1st Draft PRE-FESIBILITY STUDY FOR PRODUCTION OF TROUT FISH FARMING (INLAND FISH FARMING) PAKISTAN AGRICULTURE RESEARCH COUNCIL ISLAMABAD MINISTRY OF NATIONAL FOOD SECURITY AND RESEARCH Government of Pakistan www.parc.gov.pk February, 13 2014 1 Table of Contents 1. DISCLAIMER ..........................................................................................................................1 2. PURPOSE OF DOCUMENT ...................................................................................................1 3. INTRODUCTION TO SCHEME ............................................................................................1 4. EXECUTIVE SUMMARY ......................................................................................................2 5. BRIEF DESCRIPTION OF PROJECT ....................................................................................2 6. CRITICAL FACTORS .............................................................................................................3 7. INSTALLED AND OPERATIONAL CAPACITY FOR TROU FISH FARMING ..............3 8. GEOGRAPHICAL POTENTIAL FOR INVESTMENT .........................................................3 9. POTENTIAL TARGET MARKETS .......................................................................................3 10. PRODUCTION PROCESS FLOW ......................................................................................4 11. PROJECT COST AND BENEFIT SUMMARY ..................................................................4 11.1. Project Economics..................................................................................................................... 4 11.2. Project Financing ...................................................................................................................... 4 11.3. Project Cost ............................................................................................................................... 5 11.3.1. Space Requirement ................................................................................................................... 5 11.3.2. Machinery and Equipment ........................................................................................................ 5 11.3.3. Furniture and Fixture ................................................................................................................ 5 11.3.4. Operational and Maintenance cost ............................................................................................ 6 11.3.5. Human Resource Requirement ................................................................................................. 6 11.4. Revenue Generation .................................................................................................................. 6 12. KEY ASSUMPTION ............................................................................................................7 13. USEFUL LINKS ...................................................................................................................8 14. ANNEXURES ......................................................................................................................9 Annexures I: Income Statement ................................................................................................................ 9 Annexure II: Summary Statistics ............................................................................................................ 10 i List of Tables Table 1. Project Economics -------------------------------------------------------------- 4 Table 2. Project financing -------------------------------------------------------------- 4 Table 3. Total Project Cost -------------------------------------------------------------- 5 Table 4. Space requirement and its cost ----------------------------------------------------- 5 Table 5. List of Furniture & Fixture and its cost -------------------------------------------- 5 Table 6. Operational & Maintenance cost -------------------------------------------- 6 Table 7. Human Resource Requirement its cost -------------------------------------------- 6 Table 8. Revenue of the Project ------------------------------------------------------------- 6 Table 9. Key Assumption ------------------------------------------------------------- 7 ii 1. DISCLAIMER This information memorandum is to introduce the subject matter and provide a general idea and information on the subject. Although, the material included in this document is based on data / information generated from experiments and field testing by a team of relevant scientists; however, it is based upon certain assumptions which may differ from case to case. The contained information may vary due to any change in any of the concerned factors, and the actual results may differ accordingly from the presented information. The PARC and its employees do not assume any liability for any financial or other loss resulting from this memorandum in consequence of undertaking this activity. The prospective user of this memorandum is encouraged to contact qualified consultant/technical expert, especially designated focal person(s) of this enterprise for reaching to an informed decision. 2. PURPOSE OF DOCUMENT The purpose of this document is to facilitate potential investors in Trout Fish Farming Business by providing them with a general understanding of the business, with the intention of supporting potential investors in crucial investment decisions. The project pre-feasibility may form the basis of an important investment decision and in order to serve this objective, the document/study covers various aspects of project concept development, start-up, production, finance, and business management. The need to come up with pre-feasibility reports for undocumented or minimally documented sectors attains greater imminence as the research that precedes such reports reveal certain thumb rules; best practices developed by existing enterprises by trial and error, certain industrial norms and well established research findings that become a guiding source regarding various aspects of business set-up and it’s successful management. Apart from carefully studying the whole document, one must consider critical aspects provided later on, which form the basis of investment decisions. 3. INTRODUCTION TO SCHEME Prime Minister’s Youth Business Loan Program, for young entrepreneurs, with an allocated budget of Rs. 5.0 Billion for the year 2013-14, is designed to provide subsidized financing at 8% mark-up per annum for one hundred thousand (100,000) beneficiaries, through designated financial institutions, initially through National Bank of Pakistan (NBP) and First Women Bank Ltd. (FWBL). Loans from Rs. 0.1 million to Rs. 2.0 million with tenure up to 8 years inclusive of 1 year grace period, and a debt: equity of 90: 10 will be disbursed to SME beneficiaries across Pakistan, covering; Punjab, Sindh, Khyber Pakhtunkhwa, Balochistan, Gilgit-Baltistan, Azad Jammu & Kashmir and Federally Administered Tribal Areas (FATA). 1 4. EXECUTIVE SUMMARY Trout is considered for Inland Fish Farming Business in this pre-feasibility document. This business is proposed to be located primarily in a cold area, having a water temperature range of 05-15 degrees centigrade. All the prospects of Trout i.e. stocking density, nutritional requirement, reproductive performance and management and development of brood stock has been studied at Trout Multiplication Research Station, Mountain Agricultural Research Centre (MARC), Gilgit and Trout Hatchery Madyan, Swat, KPK. After successful experimentation, this species is declared technically feasible for commercial fish farming. The technology of trout culture and breeding are in the phase of extension to the farmers. Farmers are already practicing its culture at their farms. The project can be started at an area of two kanals with 12,000 fish fingerlings of trout for one and half year cycle with survival rate of 90%. Total cost estimate is Rs.2.17 million, with fixed investment of Rs.0.85 million and working capital amounting to Rs.1.32 million. Given the cost assumptions, Net Present Value (NPV), Internal Rate of Return (IRR), Benefit Cost Ratio (BCR) and payback period are Rs.9348988, 54 %, 1.82 and 2.31 years respectively. 5. BRIEF DESCRIPTION OF PROJECT Following key parameters must be addressed as per pre-feasibility study: • Techniques: Different techniques are used for trout farming. However, keeping in view the economical, technical and managerial factors, semi-intensive fish farming, and monoculture technique is suggested for the proposed project. • Location: The business can be initiated in cold area specially Swat, Kaghan, Chitral (KPK), Murree in Punjab, Gilgit Baltistan and Azad Jammu Kashmir having suitable environment, particularly freshwater temperature range between 5-15 oC. • Product: Fish consumption is increasing in Pakistan due to changing food habits and special preferences for high quality white meat. Trout is becoming very popular due to its taste. • Target Market: In addition to local market of the regions where it is produced, major cities, such as Quetta, Karachi, Lahore and Islamabad are the target markets. Moreover, there is an enormous export potential to Middle Eastern countries. • Employment Generation: The proposed project will provide direct employment to two individuals. Financial analysis shows the profitability of proposed business within first year of its operation. 2 6. CRITICAL FACTORS The commercial viability of the proposed project depends on the following factors: • Selection of proper location with water, equipment, and staff play very important role in ensuring the project to run successfully. This species is sensitive to and temperature above 15oC is not suitable for trout culture. • Clean water rich in oxygen is mandatory for this species. • Healthy seedlings must be purchased from reliable/reputed dealers, for the assurance of desired fish species. Incidence of diseases may be monitored on regular basis. • Farm is required to maintain the record of production and management practices for successful marketing and traceability. • Farm should have strong market linkages for effective disposal of produce. 7. INSTALLED AND OPERATIONAL CAPACITY FOR TROU FISH FARMING This pre-feasibility suggests a farm operation on two kanals of land with 12,000 fish for one year of growing cycle (starting with seedlings of 3-4 inches) with survival rate of 90%.This area can be increased from 02 Kanals with double input and output. 8. GEOGRAPHICAL POTENTIAL FOR INVESTMENT The proposed location for establishment of the fish farms will primarily be Northern Areas of Pakistan specially Swat, Kaghan, Chitral, (KPK), Murree in Punjab, Gilgit Baltistan and Azad Jammu Kashmir that provide suitable environment for species (trout) with particularly water temperature. 9. POTENTIAL TARGET MARKETS The marketing of fish follows the traditional distribution channel, through middlemen or wholesalers at farm who identifies potential buyers and negotiate price, or directly to retailers in urban markets. The time spent in transportation, from farm to the retail shop, varies from area to area. Over the years, collection and transportation of fish has improved with the use of loader vehicles. However, greater the distance between farm and consumer, more complicated will be the marketing or distribution system, due to the perishable nature of the product. The key factors in marketing are availability of current market information, quality of fish and supply & demand which will determine the selling price. 3 10. PRODUCTION PROCESS FLOW The overall production cycle for the trout farming comprises of 12 months. In case of fresh seedlings the production cycle will take more time to achieve the desired output. It varies respectively, with the selection of fish (seedlings/fingerlings) size. Keeping in view the economic perspective, it is suggested that fish with 3-4 inches may be used for different ponds which will take 12 months. 11. PROJECT COST AND BENEFIT SUMMARY A detailed financial model has been developed to analyze the commercial viability of Trout Fish Farming under the Prime Minister’s Small Business Loan Scheme. Various cost and revenue related assumptions, along with results of the analysis, are outlined in this section. 11.1. Project Economics All figures in the financial model have been calculated for 12,000 units of fish on 1 kanal of land. The following table shows internal rates of return and payback period. Table 1. Project Economics Description Details Net Present Value (NPV) Rs. 9,348,988 Benefits Cost Ratio (BCR) 1.82 Internal Rate of Return (IRR) 54% Payback Period (years) 2.31 Factors that influence the profitability of Inland Fish Farm are farm management, quality of inputs and environmental factors. 11.2. Project Financing Following table provides details of the equity required and variables related to bank loan; Table 2. Project financing Description Total Equity (10%) Bank loan (90%) Details Rs. 2,163,33 Rs 1,949,700 Mark up to borrower (per annum) Tenure of Loan (Years) Grace Period (years) 8% 8 1 4 11.3. Project Cost Following requirements have been identified for operations of the proposed business and along with details costing (Table 3). Table 3. Total Project Cost Capital Investment Amount (Rs.) Total Capital Cost 850,000 Initial Working Capital 1,316,333 Total Project Cost 2,166,333 11.3.1. Space Requirement Following table gives details of space requirements and its costing for the project under consideration. Table 4. Space requirement and its cost Space Requirement (Sq. ft.) Cost Rs./ Unit Quantity (Nos) Area (Sq. ft.) Office Building cum Store 50,000 01 10x14 Total Cost (Rs.) 50,000 Construction of Ponds and channels Total 250,000 03 01 kanal 750,000 800,000 11.3.2. Machinery and Equipment No machinery/equipment is required for trout fish farming. 11.3.3. Furniture and Fixture Following table provides list of Furniture and Fixture required for Inland Fish Farm. Table 5. List of Furniture & Fixture and its cost Description Furniture and Fixture Quantity (Nos) Lump sump 5 Unit Price (rupees) 50,000 PKR 50,000 11.3.4. Operational and Maintenance cost Following table provides list of consumable requirement for Inland Fish Farm and accordingly cost of all the consumable required items using current prices. Table 6 . Operational & Maintenance cost Description Nos Trout fish Seed* 12000 Fish Feed 6000 kg Land rent 2 kanal Depreciation cost Utility Bills Communication Charges Miscellaneous (cash in hand) Total *Madyan Trout Hatchery Swat/MARC, Gilgit Unit Price (PKR) 30 100/kg 20000/Kanal 1000/month 500/month - Total (PKR) 360,000 600,000 40,000 8333 12000 6000 50000 1,076,333 11.3.5. Human Resource Requirement The table below provides details of human resource required to manage basic fish farm. The staff salaries are estimated according to the market trends. However, these requirements and pay scales may vary area to area. Table 7. Human Resource Requirement its cost Description No. of Employees Labour 11.4. Salary/person/ month 10,000 2 Total salary per year 240,000 Revenue Generation Final product of Inland Fish Farm is fish ready for sale in market that will generate revenue. The capacity of farm is 12,000 units of fish for first year sell price as per market Rs. 1000. Table 8. Revenue of the Project Survival Product Unit @90% Fish 12,000 10,800 Average Weight of fish 0.25 kg Total Sales Revenue First Year Sales Production Price (Kg) (Rs./Unit) 2700 1000 2,700,000 6 First Year Revenue (Rs) 2,700,000 12. KEY ASSUMPTION Table 9. Key Assumption* Particulars Assumption Sales Price Growth Rate 10% per year Increase in cost of raw material 10% per year Increase in utilities 10% per year Debt/Equity Ratio 90:10 Building & Ponds 5% Office furniture & fixture 5% Loan Period 8 years Grace Period 1 year Loan installments Annually Financial charges (interest rate) 8% * Average inflation rate of past 10 years is used as proxy of input and out prices growth rate. (Source: Economic Survey of Pakistan) 7 13. USEFUL LINKS Resource/focal Person PSO/Program Leader Aquaculture and fisheries program, Livestock research institute, National Agriculture Research Center, Islamabad Phone: 0518443868 OR 0519255331 Email: afzal_afri@hhotmail.com Aziz Ahmed, MARC, Juglot, Gilgit Cell: 03468487776, Email: azizglt_73@yahoo.com aqua.ucdavis.edu/DatabaseRoot/pdf/TROUTMAN.PDF www.fao.org 8 14. ANNEXURES Annexures I: Income Statement Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 2,700,000 2,970,000 3,267,000 3,593,700 3,953,070 4,348,377 4,783,215 5,261,536 5,787,690 6,410,823 Seedling Cost 360000 396000 435600 479160 527076 579783.6 637762 701538.2 771692 848861.2 Feeding Cost 600000 660000 726000 798600 878460 966306 1062937 1169230 1286153 1414769 Cost of Goods Sold 960000 1056000 1161600 1277760 1405536 1546090 1700699 1870768 2057845 2263630 Gross Profit Repair & Maintenance 1740000 1914000 2105400 2315940 2547534 2802287 3082516 3390768 3729845 4147194 0 42500 44625 46856.25 49199.06 51659.02 54241.97 56954.06 59801.77 62791.86 Salaries 240000 264000 290400 319440 351384 386522.4 425174.6 467692.1 514461.3 565907.4 Rent 40000 44000 48400 53240 58564 64420.4 70862.44 77948.68 85743.55 94317.91 Utilities Communication charges 12000 13200 14520 15972 17569.2 19326.12 21258.73 23384.61 25723.07 28295.37 6000 6600 7260 7986 8784.6 9663.06 10629.37 11692.3 12861.53 14147.69 8333.333 8333.333 8333.333 8333.333 8333.333 8333.333 8333.333 8333.333 8333.333 8333.333 50000 55000 60500 66550 73205 80525.5 88578.05 97435.86 107179.4 117897.4 155976 155976 138495 119616 99227 77206 53424 27740 0 0 Sub - Total 512309.3 589609.3 612533.7 637993.9 666266.2 697656.3 732502.8 771180.5 814104 891691 Operating Income 1227691 1324391 1492866 1677946 1881268 2104631 2350013 2619587 2915741 3255503 Net Income 1227691 1324391 1492866 1677946 1881268 2104631 2350013 2619587 2915741 3255503 Sales (Revenues) Depreciation Other Office Expenditure Interest on Loan 9 Annexure II: Summary Statistics 0 Period Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 2166333 0 0 0 0 0 0 0 0 0 0 Fixed Cost 850000 0 0 0 0 0 0 0 0 0 Variable cost Total Cost (Fixed + Variable) 1316333 1489633 1635638 1796138 1972575 2166539 2379777 2614209 2871949 3155320 2166333 1489633 1635638 1796138 1972575 2166539 2379777 2614209 2871949 3155320 Interest on loan Total cost inclusive interest payment (Outflow) Revenues from fish production 155976 155976 1384951 119616 99227 77206 53424 27740 0 0 2322309 1645609 1774134 1915754 2071802 2243746 2433201 2641949 2871949 3155320 2,700,000 2970000 3267000 3593700 3953070 4348377 4783215 5261536 5787690 6366459 Salvage value of assets 0 0 0 0 0 0 0 0 0 44,365 Gross Profit (Inflow) Net cash flow (Inflow – Outflow) 2,700,000 2,970,000 3,267,000 3,593,700 3,953,070 4,348,377 4,783,215 5,261,536 5,787,690 6,410,823 377,691 1,324,391 1,492,866 1,677,946 1,881,268 2,104,631 2,350,013 2,619,587 2,915,741 3,255,503 Initial Project Investment -2166333 Payback Period NPV IRR BCR 2.31 Rs. 9,348,988 54% 1.82 10