Technological Studies Exemplar Project Enquiry Crossing the Forth (Advanced Higher) 8537 . Spring 2001 HIGHER STILL Technological Studies Exemplar Project Enquiry Crossing the Forth Advanced Higher Support Materials CONTENTS Page Table of Contents 1 List of Illustrations 2 Introduction 3 Analysis and Description 6 Conclusion 10 References 12 Technological Studies: Exemplar Project Enquiry: Crossing the Forth (AH) 1 LIST OF ILLUSTRATIONS Page Figure 1 The Arch Bridge 3 Figure 2 The Forth Rail Bridge 4 Figure 3 The Forth Road Bridge 4 Figure 4 Suspension Cable (Parabola) 8 Figure 5 Suspension Cable (Catenary) 9 Technological Studies: Exemplar Project Enquiry: Crossing the Forth (AH) 2 INTRODUCTION The River Forth has presented a major obstacle to communication between the northeast and the south of Scotland. The shape of Scotland’s coastline is such that distances between centres of population are out of proportion to the size of the country, and Bridges are vital to the economy. Yet there was no road crossing east of Stirling as recently as 1936, and vehicles, passengers and livestock had to make the time consuming passage by ferryboat at Queensferry or Kincardine. Up until the 18th century most bridges were arch bridges, and their design was the province of builders, or architects. An arch bridge transmits the vertical thrust through the stonework to its abutments, and is a very stable structure. (Figure 1) This means that the height of the bridge is comparable to the span. Brunel’s, daring flat arches of the Maidenhead Bridge in 1837 spanned 39 metres for a rise of only 7.5m, but this increased the loading on the abutments, although since the thrust was compressive the masonry was able to cope, and the bridge is still there, carrying trains ten times heavier than those it was built for. However to cross wider rivers it was the custom to build a series of connected arches. The railway viaducts across valleys stand today as a tribute to the Victorian Engineers. Figure 1 The Arch Bridge The rapid growth of Railways in the mid nineteenth century highlighted the need for a crossing of the Forth, although plans to construct a road crossing were drawn up as early as 1750, before the development of railways. Travel by road was in any case slow and difficult, and the ferries could easily cope with the demands of horse drawn carriages, foot passengers and even livestock. The topography of the Forth river bed made an Arch Bridge impracticable. A Suspension Bridge was considered, but as will be seen later, such bridges were considered to be at the limit of their span with the materials available, and were too flexible to accept the varying loads of trains. Technological Studies: Exemplar Project Enquiry: Crossing the Forth (AH) 3 Figure 2 The Forth Rail Bridge After many plans had been considered, the design of Sir John Fowler and Sir Benjamin Baker was adopted and work began in 1883, and was completed in 1890. The principle of the Forth Rail Bridge is the Cantilever. The development of road transport and the steady improvement in the road system in the first half of the twentieth century brought increasing demands for a road crossing of the Forth downriver from Stirling, as the demands on the Ferries was becoming too great, and they were time consuming, which was very frustrating as average road speeds steadily increased. The alternative was an equally time-consuming detour. An additional railway crossing had been built at Alloa, but it was not until 1936 that a road crossing was built to replace the ferry at Kincardine. This was at a narrow part of the river, and it incorporated a swing section to allow shipping to pass upstream to Alloa and Stirling, once busy ports. Significantly the Swing Bridge has now been locked following the decline in shipping trade at these ports. Figure 3 The Forth Road Bridge Technological Studies: Exemplar Project Enquiry: Crossing the Forth (AH) 4 A growing public demand led to a road crossing of the Forth a short distance upstream from the Rail Bridge. This time the Suspension Bridge was considered, because of the large span needed, and the requirement for only two support piers which utilised a strategically placed rock on the north side, and a pier constructed using a caisson on the deeper south side. The high deck of this bridge as with that of the cantilevers of the Rail Bridge allowed unrestricted access to shipping. Rope suspension bridges have been in use for thousands of years. To construct a strong bridge with a large span required the development of wrought iron for the support chains, a cheap strong material, and Telford made use of this in 1825 to cross the Menai Straits. The span of 166 m was reckoned to be approaching the limit for this material. He worked with a highest working stress of 55 MN/m2 with a Factor of Safety of 3. Brunel crossed the Avon Gorge at Clifton with a span of 190 m. The use of high tensile steel wires made much larger spans possible, as the Engineer could work with stresses of 580 MN/m2 , ten times that employed by Telford. Work started on the Forth Road Bridge in 1958, and it was completed in 1963. Technological Studies: Exemplar Project Enquiry: Crossing the Forth (AH) 5 ANALYSIS AND DESCRIPTION The Forth Rail Bridge consists of three double cantilevers supported by masonry piers, the Fife Pier and the central Inchgarvie Pier built on whinstone rock, the South Queensferry Pier on boulder clay. The central pier makes use of Inchgarvie Island, well placed near the centre of the Firth. The ends of the bridge are not fixed to the approach viaduct, but carry a counterbalance of 1000 tonnes to balance half the weight of the central span each. The deck is thus in perfect balance for dead loading, but trains entering the bridge upset this, which accounts for the wider base for the Inchgarvie cantilevers. The three foundations were constructed under water by sinking caissons. These 24 m diameter cylinders were settled on the river bed, open at the base, and all the water pumped out and kept out by compressed air. This allowed workmen working inside the caissons to construct the masonry foundations. Once completed the remaining space in the caissons was filled with concrete. Each foundation block was topped with four circular granite faced piers. The steel structure was then anchored to the masonry by 48 steel bolts each 64 mm diameter and 8 meters long. Work on each of the cantilevers was carried out simultaneously. The main “vertical” columns are 3.7 m in diameter and incline inwards at 80 to the horizontal. Each tower is 104 m high, and with a clear height of 46 m above high water, allows free passage to shipping of all types. The central joints between the cantilevers allow for 25 mm expansion, and at each shore end there is provision for a further allowance of 12.5 mm. An internal viaduct constructed from two latticed girders, 5 m between centres and with cross girder every 3.4 m, carries the two rail tracks. The viaduct is supported from the cantilevers by cross girders and trestles. It is interesting to note that, in contrast to the Road Bridge, the design load of the Rail Bridge has gone down, since modern trains are much lighter than the steam trains of old. The cost of the bridge was £2 500 000, and the materials used were: Steel Masonry: Granite Ordinary stone Concrete Rivets 55,000 tonnes 21,000 cubic metres 37.000 cubic metres 49,000 cubic metres 8 million. 4,500 workmen were employed in the construction of the Bridge. Sadly 57 workmen lost their lives in the course of construction. A painting schedule was drawn up to combat corrosion. The bridge to be painted entirely every three years. 29 Painters were engaged permanently, using 17 tonnes of paint to cover the 59 hectares of steel. Technological Studies: Exemplar Project Enquiry: Crossing the Forth (AH) 6 The campaign to build a road bridge near the rail bridge began in earnest in 1923 at a Press conference at the Hawes Inn, South Queensferry, attended by all the towns in the locality and motoring associations and motor traders. Discussions went on, interrupted by the Second World War, until 1956, when it was agreed that a suspension bridge should be built utilising the MackIntosh Rock west of the Rail Bridge. The main span would be 1006 m long. The Government and the local Authorities contributed part of the cost, the remainder to be by loans, repayable out of toll revenue from the Bridge. After clearing the sites of the north and south approaches, the first work on the bridge was the building of a causeway 400 m out to the MackIntosh rock. This whinstone reef is about 6 m below low water. The top of the rock was blown off to make a base for the north tower. The south pier was built using caissons, working through boulder clay onto sandstone at a depth of 27 m below low water. The main towers were prefabricated in Glasgow, and three welded high tensile steel boxes in each leg. The steel plate was up to 32 mm thick and each section weighed 35 tonnes. When assembled the towers were quite a spectacle at 157 m high. On July 5th 1961 the first cable was erected across the Forth. In all 22 cables 25 mm diameter and 1834 m long were put in place to support temporary catwalks. The two catwalks were linked by cross bridges to assist in spinning the main cables. The system of spinning was invented by J A Roebling in the United States in 1845 on the Pittsburgh Canal. This was to be the first use of the system in Europe. As mentioned earlier, a special school was set up in South Queensferry to teach the techniques of cable-spinning. Four tunnels had been prepared, two at either end, to form anchorage for the cables. An idea of their size can be gathered from the fact that when completed each tunnel was filled with 10,500 tonnes of concrete. Two wires were passed from the shore-based drums over a travelling pulley block and anchored in the south tunnel. The pulley block was then hauled across the river and the wires anchored in the corresponding north tunnel. The pulley was then returned to the south side for the next pair. Nearly 12,000 of the 5 mm diameter wires were taken across for each main cable. The wires were laid parallel in groups, and were then compacted into circular form by a moving mechanism of a circle of rams. The final diameter was 600 mm. After treatment to prevent corrosion the circular cable was bound with soft galvanised wire, an operation which required 48,000 kilometres for the two cables. Cast steel cable bands spaced at 18 m centres were clamped round the cables to hold the hangers for the decking. Each hanger consists of two loops of 50 mm diameter wire. The deck was assembled outwards from the towers. The steelwork was raised by electric derricks and assembled in front of the derrick which then moved on to the new part and raised the next. The final piece fitted to join the two sides was accurate to within 25 mm. Technological Studies: Exemplar Project Enquiry: Crossing the Forth (AH) 7 At the peak of activity, 450 men were employed in the construction of the road bridge, which cost in excess of £11 500 000. 29,500 tonnes of steel were used to construct the towers, decking and cables. The question of tolls for what many regard as part of the national road network has long engaged public attention. The toll was set initially at two shillings and sixpence (12½ pence). At this rate of collection with the traffic at the time the initial cost was not being repaid. Indeed the interest on the loan was not being raised, and unpaid interest was added to the capital. The situation was resolved mainly by the inflation of the seventies, which in effect reduced the value of the loan, together with increased traffic and a toll of 40p. Automatic collection of tolls was tried in an attempt to reduce queuing, but was found to be a failure. A scheme to collect double tolls only on the North lane is now in force. T P Q H Vertical chains y O x Figure 4 Suspension Cable (Parabola) Figure 4 shows part of the Suspension cable holding up the horizontal deck. If the weight of the cable is neglected, the weight of the bridge is evenly distributed. Consider portion OP of the cable. Forces acting are: 1. Tension at O (horizontal) H 2. Tension at P, T acting at degrees to horizontal 3. Tensions of vertical chains (vertical). Resolve horizontally: H – T cos = O Resolve vertically: =O sin - W Where W is sum of all tensions in the support chains between O and P Technological Studies: Exemplar Project Enquiry: Crossing the Forth (AH) 8 If the weight of the portion of the bridge between O and P is w per unit length, W = wx Giving and T sin = wx T cos = H Dividing these gives Thus tan dy/dx Integrating y = wx/H = wx/H = ½wx²/H (+C) This is the equation of a parabola, which is the shape taken by the suspension cables. B A Figure 5 Suspension Cable (Catenary) Figure 5 shows the part of the Suspension on completion before being attached to the deck. The weight of the cable is now significant, and is not evenly distributed in the horizontal plane. This is shown by inspection, as there is clearly more cable in horizontal distance B compared with the same horizontal distance A, due to the increasing angle of the cable away from the centre. It can be shown that the shape taken up by the freely suspended cable is a Catenary. This has a different profile to the parabola, and though the difference is not great, it becomes significant for cables 1 kilometre in length. The bridge builders have careful calculations to make to ensure that the length of the cables is correct so that they can change profile when connected to the deck, and that the deck support hanger cables are of the correct length. Technological Studies: Exemplar Project Enquiry: Crossing the Forth (AH) 9 CONCLUSION Both the Forth Rail Bridge and the Forth Road Bridge fulfil their function very well. Each structure was built in response to a need for improved communications at a particular time in history, and each was constructed with regard to the type of transport involved, the topography of the area, the materials and the techniques available at the time of construction. Fowler and Baker, aware of the spectre of failure in the wake of the Tay Bridge disaster, built a structure far stronger than was really necessary. The material used was steel, comparatively cheap plentiful and easily worked, but has left a legacy of corrosion which requires continuous maintenance. On the other hand the maximum loading which the bridge has to withstand has gone down with time, as the diesel trains of today are far lighter than the steam trains of old, and when the line is electrified the loading will be even less. This is in marked contrast to the Road Bridge, where traffic loading has increased steadily since it was built, and the bridge has undergone strengthening once or twice already. The suspension bridge is in theory an ideal solution for a road crossing over a wide deep estuary, since road traffic, being in discrete packets rather than a train, can tolerate some road movement. However the stability of a suspension bridge has been achieved over time by trial and error. The Tacoma Narrows Bridge in America suffered a spectacular failure in 1940 because the deck was not stiff enough, and a wind of only 42 miles per hour which blew steadily for a few days caused the swaying to increase until the bridge destroyed itself. Future bridges employed stiffening in the form of box girders, but this brought new problems, as the tendency to buckle had not been fully appreciated, and the Forth Bridge had further stiffening work on its girders not long after it was built. In recent times the use of jacks in the towers together with strengthening inside the towers has raised the load carrying capacity of the bridge. The technique of spinning high tensile steel cables has been described, and the fact that a school was set up to teach this method of construction is indicative of the careful preparation that characterised the whole enterprise. The employment of up to 4500 men on the Rail Bridge brought some wealth to the area over seven years, and permanent employment for maintenance staff. Fife and the North East enjoyed improved communications with the capital and the South. The loss of 57 lives shows that health and safety matters were not a major consideration. In contrast the workmen on the Road Bridge wore hard hats, safety belts, safety boots and special clothing. Safety nets, walkways and handrails were provided as well as a safety boat. Even so 3 workmen lost their lives during the construction. High winds were a constant hazard, and in the worst of these, winds over 30 miles per hour, the workmen were not expected to operate. The 74 staff of the ferries, displaced by the construction of the bridge, were given employment in the operation of the bridge. Technological Studies: Exemplar Project Enquiry: Crossing the Forth (AH) 10 Both bridges stand as monuments to the achievements of man. Each owes its success to the pioneering work, ingenuity, inventiveness (and the failures) of many generations of Engineers. Each bridge is distinctively different in solving basically the same problem, from the solid ruggedness of the Victorian ironwork to the elegant sophistication of the nineteen sixties. Whilst praising and admiring what we see however, we must acknowledge that also, as with most great works, the hand of man is not flawless. Technological Studies: Exemplar Project Enquiry: Crossing the Forth (AH) 11 REFERENCES Mackie A A Tale of Two Bridges, Commercial Enterprises, Edinburgh Gordon J E Structures, Penguin Books Ltd, Harmsworth Norman E et al Advanced Design & Technology, Longman Group Ltd Jeans J H Theoretical Mechanics, Ginn & Company CD Rom Microsoft Encarta CD Rom Europress Family Encyclopedia 1999 Internet Sites www.google.com www.hydratight.com/morlift/forth_bridge.htm www.structurae.de/DataEnglish/str00300.html www.geo.ed.ac.uk/scotgaz/features/featuresfirst101.html www.webviews.co.uk www.scotlandvacations.com/forthbridge.htm www.forth-bridge.co.uk Technological Studies: Exemplar Project Enquiry: Crossing the Forth (AH) 12