Life Cycle Cost Analysis The AMP Initiative Walsh Construction Co

advertisement
6/8/2014
YOUR DATES HERE
Life Cycle Cost Analysis
The AMP Initiative
Walsh Construction Co./WA
Marc Streleski
1
6/8/2014
Outline
•
•
•
•
•
•
What is Life Cycle Cost Analysis?
The AMP Initiative
Relativity of Cost
Renovation Example
New Construction Example
Summary
Life Cycle Cost Analysis
•
Purpose
•
To estimate the overall costs of project alternatives and to select the design that
ensures the facility will provide the lowest overall cost of ownership consistent
with its quality and function.
•
Deliverable ≈ most economical project
•
Most Economical Project ≈ trade between increased capital costs and
lower operational costs.
•
•
•
High Performance Building Envelopes
Energy and Resource Conservation
Increased Durability
2
6/8/2014
AMP Initiative
• Asset Management Preservation
– Method of determining your Most Economical Project
•
•
•
•
Detailed & Integrated Analysis
Applicable Project Types
Focus on Performance
Delivery Methods
Relativity of Cost
$4.7M Renovation
Land & Related Cost
Construction Contract
Construction Contingency
Furnishings
Architect & Engineer
Surveys & Construction Testing
AMP Initiative
Permits & Impact Fees
LIHTC Fees
Construction Loan Fees & Expenses
Construction Loan Interest
Perm Loan Legal & Closing
Perm Financing Fees & Expenses
Insurance, Accouting & Lease Up
Developer Fee-Sponsor
Reserves
Syndication Costs
3
6/8/2014
Relativity of Cost
Total Costs over 50 years - Renovation
Development Costs
Utilities & Garbage
7%
18%
Grounds & Maintenance
Replacement Reserve
16%
Management Off-Site
Management On-Site
Other Operating
Services
Relativity of Cost
$11.6M New Construction
Land & Related Cost
Construction Contract
Construction Contingency
Furnishings
Architect & Engineer
Surveys & Construction Testing
AMP Initiative
Permits & Impact Fees
LIHTC Fees
Construction Loan Fees & Expenses
Construction Loan Interest
Perm Loan Legal & Closing
Perm Financing Fees & Expenses
Insurance, Accouting & Lease Up
Developer Fee-Sponsor
Reserves
Syndication Costs
4
6/8/2014
Relativity of Cost
Total Costs over 50 years – New Construction
21%
Total
Development
Costs
Utilities &
Garbage
Grounds &
Maintenance
28%
13%
Replacement
Reserve
Management OffSite
Renovation
Diminishing Returns?
Savings
100
Existing
X
85
15
0
Energy Star
Baseline Target
(CODE)
(Most Economical
Project)
Extreme
(Passive House)
5
6/8/2014
New Construction
Savings
100
85
Diminishing
Returns?
X
15
0
Energy Star
Baseline
(CODE)
Target
Extreme
(Most Economical
Project)
(Passive House)
Renovation Example
6
6/8/2014
Renovation Example
Renovation Example
7
6/8/2014
Renovation Example
•Estimate
•Integrate Utility Savings
Renovation Example
8
6/8/2014
Renovation Example
Baseline Annual Cost
vs. Target
Renovation Example
•Target is $1.2M more than the Baseline
•Target provides $100K savings annually
9
6/8/2014
Achieving the Target
•
•
•
•
Revise Strategy
Increase Project Budget/Evaluate with Operating Budget Savings
Phase project(s)
Restructure to realize future savings
New Construction Example
Salishan – Tacoma, WA
HOPE VI - Redevelopment
SAL 1,2,3
• Walsh Construction
• Tacoma Housing
Authority
SAL 5
SAL 6
SAL 4
SAL 7
10
6/8/2014
New Construction Example
•
•
•

Designed to perform 30% Better
High Performance Building Envelope First

No Leaks
 Air Barrier

Better Windows

Insulation Above Code:
 R15 Foundation
 R23 Walls (Blown In)
 R25 Rim Joist
 R49 Attic
Better Systems Second

Ductless Heat Pumps

More efficient Appliances

Efficient Fixtures
Field QA/QC
New Construction Example
SAL 7
•
•
•
•
Actual Energy Savings 451,724 KwH
Actual Performance 35% better
Payback ≈ 12 years
Project Lifecycle 100+ years
11
6/8/2014
Summary
•
•
•
•
•
Integration with Master Planning Process
Advanced tool in project planning/design
Flexibility
Does not replace Design Team
Process Yield = Most Economical Project!
12
Download