter at 388 Edgecliff Road, Woollahra. We note that time will not cease to be of the essence. In the event that you fail to complete at that time, the vendors will regard themselves as entitled to terminate the said contract for sale. – 35 – When Conveyances Go Wrong Tony Cahill 12. Mr Germanos attended for settlement at 11.55 am on 29 August at the offices of the vendors’ solicitors. He had with him the necessary cheques and he had instructions to settle. Mr Carter said that the vendors were not ready: they had not signed the transfer and he had extended the settlement date. Mr Germanos said that this could not be done unilaterally and Mr Germanos disagreed. The bank cheques were produced for inspection by Mr Carter and after that Mr Germanos left the office. He returned again at 2.55 pm and once again Mr Carter said that the vendor was not able to settle and would not be able to settle that day. On return to his office after 3.00 pm Mr Germanos sent a letter giving notice of termination. 13. It took Mr Carter until to 11 September to have the transfer signed by all the necessary vendors. On that basis it seems that the vendors would have been able to settle on 12 September 2001 if the notice purporting to extend or vary the completion date was effective. His Honour held: The vendor was bound by the terms of the notice to complete issued on the vendor’s behalf. In particular, a party issuing a notice cannot unilaterally extend the notice. The failure of the purchaser to submit a transfer on time did not excuse the vendor from the obligation when issuing a notice to be able to settle at the appointed time. The failure of the vendor to supply title particulars to allow the purchaser to prepare a transfer was a contributing factor in this case. The issue of the notice effectively waived the purchaser’s late compliance. A prudent practitioner with multiple vendors should have prepared and had executed a transfer in sufficient time. The decision of Windeyer J was upheld on appeal: Fekala Pty Ltd v Castle Constructions Pty Ltd [2002] NSWCA 297. The remaining matter for resolution was an inquiry into the damages sustained by the purchaser. In Castle Constructions Pty Limited v Fekala Pty Limited & Ors [2004] NSWSC 672, Berecry AM assessed the damages sustained at $3,698,000 (at [38]). However, the failure of the purchaser to take all reasonable steps to mitigate its losses by, for instance, failing to take up the opportunity to purchase an alternative site at Cammeray, disentitled the purchaser to any damages (at [75] to [78]). The Acting Master further held that the failure of the purchaser to take up the vendors’ offer to complete after the termination had occurred was not unreasonable, given that one of the mortgagors had threatened litigation arising out of the – 36 – When Conveyances Go Wrong Tony Cahill aborted sale (at [61] to [62]). In an appeal from the Acting Master’s decision (Castle Constructions Pty Ltd v Fekala Pty Ltd and Ors [2005] NSWSC 642), Palmer J considered that the key issue was not mitigation of damages, but causation. His Honour observed (at [48] to [52]): 48 In my opinion, Castle’s loss of the profits of the Eastwood Property venture was not at all caused by the fact that Fekala was, for a matter of days, unable to procure all necessary signatures on the Memorandum of Transfer. Castle had by that time decided that the venture was too risky; it had tried, unsuccessfully, to persuade Fekala to release it from the contract. When the opportunity arose for Castle to escape the contract because of Fekala’s temporary difficulty in obtaining all of the co-mortgagees’ signatures, Castle seized that opportunity with alacrity and terminated the contract. Thereafter, it resisted attempts by Fekala to procure it to continue with the acquisition. 49 In those circumstances it is clear, in my opinion, that whatever loss of profits Castle may have suffered from not proceeding with the Eastwood Property venture was caused, not by Fekala’s breach of contract in failing to deliver an executed transfer on time, but rather by Castle’s independent decision that it did not wish to proceed with the venture at all. To use the words of Robert Goff J in Koch, the decision of Castle not to proceed with the contract was an independent decision, independent of the wrongdoing but taking place in the context of a pre-existing breach of contract by Fekala. The loss of the profits of the venture did not, therefore, arise out of, nor was it in any real sense caused by, Fekala’s breach of contract. 50 In my opinion, an innocent party to a contract cannot claim from the contract-breaker damages for the loss of profits from a transaction which the innocent party chose not to undertake for its own business reasons and which the breach of contract gave it an opportunity to avoid. Put another way, when Fekala breached the contract, Castle chose not to proceed with the venture because of all of the commercial risks involved. Now, Castle seeks by way of damages for breach of contract the profits of that venture, freed of all of the commercial risks. In popular parlance, that is called trying to eat your cake and have it too. Such an endeavour has the same result in the law as it does in real life. 51 The only damages flowing from Fekala’s breach of contract in failing to complete on 29 August 2001 which Castle was properly entitled to recover were, as Fekala submitted, legal and architects’ costs and expenses thrown away by the termination of the contract or loss of bargain damages equal to the difference between the contract price of the Eastwood Property and its market price as at the date of breach. However, Castle chose not to claim these heads of damages and led no evidence as to the market value of the Eastwood Property as at the date of breach of the contract. The Acting Master was not able, therefore, to assess damages under these heads. – 37 – When Conveyances Go Wrong Tony Cahill Orders 52 For the reasons which I have given, I respectfully differ from the grounds upon which the Acting Master held that Castle was not entitled to damages for loss of profits. I do not think that this is a case in which the purchaser has failed to mitigate its damages for loss of profit flowing from a breach of contract. Rather, I think that it is a case in which the breach of contract did not produce the loss of profit for which the purchaser contends. The purchaser’s appeal was dismissed. The purchaser then unsuccessfully appealed to the Court of Appeal; Castle Constructions Pty Limited v Fekala Pty Limited & Ors [2006] NSWCA 133; (2006) 65 NSWLR 648. The majority (Mason P, with whom Beazley JA agreed) agreed with the Acting Master that the purchaser failed to mitigate, but relied not on the failure to purchase the alternative property but rather on the failure to complete with the vendor of the Eastwood property (at [54] to [56], [80] to [83]). Bryson JA would have dismissed the appeal on the basis of the finding by Palmer J that the loss of profits suffered from not proceeding with the original contract was not caused by the breach but by the purchaser’s independent decision that it did not wish to proceed with the venture at all (at [98] to [99]). For a case considering the formal requirements of a valid notice to complete, which considered, among other cases, the Fekala litigation, see Tuedwell Pty Ltd v J C Craig Constructions Pty Ltd [2003] NSWSC 450 (23/5/03 per Palmer J). Contracts were exchanged on 10 September 2002. The (non-essential) date for completion was 19 November 2002. The purchasers were not ready. A notice to complete issued on behalf of the vendor on 20 November with the due date for completion 4 December. By letter of 2 December the purchaser’s conveyancer denied the validity of that purported notice because 14 days was not a reasonable time for compliance. This contention was rejected by the vendor’s solicitor by letter of 3 December, which went on to state: However, in good faith and to afford your client further time to complete but without prejudice to my client’s rights under the Notice and otherwise for your client’s breach, my client agrees to vary the Notice by extending the time for completion under the Notice to provide that completion is to take place on or before 3.00 pm on Friday 20 December 2002. Time is and remains of the essence. By letter of 19 December the purchaser continued to deny validity of the notice. No settlement occurred on 20 December, and on 23 December the vendor terminated the contract. – 38 – When Conveyances Go Wrong Tony Cahill On the issue of the reasonableness of time for compliance, His Honour found for the vendor (at [13] to [16]): 13 While the reasonableness of the time for completion given in a notice to complete depends upon the particular circumstances of the case, it is, generally speaking, accepted that fourteen days is the norm: see, for example, Castle Hill Tyres at 14,964 per Young J (as his Honour then was). In Sindel v Georgiou (1984) 58 ALJR 515, at 518, the High Court, while referring to a case in which the circumstances justified a six day notice to complete, said that strong circumstances must be shown to justify the giving of a notice to complete which allows less than fourteen days for completion. 14 In the present case, the First Defendant had already had seventy days to complete the contract before the Notice to Complete was given. Clause 15 of the contract entitled the Plaintiff to serve a Notice to Complete once the date for completion had passed, if it was otherwise entitled to do so. Mr Skinner has not submitted that the Plaintiff was not lawfully entitled under the contract to serve a Notice to Complete on 20 November. The Notice required completion by the 85th day after exchange. 15 There was no evidence of any particular difficulty in which the First Defendant was placed by the giving of a notice requiring completion by 4 December. All that Mr Bahar said about the notice, and said repeatedly, was that the time for completion therein given was insufficient. He did not say why it was insufficient, either in his correspondence or in evidence in this case. 16 In those circumstances, bearing in mind that, as the High Court has said in Sindel at 515, it is very much a matter of impression whether the stipulated time for completion given in a notice is reasonable in light of the facts of a particular case. I am of the opinion that the time for completion given in this case was reasonable and that the Notice to Complete was valid. His Honour further held that, in the light of the Fekala case, the purported unilateral extension by the vendor of the time for compliance with the notice to complete was ineffective. However, the termination on 23 December was justified for failure to comply with the time and date originally nominated in the notice. 7 Caveating in disputed conveyancing transactions Most contracts for the sale of a lot in an unregistered plan contain a provision forbidding the lodgment of a caveat by a purchaser. From the vendor’s point of view, such caveats (especially if widely drawn) may impede registration of the subdivision plan, and therefore delay settlement. – 39 – When Conveyances Go Wrong Tony Cahill A further problem is that there is authority for the proposition that where a caveat is lodged over land that is subsequently subdivided, the caveat operates over the subdivided parts – Lintel Pines Pty Ltd v Nixon [1991] 1 VR 287. Does such a clause preclude a purchaser from lodging a caveat? The short answer is, no. A contractual promise not to caveat is the sort of promise which a court would, in an appropriate case, enforce by injunction, and will be relevant in proceedings to remove or extend a caveat (and, of course, will give rise to an action for breach of contract). For a useful discussion of the principles in the context of an off the plan purchase, see Australian Property & Management Pty Ltd v Devefi Pty Ltd (1997) 7 BPR 15,255 and Forder v Cemcorp Pty Ltd [2001] NSWSC 281; (2001) 10 BPR 18,615; (2001) ANZ ConvR 391; (2001) NSW ConvR ¶55-966 – the latter case confirming that the grantee of an option to purchase a lot in an unregistered strata plan has a caveatable interest. Whatever may be the basis of restricting caveats by purchasers prior to registration of a plan of subdivision, it is hard to find any justification in doing so once the plan is registered. A reasonably drafted additional provision would, I suggest, expressly confirm this right. A recent case considering the appropriate precautions to take in purchasing off the plan, and the possible consequences to the lender to the developer, is Broster v Brueckner [2003] NSWCA 281. In July 1997, the respondent entered into contracts to purchase two home units from The Satellite Group (Ultimo) Pty Limited (“Satellite Ultimo”). The purchase was made “off the plan”. He paid the whole of the purchase price to Satellite Ultimo (thereby obtaining the benefit of a much lower price for the unit). At the time of entering those contracts, he obtained a guarantee of performance from the directors and secretary of Satellite Ultimo (one of whom was the appellant in the Court of Appeal). The contract for sale was in the usual 1996 edition of the Standard Form Contract of the Law Society and the Real Estate Institute of New South Wales. Clause 2.8 of the contract provided: If any of the deposit or of the balance of the price is paid before completion to the vendor or as the vendor directs, it is a charge on the – 40 – When Conveyances Go Wrong Tony Cahill land in favour of the purchaser until termination by the vendor or completion. The contract also contained a number of special conditions including Special Condition 5, which provided: It is an essential condition of this contract that the Purchaser shall not lodge any caveat over any part of the title to the land comprising the Site which shall, or may have the effect, of preventing or delaying the registration of the consolidated plan of subdivision, the stratum plan of subdivision, the strata plans of subdivision, the cancellation, release or registration of any 88B instrument or easement or any right or restriction referred to in or contemplated by this Contract, or which might otherwise prevent the registration of any mortgage, discharge of mortgage, or variation of mortgage to which the vendor is a party and which mortgage is, or was associated with, the funding of the acquisition of the site, or the construction on the site of the Building by or on behalf of the Vendor. Satellite Ultimo subsequently mortgaged the land, on which it was proposed to build the home units, to Westpac. Before Westpac took its mortgage, it was informed that the respondent (and numerous other people) had entered into contracts to purchase identified home units in the building. Satellite Ultimo encountered financial problems, and a receiver was appointed to it soon after the building was completed. Westpac has exercised a mortgagee’s power of sale in relation to the two units which Satellite Ultimo had contracted to sell to the respondent. The respondent had failed to protect its security in the units by caveat. The expert evidence on that issue was instructive (at [8]): ... it is the usual practice of ... a solicitor to cause a caveat under the Real Property Act 1900 to be lodged to protect the purchaser’s interest under a contract for sale when there is a delayed settlement, release of the deposit, or a perceived unusual risk. He also says it is the usual practice of such a solicitor to lodge a caveat where a purchaser is acquiring a property, “off the plan”, and for such a caveat to be lodged immediately after exchange of contracts. The trial judge found that a prudent purchaser would have lodged a caveat (at [9]). Evidence was given on behalf of Westpac that “... if there had been a caveat of any description on the property at the time of Westpac making its advance. ... if [the respondent] had lodged a caveat, Westpac would have required it to be removed before any money was advanced, but in – 41 – When Conveyances Go Wrong Tony Cahill consequence of the lodgment of a caveat Westpac would have had clear actual notice of [the respondent’s] rights” (at [12]). As the respondent did not lodge a caveat, the trial judge found, and this was not challenged on the appeal, that Westpac was not bound by any personal equity that required it to recognise the respondent’s interest in the two units. Accordingly, Westpac held title free of the respondent’s interest. The issue on the appeal was whether the finding of the trial judge was correct in finding that the damages to which the respondent was entitled was the amount of damages his Honour awarded against Satellite Ultimo ($579,000), less the contract price of the two units ($275,000), being $304,000. The appeal was dismissed. In the light of the issues raised by Black v Garnock, discussed above, the issues raised by Broster v Brueckner will need careful consideration by vendors, purchasers and financiers. For a case considering the wrongful maintenance of a caveat in a different context, see Marinkovic v Pat McGrath Engineering Pty Ltd [2004] NSWSC 571 (10/6/04 per Palmer J). The subject matter of the sale in Marinkovic was a factory. The building itself was Council approved, but a mezzanine level constructed about two years about completion of the building proper was not approved. Some months after the mezzanine was built, Council wrote to the owner demanding the work be removed within 30 days. The owner wrote to Council stating he was unaware that approval was needed, apologising, and indicating he had ordered a stairway to provide fire safety access as advised by a named Council officer. Council subsequently wrote to the owner in these terms: Council has decided to take no further action in regard to the unauthorised construction of the timber/metal framed storage area within the existing warehouse, subject to satisfactory construction of the egress stairs in accordance with the requirements of ordinance 70 and a satisfactory inspection by Council’s district building surveyor. The inspection took place and the owner heard nothing further. Eight years later the owner exchanged contracts. The deposit was released to the vendor pursuant to a special condition in the contract. After exchange the purchaser made inquiries of the Council about what consents – 42 – When Conveyances Go Wrong Tony Cahill existed. This led to correspondence as set out in the judgment (at [11][12]): 11 On 31 January 2001 the solicitors for the defendant wrote to the solicitors for the plaintiff saying that the mezzanine floor level of the property did not appear to have any record of approval at Randwick Council for construction. The letter said that there had been a pre-contractual representation by the plaintiff that the total area of useable space in the property was 850 square metres, and that the apparently unauthorised construction of the mezzanine floor severely impacted on the character and value of the improvements. The letter continued: We would be pleased if you could urgently provide details of both development approval and building approval for construction of the mezzanine floor level, the availability of which floor space was central to the decision of our client to enter into the contract. We are further instructed that in the absence of evidence of such approvals being produced within seven days of the date of this letter, the instructions of our client are to rescind the contract for breach of an essential precontractual condition upon the basis of which our client entered into the contract. Our client also reserves the right to seek damages. Defendant’s Enquiries Re Approval of Mezzanine Level 12 There appears to have been no response by the plaintiff's solicitor to the letter of 31 January 2001. On 14 February 2001 the solicitor for the defendant wrote again to the solicitor for the plaintiff, saying: Further to our letter of 31 January 2001, our client has made independent inquires at Randwick Council and has been advised that the mezzanine floor level of the above property has been constructed without development approval from the Council. In these circumstances, there has not only been a breach of a pre-contractual representation by the vendor, but there is also a breach of the implied warranty contained in section 52A of the Conveyancing Act and in accordance with instructions from our client we enclose herewith notice of rescission and we require immediate return of a cheque for $79,000 in favour of our clients in return of the deposit. That letter enclosed a Notice of Rescission. There has been no criticism of the legal adequacy of the wording of the Notice. In March 2001, the purchaser lodged a caveat, claiming an interest as purchaser under the contract. – 43 – When Conveyances Go Wrong Tony Cahill In August 2001, each party applied (apparently on the same day) for a building certificate. After requesting and obtaining certification as to fire safety, the Council issued building certificates in November 2001. On 7 December 2001, the vendor entered into a contract to resell the property. The vendor’s solicitors informed the purchaser under the first contract of this development, and sought removal of the caveat. The purchaser wrote to the vendor agreeing to remove the caveat upon payment of the deposit by bank cheque either at or before settlement of the second sale. The subsequent correspondence was interesting (at [26] to [31]): 26 There was no response to that letter until 18 January 2002, when the solicitors for the plaintiff wrote to the solicitors for the defendant, saying that the new sale of the property would settle on 21 January 2002 at 2 pm. Again, the solicitors for the plaintiff threatened that unless they received a Withdrawal of Caveat proceedings would be commenced for removal of the caveat. 27 By letter of 22 January 2002, the solicitors for the plaintiff wrote to the solicitors for the defendant again, saying that settlement had now been fixed for that afternoon at 2 pm. They said: We confirm we are instructed that an amount of $79,000 shall be held in trust and request that you immediately prepare a withdrawal of caveat as it is required by this afternoon at 2 pm. The letter said that if the matter did not settle, they would commence proceedings for withdrawal of the caveat. 28 Then occurred a strange piece of correspondence. On 22 January 2002, the solicitors for the defendant faxed to the solicitors for the plaintiff a document which starts like a letter, under which they put forward a proposal that the amount of $79,000 be retained by the plaintiff on terms that it be held in a controlled moneys account, and paid out only on a joint authority from the clients, or an order of the Court determining the ownership of the funds. The faxed letter becomes blank part-way down the page. This happened because it was a mistake on the part of the solicitors for the defendant to send that letter at all, and they must have realised the mistake in the middle of transmitting the fax, and stopped the transmission. 29 On 22 January 2002, the solicitors for the defendant wrote to the solicitors for the plaintiff saying: We are unable to obtain any additional instructions from our client, which would allow us to provide a withdrawal of caveat on the basis suggested by your firm. We note that the deposit moneys were paid by our client and released to your client, who has used them to his advantage. As our client claims that it validly rescinded the contract for sale, it maintains a claim for the return of the deposit. – 44 – When Conveyances Go Wrong Tony Cahill Your firm has threatened to take proceedings to seek orders for the requirement of the removal of the caveat. On the present evidence available, your client has no proper grounds to obtain such orders. The true issues in this matter can only be resolved by determining the validity or otherwise, of the notice of rescission. Accordingly, we must advise that our client is not prepared to withdraw its caveat. 30 The letter foreshadowed that different instructions might be obtained, but that was the position for the moment. Another letter of 22 January 2002 explained that the earlier facsimile (see para [28] above) had been sent in error, and that it had been intended to be viewed by the defendant for the purpose of instructions. 31 On 23 January 2002 the defendant’s solicitors wrote a further letter, saying that their client was prepared to withdraw the caveat on the basis that the clients entered into a Deed of Release where each party gave up any claims against the other, whereby $70,000 was to be paid to the defendant, and $9,000 paid to or kept by the plaintiff, and that some District Court proceedings, which the defendants were threatening, would not be brought. The withdrawal of caveat was not forthcoming. The re-sale contract was ultimately terminated by the purchaser. The termination was disputed, litigated, and settled on terms favourable to the purchaser. Campbell J held that the purchaser was entitled to rescind (at [45] to [51]). The issue of relevance to this paper was the maintenance of the caveat, and Campbell J held that the purchaser had wrongfully maintained its caveat (at [56] to [62]): 56 … [T]he Court will not permit a caveat to be used as a device for exerting commercial pressure. In such a case the caveat is legitimately lodged in respect of a disputed claim, but forces the registered proprietor to pay out that claim even though it is disputed. The Court has consistently taken the attitude that where the caveat claims an interest in land as security for the payment of money, if the registered proprietor is prepared to put up an alternative security which is commercially adequate, then it will remove the caveat even though the caveat may be completely valid: Kingstone Constructions Pty Ltd v Crispel Pty Ltd (1991) 5 BPR 11,987 at 11,991; Gibson v Co-ordinated Building Services Pty Ltd (1989) 4 BPR 9630; Australian Property & Management Pty Ltd v Devefi Pty Ltd (1997) 7 BPR 15,255 at 15,257. 57 It seems to me that similar principles ought apply to the construction of section 74P. After all, section 74MA sets out what is to happen if a person who wishes to have a caveat removed is able to get to Court and have the Court decide whether it should or should not be removed. Section 74P deals with the situation where a person who wishes to have a caveat – 45 – When Conveyances Go Wrong Tony Cahill removed has requested that it be removed, but for one reason or another has not actually gone to Court to seek enforcement of that request. I see no reason why the test for whether or not the caveat should be removed ought be different under section 74P to that applied under section 74MA. 58 In the present case, the defendant, once it had rescinded the contract, had a clear entitlement to get its deposit back. That arose under the terms of clause 21 of the 2000 Regulation. Clause 21 of the 2000 Regulation, considered by itself, gave only a personal right of action to recover the deposit. 59 Clause 2.8 of the Contract for Sale between the plaintiff and defendant contained a provision that: If any deposit ... is paid before completion to the vendor or as the vendor directs, it is a charge on the land in favour of the purchaser until termination by the vendor or completion, subject to any existing right. That clause covers the present situation, where there has been neither termination by the vendor, nor completion, and confers an equitable charge on the land, for the amount of the deposit. As well, there is a general law doctrine whereby an equitable lien exists for a purchaser’s deposit, where a contract for sale of land goes off without any default on the part of the purchaser: Francombe v Foster Investments Pty Ltd [1978] 2 NSWLR 41 at 57; Whitbread & Co, Limited v Watt [1902] 1 Ch 835; Combe v Swaythling (Lord) [1947] Ch 625. A purchaser’s lien of this kind is a caveatable interest: Ex parte Lord [1985] 2 Qd R 198. 60 Here, the interest which was claimed in the caveat was much wider than the interest which the defendant was legitimately entitled to, of a charge or lien to secure repayment of the deposit. That is not something which seems to have produced any particular consequences, however. 61 The course of negotiation between the solicitors which I have outlined shows that the plaintiff had offered, at a comparatively early stage, to place the deposit into a controlled money account, to await a court determination concerning who was entitled to it. The defendant refused to agree to those terms. Instead, the defendant tried to strike a better bargain for itself, under which the defendant would be able to dispense with any argument about who was entitled to the deposit. Its proposal was that it would get back its $79,000 in exchange for a withdrawal of the caveat (on 18 December 2001), or that it would get $70,000 back plus a release (on 23 January 2002). Each of these bargains which the defendant sought to obtain was more than a court would have required if the matter had gone to Court for an order seeking removal of the caveat. This was implicitly recognised by the defendant on 21 February 2002, when it agreed to the caveat being withdrawn on the basis that $79,000 be paid into a controlled moneys account. It was the proposal which the defendant’s solicitor made to the defendant on 22 January 2002, in the letter part of which was mistakenly faxed to the plaintiff’s – 46 – When Conveyances Go Wrong Tony Cahill solicitor. In these circumstances, I am satisfied that the case has been made out that the defendant, without reasonable cause, refused or failed to withdraw its caveat after being requested to do so. 62 Caveators should be aware that they are playing with fire if they insist on maintaining a caveat when they know that the existence of the caveat is imperilling settlement of a conveyancing transaction, and when they have been offered adequate security for the interest they have in the land. The purchaser under the first contract was ordered to pay compensation under section 74P of the Real Property Act (at [71]). The purchaser received a refund of the deposit plus interest (at [72] to [73]). Each party was required to pay its own costs (at [77]). ***** – 47 –