HP Openview Service Desk - DoIT Project Management Advisor

advertisement
Communication Plan
Project Name:
HP Openview Service Desk Implementation
Project
Disclaimer: This example is based on a real project; however, the content has
been modified and specifics removed (e.g., names, dates, budget amounts).
Prepared By:
Position:
Date:
Version No:
Document Change Control
The following is the document control for the revisions to this document.
Version Number
Date of Issue
Author(s)
Brief Description of Change
1.2.1
mm/dd/yy
Project Manager
Initial Plan
Definition
The following are definitions of terms, abbreviations and acronyms used in this document.
Acronyms or Abbreviations
Definition
CIS
Change Information System
DoIT
HP
PSST
PTE
SOAPI
Division of Information Technology
Hewlett Packard
Project Start-up, Status, & Tools
Professional & Technical Education
mm/dd/yy
Support Organization Asset Procurement Information
Communication Plan Example
Page i
Table of Contents
1. INTRODUCTION ........................................................................................................ 1
2. COMMUNICATION OBJECTIVES .............................................................................. 1
3. COMMUNICATION PURPOSE AND TARGET AUDIENCES ..................................... 1
4. COMMUNICATION MESSAGE AND DELIVERY ....................................................... 2
mm/dd/yy
Communication Plan Example
Page ii
1. Introduction
The purpose of the communication plan is to ensure the Service Desk Implementation project
plan provides relevant, accurate, and consistent project information to project stakeholders and
other appropriate audiences. By effectively communicating the project can accomplish its work
with the support and cooperation of each stakeholder group.
The communication plan provides a framework to manage and coordinate the wide variety of
communications that take place during the project. The communication plan covers who will
receive the communications, how the communications will be delivered, what information will be
communicated, who communicates, and the frequency of the communications.
2. Communication Objectives
Effective and open communications is critical to the success of the project.
The key communication objectives for this project are:
 Promote and gain support for the implementation of Hewlett-Packard’s OpenView Service
desk as a replacement for DoIT’s Change Information System (CIS) and Support
Organization Asset Procurement Information (SOAPI).
 Provide accurate and timely information about the project to the sponsor and stakeholders
3. Communication Purpose and Target Audiences
This section identifies the audiences targeted in this Communication Plan, and the purpose of
communicating with each audience.
Audience
Communication Purpose
HP OpenView Service Desk
Advisory Council
Sponsor
Core Team
DoIT Staff
Project deliverables, Project progress, and project issues
mm/dd/yy
Project plan, project progress, and project issues
Project progress and issues
Impact due to changes to procedures and policies
Communication Plan Example
Page 1
4. Communication Message and Delivery
The following outlines the targeted audiences, the key communication messages to be delivered,
and the method for delivering the information, the communicator, and the frequency of the
delivery.
Audience
Message
Delivery Method
Delivery
Frequency
Communicator
Project Sponsor
Project Plan
Meeting
Bi-weekly
Project Manager
Status Report
Report published in My WebSpace
with DoITnet and PSST link
Meeting
Bi-weekly
Project Manager
Monthly
Project Manager
Report published in My WebSpace
with DoITnet and PSST link
Meeting
Classroom
Bi-weekly
Project Manager
Bi-weekly
Scheduled
Project Manager
PTE & Project
Manager
DoITnet, E-Mail notification,
Service Desk Web Page, DoIT
Connection
1 month prior to
rollout
HP Service
Desk Advisory
Council
Project Plan
Core Team
DoIT Staff
Status Report
Training
Status Report
Announcement
mm/dd/yy
Communication Plan Example
Project Manager
Page 2