Determination ActewAGL Distribution ABN 76 670 568 688 Pass through application for Australian Capital Territory Electricity Feed-in Tariff Scheme 2011-12 AER determination| ActewAGL pass through application for ACT electricity feed-in tariff scheme 2011-12 i January 2013 AER determination| ActewAGL pass through application for ACT electricity feed-in tariff scheme 2011-12 ii © Commonwealth of Australia 2013 This work is copyright. Apart from any use permitted by the Copyright Act 1968, no part may be reproduced without permission of the Australian Competition and Consumer Commission. Requests and inquiries concerning reproduction and rights should be addressed to the Director Publishing, Australian Competition and Consumer Commission, GPO Box 3131, Canberra ACT 2601. AER reference: 47276/D12/181643 AER determination| ActewAGL pass through application for ACT electricity feed-in tariff scheme 2011-12 i Contents Contents ........................................................................................................................ ii Shortened forms ..........................................................................................................iii Overview ...................................................................................................................... iv 1 Determination ..................................................................................................... 1 2 ActewAGL’s pass through application ............................................................. 2 3 Assessment approach ......................................................................................... 3 4 Reasons for determination ................................................................................. 7 Appendix A ................................................................................................................. 13 AER determination| ActewAGL pass through application for ACT electricity feed-in tariff scheme 2011-12 ii Shortened forms Shortened form Full title AER Australian Energy Regulator ACT Australian Competition Tribunal ActewAGL ActewAGL Distribution ABN 76 670 568 688 CPI consumer price index DNSP distribution network service provider FiT feed-in tariff FiT scheme ACT Electricity Feed-in Tariff Scheme NEL National Electricity Law NER National Electricity Rules RIN regulatory information notice WACC weighted average cost of capital AER determination| ActewAGL pass through application for ACT electricity feed-in tariff scheme 2011-12 iii Overview On 13 November 2012, ActewAGL Distribution ABN 76 670 568 688 (ActewAGL) submitted a pass through application to the Australian Energy Regulator (AER) in respect of the feed-in tariff (FiT) payments incurred under the Australian Capital Territory (ACT) Electricity Feed-in Tariff Scheme (FiT scheme). In its application, ActewAGL proposed a negative pass through amount in 2011–12 of $727 564. The pass through regime allows distribution network service providers (DNSPs) to pass through certain costs to customers, representing the difference between the FiT scheme costs estimated in the determination and the actual costs incurred, subject to certain efficiency standards and other matters assessed by the AER. The AER must assess the application against the requirements in clause 6.6.1 of the National Electricity Rules (NER) and the current AER determination currently applying to ActewAGL.1 In particular, the AER must determine if a pass through event occurred, and if so, determine an approved pass through amount. The AER considers that ActewAGL’s pass through application establishes that a pass through event occurred. The AER notes that ActewAGL is obliged under the Electricity Feed-in (Renewable Energy Premium) Act 2008 (ACT) to incur direct FiT payments. The AER is satisfied that the direct FiT payments incurred by ActewAGL in 2011–12 were paid through the operation of the Electricity Feed-in (Renewable Energy Premium) Act 2008 (ACT) and materially reduced ActewAGL’s costs in providing direct control services in the regulatory control period. The AER is required by the NER to determine the amount of the pass through amount that should be passed through in each remaining year of the regulatory control period. Based upon its assessment of the relevant factors listed in clause 6.6.1(j) of the NER, the AER concludes the approved negative pass through amount for ActewAGL is $727 564 ($Dec 2013). 1 AER, Final Australian Capital Territory distribution determination decision 2009-10 to 2013-14, 28 April 2009, as revoked and substituted in April 2012. See AER, Revocation and substitution of ActewAGL 200914 distribution determination, April 2012. AER determination| ActewAGL pass through application for ACT electricity feed-in tariff scheme 2011-12 iv Therefore, the AER has determined that -$727 564 ($Dec 2013) is the approved pass through amount. This means that in 2013-14 ActewAGL will decrease its approved revenue by $727 564 (a decrease of 0.5% from the determination). For ActewAGL customers the decrease in revenue will be returned back to customers in the form of lower network charges. ACT electricity feed-in tariff scheme The FiT scheme is an ACT Government initiative which commenced on 1 March 2009. It is designed to reward ACT households and businesses that install renewable energy generation technology by paying a premium price for the electricity they generate. The FiT scheme is based on gross generation. For each unit of metered kilowatt hour (kWh) renewable energy generated (solar or wind), eligible customers are paid at a premium rate greater than the retail price they would usually pay to buy the same amount of energy. 2 Eligible customers are guaranteed payment for 20 years at the premium rate in effect at the time their renewable energy generator is connected to a distributor’s network.3 Originally, the FiT scheme was targeted at householders and small business and limited to installations up to 30kW in capacity (referred to as the micro generator category). It was subsequently extended to installations up to 200kW in capacity (referred to as the medium generator category). On 13 July 2011, the ACT Government closed the FiT scheme to both micro and mediumgenerators. This means that customers installing renewable energy generators are no longer eligible for receipt of the ACT feed-in tariff unless they have signed a contract with their installer and paid a deposit no later than 31 May 2011. The FiT scheme premium rates are as follows: 2 ACT Department of the Environment, Climate Change, Energy and Water Fact Sheet ‘Solar pays in Canberra: ACT Electricity Feed-in Tariff Scheme’, March 2011. 3 s. 11 of the Electricity Feed-in (Renewable Energy Premium) Act 2008 (ACT). AER determination| ActewAGL pass through application for ACT electricity feed-in tariff scheme 2011-12 v 50.05 cents per kWh for systems up to 10kW from the commencement of the scheme until 30 June 2010 40.04 cents per kWh for systems between 10kW and 30kW 45.7 cents per kWh for systems up to 30kW from 1 July 2010. Section 6 of the Electricity Feed-in (Renewable Energy Premium) Act 2008 (ACT) makes it a condition of an electricity distributor’s licence that for eligible FiT scheme customers they must: connect a renewable energy generator to the distributor’s network to enable electricity generated by the generator to be supplied to the network; and reimburse the retailer that supplies electricity to the eligible entity’s premises the difference between the amount payable for the electricity generated as set out in subsection (3) and the normal cost of that electricity.4 It is also a licence condition that distributors pass onto eligible customers the additional metering costs in relation to electricity generated by the generator. Structure of determination This determination is structured as follows: 4 Chapter 1 – sets out the AER’s determination on ActewAGL’s pass through application Chapter 2 – sets out ActewAGL’s pass through application Chapter 3 – sets out the AER’s assessment approach Chapter 4 – sets out the AER’s reason for the determination. The level of payment will differ depending upon the category of generator and the date upon which the eligible customer entered into the contract for the installation of a renewable energy generator. AER determination| ActewAGL pass through application for ACT electricity feed-in tariff scheme 2011-12 vi 1 Determination The AER considers that ActewAGL’s pass through application establishes that a pass through event occurred. The AER is satisfied that the direct FiT payments incurred by ActewAGL in 2011– 12 were paid through the operation of the Electricity Feed-in (Renewable Energy Premium) Act 2008 (ACT) and materially reduce ActewAGL’s costs in providing direct control services in the regulatory control period. The AER is required by the NER to determine the amount of the pass through amount that should be passed through in each remaining year of the regulatory control period. Based upon its assessment of the relevant factors listed in clause 6.6.1(j) of the NER, the AER concludes the approved negative pass through amount for ActewAGL’s is $727 564 ($Dec 2013). This means that in 2013-14 ActewAGL will decrease its approved revenue by $727 564 (a decrease of 0.5% from the determination). For ActewAGL customers the decrease in revenue will be returned back to customers in the form of lower network charges. AER determination | ActewAGL pass through application for ACT electricity feed-in tariff scheme 2011-12 1 2 ActewAGL’s pass through application On 13 November 2012, the AER received a pass through application from ActewAGL relating to payments under the FiT scheme. The application seeks the AER’s approval to pass through a negative pass through amount of $727 564 for 2011-12. ActewAGL’s application indicates it incurred $10 225 445 ($June 2012) of FiT payments in 201112. The application indicates that the forecast amount of 2011–12 FiT payments included in the ACT determination was $10 866 637 ($June 2012). ActewAGL submits the difference of $727 564, when adjusted for inflation and the time value of money, is the proposed FiT negative pass-through amount. ActewAGL proposes that this amount be passed back to customers in 2013–14 distribution charges. In its application ActewAGL provides a report from its accounting system. It also confirms that the auditor did not find any errors with the 2011–12 FiT payments during the audit of the statutory accounts. AER determination | ActewAGL pass through application for ACT electricity feed-in tariff scheme 2011-12 2 3 Assessment approach The AER is required to consider a pass through application in accordance with clause 6.6.1 of the NER. 3.1 Relevant regulatory requirements The AER received ActewAGL’s application on 13 November 2012 and, therefore, is applying the NER that applied on this date.5 The clauses of the NER which the AER had regard to when making its determination are outlined in appendix A. In particular, the relevant factors that the AER must take into account when making a pass through determination are set out in clause 6.6.1(j) of the NER: Relevant factors (j) In making a determination under paragraph (d) or (g) in respect of a Distribution Network Service Provider, the AER must take into account: (1) the matters and proposals set out in any statement given to the AER by the provider under paragraph (c) or (f); and (2) in the case of a positive change event, the increase in costs in the provision of direct control services that, as a result of the positive change event, the provider has incurred and is likely to incur until: (i) unless subparagraph (ii) applies – the end of the regulatory control period in which the positive change event occurred; or (ii) if the distribution determination for the regulatory control period following that in which the positive change event occurred does not make any allowance for the recovery of that increase in costs – the end of the regulatory control period following that in which the positive change event occurred; and 5 The AER notes that version 52 of the NER applied during the period in which ActewAGL’s application was received. AER determination | ActewAGL pass through application for ACT electricity feed-in tariff scheme 2011-12 3 (2A) in the case of a negative change event, the costs in the provision of direct control services that, as a result of the negative change event, the provider has saved and is likely to save until: (i) unless subparagraph(ii) applies – the end of the regulatory control period in which the negative change event occurred; or (ii) if the distribution determination for the regulatory control period following that in which the negative change event occurred does not make any allowance for the pass through of those cost savings to Distribution Network Users – the end of the regulatory control period following that in which the negative change event occurred; and (3) in the case of a positive change event, the efficiency of the provider's decisions and actions in relation to the risk of the positive change event, including whether the provider has failed to take any action that could reasonably be taken to reduce the magnitude of the eligible pass through amount in respect of that positive change event and whether the provider has taken or omitted to take any action where such action or omission has increased the magnitude of the amount in respect of that positive change event; and (4) the time cost of money based on the weighted average cost of capital for the provider for the regulatory control period in which the pass through event occurred; and (5) the need to ensure that the provider only recovers any actual or likely increment in costs under this paragraph (j) to the extent that such increment is solely as a consequence of a pass through event; and (6) in the case of a tax change event, any change in the way another tax is calculated, or the removal or imposition of another tax, which, in the AER's opinion, is complementary to the tax change event concerned; and (7) whether the costs of the pass through event have already been factored into the calculation of the provider's annual revenue requirement for the regulatory control period in which the pass through event occurred or will be factored into the calculation of the provider's annual revenue requirement for a subsequent regulatory control period; and 7A the extent to which the costs that the provider has incurred and is likely to incur are the subject of a previous determination made by the AER under this clause 6.6.1; and (8) any other factors the AER considers relevant. AER determination | ActewAGL pass through application for ACT electricity feed-in tariff scheme 2011-12 4 3.2 Assessment approach When assessing ActewAGL’s negative pass through application, pursuant to the NER, the AER must first determine whether a ‘negative change event’ occurred. This assessment is done with reference to the NER and the current AER determination applicable to the applicant ActewAGL (which defines the pass through events which ActewAGL can utilise during the regulatory control period). The AER, as part of this process, also determines the materiality of the proposed past through amount. Under chapter 10 of the NER a negative change event for a DNSP is defined as: a pass through event that materially reduces the costs of providing direct control services. Once the AER determines that a negative change event has occurred it must then determine: 6 (1) the required pass through amount; and (2) taking into account the matters referred to in paragraph (j): (i) how much of that required pass through amount should be passed through to Distribution Network Users (the "negative pass through amount"); and (ii) the amount of that negative pass through amount that should be passed through to Distribution Network Users in the regulatory year in which, and each regulatory year after that in which, the negative change event occurred. The AER makes this determination taking into account those factors set out in clause 6.6.1(j) of the NER (quoted above). 3.3 What the AER considered in making this determination The AER’s determination has been made in accordance with clause 6.6.1 of the NER. In forming its determination, the AER has: 6 considered the application and supporting information it received from ActewAGL NER, clause 6.6.1(g). AER determination | ActewAGL pass through application for ACT electricity feed-in tariff scheme 2011-12 5 considered information provided by ActewAGL on 5 December 2012 in response to an information request from the AER7 7 undertaken its own analysis to verify the information provided by ActewAGL. This additional information related to the methodology ActewAGL used to reconcile the FiT payments identified in its application to those contained in the RIN and the timing of ActewAGL’s application. AER determination | ActewAGL pass through application for ACT electricity feed-in tariff scheme 2011-12 6 4 Reasons for determination The AER is satisfied that ActewAGL’s pass through application establishes that a pass through event occurred. The AER considers the direct FiT payments incurred by ActewAGL in 2011–12 materially reduce ActewAGL’s costs in providing direct control services in the regulatory control period, as required under clause 6.6.1(j)(2A) of the NER. 4.1 Occurrence of a pass through event Chapter 16 of the AER’s Final Australian Capital Territory distribution determination decision 2009– 10 to 2013–14 deals with pass through arrangements. In this determination a ‘Feed-in tariff direct payment event’ is regarded as a specific nominated pass through event. A ‘Feed–in tariff direct payment event’ is defined as:8 Feed-in tariff direct payment event means a change in the total amount of direct feed–in tariff direct tariff payments paid by ActewAGL in respect of the ACT Feed-in tariff scheme. For the purpose of this definition, the change in the amount of direct tariff payments paid by ActewAGL must be calculated as the difference between: (1) the amount of direct tariff payments paid by ActewAGL in each regulatory year of the next regulatory control period, derived from the metered output of generators subject to the scheme, and the applicable feed–in tariff rate applying to the metered output; and (2) the amount of scheme direct tariff payments which were forecast for the purpose of and included in the ACT distribution determination for each regulatory year of the next regulatory control period. Relevant direct tariff payments under this pass through mechanism are those paid through the operation of the Electricity Feed-in (Renewable Energy Premium) Act 2008 (ACT), and any amendments to this Act, or through the operation of a new Act implementing the expected second stage of the scheme applying to larger generators. 8 AER, Final Australian Capital Territory distribution determination decision 2009-10 to 2013-14, 28 April 2009, pp. 131-132, as revoked and substituted in April 2012. See AER, Revocation and substitution of ActewAGL 2009-14 distribution determination, April 2012. AER determination | ActewAGL pass through application for ACT electricity feed-in tariff scheme 2011-12 7 4.1.1 Direct feed-in tariff payments The AER is satisfied that the direct payments incurred by ActewAGL in 2011–12, as set out in its pass through application, arise out of the operation of the FiT scheme. The FiT scheme is established under the Electricity Feed-in (Renewable Energy Premium) Act 2008 (ACT). This legislation makes it a condition of an electricity distributor’s licence that they must connect eligible FiT scheme customers and reimburse the retailer for the electricity generated. 9 4.1.2 Materiality Chapter 10 of the NER defines a negative change event for a distribution network service provider as: a pass through event that materially reduces the costs of providing direct control services. In the AER’s Final ACT distribution determination decision 2009–10 to 2013–14, the AER stated that a pass through event will have a material impact if the costs associated with the event exceed one per cent of the annual smoothed revenue requirement specified in the final decision in the years of the regulatory control period that the costs are incurred. However, the AER also stated that a lower materiality threshold, representing the administrative costs of assessing the application, may be appropriate for specific nominated pass through events.10 The AER notes that the ‘feed-in tariff direct payment event’ falls within this category and, therefore, is subject to a lower materiality threshold. Consistent with the final determination, the AER applied a materiality threshold for a specific nominated event that reflects the administrative costs of assessing the application. As set out in table 4.1 below, the proposed pass through amount equates to approximately 0.5% per cent of ActewAGL’s annual revenue requirement for 2011-12 as determined by the AER. in its 9 s. 6 of the Electricity Feed-in (Renewable Energy Premium) Act 2008 (ACT). 10 AER, Final Australian Capital Territory distribution determination decision 2009-10 to 2013-14, 28 April 2009, p. 130, as revoked and substituted in April 2012. See AER, Revocation and substitution of ActewAGL 2009-14 distribution determination, April 2012. AER determination | ActewAGL pass through application for ACT electricity feed-in tariff scheme 2011-12 8 determination.11 The AER is satisfied that the negative pass through amount of $727 564 proposed by ActewAGL meets the administration cost threshold for specific nominated pass through events. Table 4.1: FiT pass through amounts as a proportion of ActewAGL’s annual revenue requirement for 2011-12 ActewAGL’s proposed FiT Annual revenue Proposed pass through pass through amount requirement for 2011–12 amount as % of ActewAGL’s annual revenue requirement ActewAGL $0.7 $160.6 million 0.5% Source: AER analysis The AER considers the direct FiT payments incurred by ActewAGL under the FiT scheme reduce the costs of providing direct control services. This is because the activities which ActewAGL undertakes in order to comply with its obligations under the FiT scheme relate to direct control services as defined in s. 2B of the National Electricity Law (NEL). For example, ActewAGL undertakes network operation, monitoring and metering activities, as part of the FiT scheme. 4.1.3 Timing of ActewAGL’s application Clause 6.6.1 of the NER requires DNSPs to submit a pass through application to the AER within 90 business days of becoming aware of the occurrence of a negative change event, or alternatively within 90 business days of the positive change event occurring. ActewAGL considers the trigger date for the pass through application to be the date upon which it obtained final metered output data for 2011–12. This date occurs in October 2012 and follows ActewAGL confirming the 2011–12 data from the September 2012 meter reading cycle. ActewAGL maintains that under the definition of ‘Feed-in tariff direct payment event’ contained in the 11 AER, Final Australian Capital Territory distribution determination decision 2009-10 to 2013-14, 28 April 2009, as revoked and substituted in April 2012. See AER, Revocation and substitution of ActewAGL 200914 distribution determination, April 2012, p. 12. AER determination | ActewAGL pass through application for ACT electricity feed-in tariff scheme 2011-12 9 determination, it is necessary to use the metered output to determine the actual FiT payment amount.12 The AER accepts that it is open for ActewAGL to consider that the negative change event occurred in October 2012 when final metered output data for 2011–12 became available. Accordingly, the AER is satisfied that ActewAGL submitted its pass through application within 90 business days of the negative change event occurring. 4.2 Assessment of the pass through amount In considering ActewAGL’s pass through application, the AER took into account those factors set out in clause 6.6.1(j) of the NER. Each of these factors is discussed below. 4.2.1 Matters and proposals set out by ActewAGL The AER reviewed ActewAGL’s application and supporting information. The AER made its determination based on the matters and proposals set out by ActewAGL. 4.2.2 The costs ActewAGL has saved as a result of the pass through event The AER substantiated the actual FiT scheme values used to calculate the negative pass through amount sought by ActewAGL. This was done by checking the proposed pass through amount against the FiT payments reported in ActewAGL’s 2011–12 regulatory information notice (RIN) and additional information provided by ActewAGL. 4.2.3 Time cost of money Clause 6.6.1(j)(4) of the NER requires the AER to take into account the time cost of money based on the weighted average cost of capital (WACC) for the provider. In calculating the pass through amount, the AER has made an allowance for the time cost of money. 12 ActewAGL provided this information to the AER on 5 December 2012 in response to an AER information request. AER determination | ActewAGL pass through application for ACT electricity feed-in tariff scheme 2011-12 10 Time cost of money has been based upon the WACC for ActewAGL, as set out in the AER’s Final Australian Capital Territory distribution determination decision 2009–10 to 2013–14. This is a nominal vanilla WACC of 8.79%.13 The AER applied WACC for 1.5 years as revenue will be recouped, on average, halfway through the year when the adjusted prices apply (i.e. 31 December 2013). 4.2.4 Recovery of costs solely a consequence of the pass through event The AER considers that ActewAGL’s proposed pass through amount only includes incremental costs that are solely attributed to the direct FiT payments it has incurred. ActewAGL’s direct FiT payments have been verified through its RIN for 2011–12. 4.2.5 Whether the costs have already been factored into ActewAGL’s annual revenue requirement In the AER’s Final Australian Capital Territory distribution determination decision 2009–10 to 2013–14, the AER determined that ActewAGL’s FiT scheme forecast operating expenditure for 2011–12 was $10 million ($2008–09).14 ActewAGL’s application identified the difference between the actual direct FiT payments it incurred in 2011–12 and those forecast in the final determination, as being an over recovery of $641 191. ActewAGL is proposing to pass through this difference which, when adjusted for the inflation and the time value of money, is the amount of $727 564. The AER agrees that the difference between the forecast and actual direct FiT payments was not provided for in the AER’s Final Australian Capital Territory distribution determination decision 2009–10 to 2013–14. The AER in its determination considered it appropriate for ActewAGL to recover or return to users any difference between forecast and actual direct tariff payments through 13 AER, Final Australian Capital Territory distribution determination decision 2009-10 to 2013-14, 28 April 2009, p. 109, as revoked and substituted in April 2012. See AER, Revocation and substitution of ActewAGL 2009-14 distribution determination, April 2012. AER determination | ActewAGL pass through application for ACT electricity feed-in tariff scheme 2011-12 11 a nominated pass through event. This was on the basis that the ActewAGL did not have time to test the accuracy of its direct tariff payment forecasts or develop its forecasts with the benefit of actual data.15 4.2.6 Extent the costs are subject of a previous determination made by the AER under clause 6.6.1 of the NER The AER considers that ActewAGL’s proposed pass through amount is not part of a previous pass through determination by the AER under clause 6.6.1 of the NER. In this regard, the AER notes that ActewAGL made a pass through application associated with the occurrence of a feed-in tariff event in November 2011 for a negative pass through amount in the 2010–2011 regulatory year. In December 2011, the AER approved a negative pass through amount of $3 918 484 to be passed through the distribution charges for 2012–13. 4.2.7 Any other factors the AER considers relevant There are no other factors the AER considers relevant in making its determination on the pass through amount. 15 AER, Final Australian Capital Territory distribution determination decision 2009-10 to 2013-14, 28 April 2009, pp. 130-131, as revoked and substituted in April 2012. See AER, Revocation and substitution of ActewAGL 2009-14 distribution determination, April 2012. AER determination | ActewAGL pass through application for ACT electricity feed-in tariff scheme 2011-12 12 Appendix A Excerpt from version 52 of the NER – clause 6.6.1: 6.6.1 Cost pass through (a1) Any of the following is a pass through event for a distribution determination: (1) a regulatory change event; (2) a service standard event; (3) a tax change event; (4) a retailer insolvency event; and (5) any other event specified in a distribution determination as a pass through event for the determination. (a) If a positive change event occurs, a Distribution Network Service Provider may seek the approval of the AER to pass through to Distribution Network Users a positive pass through amount. (b) If a negative change event occurs, the AER may require the Distribution Network Service Provider to pass through to Distribution Network Users a negative pass through amount as determined by the AER under paragraph (g). Positive pass through (c) To seek the approval of the AER to pass through a positive pass through amount, a Distribution Network Service Provider must submit to the AER, within 90 business days of the relevant positive change event occurring, a written statement which specifies: (1) the details of the positive change event; and (2) the date on which the positive change event occurred; and (3) the eligible pass through amount in respect of that positive change event; and (4) the positive pass through amount the provider proposes in relation to the positive change event; and (5) the amount of the positive pass through amount that the provider proposes should be passed through to Distribution Network Users in the regulatory year in which, and each regulatory year after that in which, the positive change event occurred; (6) evidence: AER determination | ActewAGL pass through application for ACT electricity feed-in tariff scheme 2011-12 13 (i) of the actual and likely increase in costs referred to in subparagraph (3); and (ii) that such costs occur solely as a consequence of the positive change event; and (iii) in relation to a retailer insolvency event, of : (A) the amount to which the Distribution Network Service Provider is entitled under any relevant credit support; and (B) the maximum amount of credit support (if any) that the Distribution Network Service Provider was entitled to request the retailer to provide under the credit support rules; and (C) any amount that the Distribution Network Service Provider is likely to receive on a winding-up of the retailer; and (7) such other information as may be required under any relevant regulatory information instrument. (d) If the AER determines that a positive change event has occurred in respect of a statement under paragraph (c), the AER must determine: (1) the approved pass through amount; and (2) the amount of that approved pass through amount that should be passed through to Distribution Network Users in the regulatory year in which, and each regulatory year after that in which, the positive change event occurred, taking into account the matters referred to in paragraph (j). (e) If the AER does not make the determinations referred to in paragraph (d) within 60 business days from the date it receives the Distribution Network Service Provider's statement and accompanying evidence under paragraph (c), then, on the expiry of that period, the AER is taken to have determined that: (1) the positive pass through amount as proposed in the provider's statement under paragraph (c) is the approved pass through amount in respect of that positive change event; and (2) the amount of that positive pass through amount that the provider proposes in its statement under paragraph(c) should be passed through to Distribution Network Users in the regulatory year in which, and each regulatory year after that in which, the positive change event occurred, is the amount that should be so passed through in each such regulatory year. Negative pass through AER determination | ActewAGL pass through application for ACT electricity feed-in tariff scheme 2011-12 14 (f) A Distribution Network Service Provider must submit to the AER, within 90 business days of becoming aware of the occurrence of a negative change event for the provider, a written statement which specifies: (1) the details of the negative change event concerned; and (2) the date the negative change event occurred; and (3) the costs in the provision of direct control services that the provider has saved and is likely to save as a result of the negative change event until: (i) unless subparagraph (ii) applies – the end of the regulatory control period in which the negative change event occurred; or (ii) if the distribution determination for the regulatory control period following that in which the negative change event occurred does not make any allowance for the pass through of those cost savings - the end of the regulatory control period following that in which the negative change event occurred; and (4) the aggregate amount of those saved costs that the provider proposes should be passed through to Distribution Network Users; and (5) the amount of the costs referred to in subparagraph (4) the provider proposes should be passed through to Distribution Network Users in the regulatory year in which, and each regulatory year after that in which, the negative change event occurred; and (6) such other information as may be required under any relevant regulatory information instrument. (g) If a negative change event occurs (whether or not the occurrence of that negative change event is notified by the provider to the AER under paragraph (f)) and the AER determines to impose a requirement on the provider in relation to that negative change event as described in paragraph (b), the AER must determine: (1) the required pass through amount; and (2) taking into account the matters referred to in paragraph (j): (i) how much of that required pass through amount should be passed through to Distribution Network Users (the "negative pass through amount"); and (ii) the amount of that negative pass through amount that should be passed through to Distribution Network Users in the regulatory year in which, and each regulatory year after that in which, the negative change event occurred. AER determination | ActewAGL pass through application for ACT electricity feed-in tariff scheme 2011-12 15 (h) A Distribution Network Service Provider must provide the AER with such information as the AER requires for the purpose of making a determination under paragraph (g) within the time specified by the AER in a notice provided to the provider by the AER for that purpose. Consultation (i) Before making a determination under paragraph (d) or (g), the AER may consult with the relevant Distribution Network Service Provider and such other persons as the AER considers appropriate, on any matters arising out of the relevant pass through event the AER considers appropriate. Relevant factors (j) In making a determination under paragraph (d) or (g) in respect of a Distribution Network Service Provider, the AER must take into account: the matters and proposals set out in any statement given to the AER by the provider (1) under paragraph (c) or (f); and in the case of a positive change event, the increase in costs in the provision of direct (2) control services that, as a result of the positive change event, the provider has incurred and is likely to incur until: (i) unless subparagraph (ii) applies – the end of the regulatory control period in which the positive change event occurred; or (ii) if the distribution determination for the regulatory control period following that in which the positive change event occurred does not make any allowance for the recovery of that increase in costs – the end of the regulatory control period following that in which the positive change event occurred; and (2A) in the case of a negative change event, the costs in the provision of direct control services that, as a result of the negative change event, the provider has saved and is likely to save until: (iii) unless subparagraph(ii) applies – the end of the regulatory control period in which the negative change event occurred; or (iv) if the distribution determination for the regulatory control period following that in which the negative change event occurred does not make any allowance for the pass through of those cost savings to Distribution Network Users – the end of the regulatory control period following that in which the negative change event occurred; and AER determination | ActewAGL pass through application for ACT electricity feed-in tariff scheme 2011-12 16 (3) in the case of a positive change event, the efficiency of the provider's decisions and actions in relation to the risk of the positive change event, including whether the provider has failed to take any action that could reasonably be taken to reduce the magnitude of the eligible pass through amount in respect of that positive change event and whether the provider has taken or omitted to take any action where such action or omission has increased the magnitude of the amount in respect of that positive change event; and (4) the time cost of money based on the weighted average cost of capital for the provider for the regulatory control period in which the pass through event occurred; and (5) the need to ensure that the provider only recovers any actual or likely increment in costs under this paragraph (j) to the extent that such increment is solely as a consequence of a pass through event; and (6) in the case of a tax change event, any change in the way another tax is calculated, or the removal or imposition of another tax, which, in the AER's opinion, is complementary to the tax change event concerned; and (7) whether the costs of the pass through event have already been factored into the calculation of the provider's annual revenue requirement for the regulatory control period in which the pass through event occurred or will be factored into the calculation of the provider's annual revenue requirement for a subsequent regulatory control period; and 7A the extent to which the costs that the provider has incurred and is likely to incur are the subject of a previous determination made by the AER under this clause 6.6.1; and (8) any other factors the AER considers relevant. Extension of time limits (k) The AER must, by written notice to a Distribution Network Service Provider, extend a time limit fixed in clause 6.6.1(c) or clause 6.6.1(f) if the AER is satisfied that the difficulty of assessing or quantifying the effect of the relevant pass through event justifies the extension. retailer insolvency event (l) For the purposes of calculating the eligible pass through amount in relation to a positive change event which is a retailer insolvency event, the increase in costs is the retailer insolvency costs excluding: (i) any amount recovered or recoverable from a retailer or a guarantor of a retailer under any relevant credit support; and AER determination | ActewAGL pass through application for ACT electricity feed-in tariff scheme 2011-12 17 (ii) amounts that the Distribution Network Service Provider is likely to receive on a winding-up of the retailer; and (iii) any costs that are recoverable under a RoLR cost recovery scheme distributor payment determination. (m) The amount the AER determines should be passed through to Distribution Network Users in respect of a retailer insolvency event must be taken to be a cost that can be passed through and not a revenue impact of the event. Excerpt from version 52 of the NER – chapter 10: approved pass through amount In respect of a positive change event for a Transmission Network Service Provider: (a) the amount which the AER determines should be passed through to Transmission Network Users under clause 6A.7.3(d)(2); or (b) the amount which the AER is taken to have determined under clause 6A.7.3(e)(1), as the case may be. In respect of a positive change event for a Distribution Network Service Provider: (a) the amount the AER determines should be passed through to Distribution Network Users under clause 6.6.1(d)(2); or (b) the amount the AER is taken to have determined under clause 6.6.1(e)(1), as the case may be. eligible pass through amount In respect of a positive change event for a Transmission Network Service Provider, the increase in costs in the provision of prescribed transmission services that, as a result of that positive change event, the Transmission Network Service Provider has incurred and is likely to incur (as opposed to the revenue impact of that event) until: (a) unless paragraph(b) applies – the end of the regulatory control period in which the positive change event occurred; or (b) if the transmission determination for the regulatory control period following that in which the positive change event occurred does not make any allowance for the recovery of that increase in costs (whether or not in the forecast operating expenditure or forecast capital expenditure AER determination | ActewAGL pass through application for ACT electricity feed-in tariff scheme 2011-12 18 accepted or substituted by the AER for that regulatory control period) – the end of the regulatory control period following that in which the positive change event occurred. In respect of a positive change event for a Distribution Network Service Provider, the increase in costs in the provision of direct control services that, as a result of that positive change event, the Distribution Network Service Provider has incurred and is likely to incur (as opposed to the revenue impact of that event) until: (a) unless paragraph(b) applies – the end of the regulatory control period in which the positive change event occurred; or (b) if the distribution determination for the regulatory control period following that in which the positive change event occurred does not make any allowance for the recovery of that increase in costs (whether or not in the forecast operating expenditure or forecast capital expenditure accepted or substituted by the AER for that regulatory control period) – the end of the regulatory control period following that in which the positive change event occurred. negative change event For a Transmission Network Service Provider, a pass through event which entails the Transmission Network Service Provider incurring materially lower costs in providing prescribed transmission services than it would have incurred but for that event. For a Distribution Network Service Provider, a pass through event that materially reduces the costs of providing direct control services. negative pass through amount In respect of a negative change event for a Transmission Network Service Provider, an amount that is not greater than a required pass through amount as determined by the AER under clause 6A.7.3(g). In respect of a negative change event for a Distribution Network Service Provider, an amount that is not greater than a required pass through amount as determined by the AER under clause 6.6.1(g). pass through event For a distribution determination - the events specified in clause 6.6.1(a1) For a transmission determination – the events specified in clause 6A.7.3(a1). AER determination | ActewAGL pass through application for ACT electricity feed-in tariff scheme 2011-12 19