agency request for - WisBuild - Department of Administration

advertisement
AGENCY REQUEST FOR
BUILDING COMMISSION ACTION
November 18, 2009
AGENCY:
Department of Administration
REQUEST:
Request authority to:
a) Construct various maintenance and repair projects at an estimated total cost of
$5,612,500 ($5,193,100 PRSB – Facility Maintenance and Repair [Y240] and $419,400
PRSB - Cash); and
b) Permit the DOA – Division of State Facilities (DSF) to adjust individual project budgets.
DSF #
Building & Location
09J3Q Milwaukee State Office Bldg.
819 N. 6th Street, Milwaukee
Project Title
Northeast Exterior
Masonry & Plaza
Repairs
PRSB
$1,020,900
DWD
Agency $
$
-
Total
$1,020,900
PROJECT DESCRIPTION:
This request provides maintenance, repair, renovation and upgrades through the All Agency
Projects Program.
DSF #09J3Q – Milwaukee State Office Bldg – Northeast Exterior Masonry/Plaza Repairs:
The Milwaukee State Office Building is located at 819 N. 6th Street in downtown Milwaukee. It is
a modern, ten-story, office structure with articulated window wall of precast concrete panels. The
facade consists of masonry and glass with mechanically fastened foam insulation and insulcrete
thin coat imbedded with white marble chips. The last cyclical maintenance done on the plazas
and barrier walls occurred in 1991. Currently, there is extensive spalling and failure of brickwork
occurring at the exterior on the building, and on the northeast plaza barrier walls. In addition,
drainage issues on the northeast plaza decks are adversely affecting occupied space below the
deck. The masonry walls adjacent to the plaza have deteriorated to the point they need to be
replaced and proper waterproofing and detailing needs to be preformed. This project provides for
the repair and/or replacement of brickwork and replaces the existing masonry barrier walls with
new stainless steel railing system.
Project budget based upon the October 2009 Condition Report prepared by an A/E consultant.
BUDGET & SCHEDULE:
Budget Line
Construction
A/E Design Fees
DSF Mgmt Fee
Contingency
Moveable Equipment
% for Art - .25%
Totals
Milwaukee
Exterior
Masonry
Project
$
834,000
$
66,800
$
36,700
$
83,400
$
$
$ 1,020,900
Program Approval
Program Approval
A/E Selection
Design Report Completed
Bid Date
Start of Construction
Substantial Completion
Final Completion
Milwaukee 2nd
& 7th Floor
Renovations
Nov-09
Dec-09
N/A
Jun-10
Jul-10
Feb-11
May-11
PREVIOUS BUILDING COMMISSION ACTION:
None
AGENCY CONTACT:
Ted Crawford, ted.crawford@wisconsin.gov, 608.266.1674
Download