Ref. Risk description
Staffing
1. Insufficient resources to manage normal operations
Consequence Likelihood Impact
Deterioration in response time – service failure / Missed opportunities /
Increased cost
L H
2. Skills gap
3. Resistance to change
Insufficient skills to deliver services
– service failure / Missed opportunities
L
New structure not embraced by single team / Fractions between two existing teams / Staff performance issues – service failure
M
4. Differences in Salary / Terms and
Conditions
New structure not embraced by single team / Fractions between two existing teams / Staff performance issues – service failure
M
M
M
L
Risk Manager Mitigating action
Development of joint ICT annual work programme monitored by Head of
Service and respective Portfolio
Holders.
Regular review of helpdesk response times
Regular service reviews with SMT
ICT Forums with services
If additional resources are required this will generate options appraisal and request to SMT
Skills gap analysis to be undertaken by Internal Audit
Appropriate training arranged for appropriate staff
Greater reliance placed on external suppliers / vendors
Full consultation with staff on changes
Regular team meetings / 1to 1 meetings
Single management team introduced at the earliest opportunity
Joint training / skills sharing opportunities
Standardised HR procedures
Full consultation with staff on changes
All roles job evaluated – HR procedures followed
Effective use of the HR teams where appropriate
Regular team meetings / 1 to 1 meetings
Single management team introduced at the earliest opportunity to instigate any required changes
Head of Service
Head of Service
Head of Service
Head of Service /
ICT Operations
Manager
5. Key personnel leave
Loss of key skills – service reduction L
Technology
6. Changes in future technologies Inappropriate investment in current technologies / skills development requirement /
Missed opportunities
M
7. Failure of existing technology Inability to provide IT services M
Regulatory
8. Do not meet data security / other legislative requirement (e.g.
Government Connect)
Loss of data – potential prosecution / failure to provide services / reputational impact / loss of customer confidence
– increased costs
L
M
L
H
H
Joint training / skills sharing opportunities
Greater reliance placed on external suppliers / vendors
Regular appraisals
Head of Service /
ICT Operations
Manager
Defined requirement within all ICT
Management roles of assessing emerging technologies
Obtain external advice / support where appropriate
Work closely with other public sector organisations to review future opportunities
Membership of SOCITM / access to other external professional bodies to review technology trends
Regular monitoring of equipment / applications
Greater reliance placed on external suppliers / vendors – appropriate service level agreements
Timely replacement of ageing / failing equipment
Effective disaster recovery plans implemented
ICT Management
Team
ICT Management
Team
Systems reviewed to ensure they meet legislative requirements
Regular internal audit reviews of key systems
Obtain Government Connect certification
Adopt and implement standardised
ICT Security policy and related procedures
Head of Service
Financial / Procurement
9. Insufficient funding to cover service
Unable to provide elements of the service / contractual disputes
L
10. Issues with single / joint procurement / licensing arrangements
Unable to obtain all the benefits of shared working / delays in the programme delivery / additional costs
M
Other
11. External organisational changes – work with other Public Sector
Bodies / changes of Government approach / broader changes to local government
Programme specific
12. ICT operational performance dips during delivery of the Joint ICT programme
Delays in programme delivery / additional costs / unrequired costs
Deterioration in response time service failure / Missed opportunities /
Increased cost
–
M
M
L
M
M
M
13. Delays in programme delivery Failure to obtain service / financial benefits as per plan / Delays in phase
2
– reducing potential for improved service delivery and reduction in organisational costs
L H
Regular review of budgets
Standard annual budgetary process
Formal request / approval for additional funding through normal channels
Regular discussions with the
Procurement / Legal teams
Early discussions with suppliers
Review joint ICT implementations / approaches elsewhere – lessons learnt
Head of Service
Head of Service
Continual monitoring of Government announcements
Continued cross working with other local authorities / public sector bodies
Corporate
Management
Team
Development of joint ICT annual work programme monitored by Head of
Service and respective Portfolio
Holders.
Regular review of helpdesk response times
Establishment of Programme Board -
Agreed rescheduling of programme plan if deemed appropriate by the
Project Board
Development of joint ICT annual work programme monitored by Head of
Service and respective Portfolio
Holders.
Establishment of Programme Board to monitor progress and to initiate remedial action
Regular reporting to the Joint
Partnership Board
Head of Service
Head of Service
14. Insufficient resources to deliver the programme
Delays in programme delivery / staff morale impacted
L H
15. Under-estimation of required budgets / overspend
16. Insufficient development of Phase
2 requirements
Delays in phase 2
– improved service delivery and reduction in organisational costs
17. Proposed technical solution proves inadequate / lacks resilience
Delays in programme delivery / additional costs or reduced programme of work – reduced benefits
Delays in programme delivery / additional costs / service failure
M
L
M
H
H
H
Development of joint ICT annual work programme monitored by Head of
Service and respective Portfolio
Holders.
Establishment of Programme Board to monitor progress and to initiate remedial action
Regular team meetings to review progress / keep team informed
Establishment of Programme Board to monitor progress and to initiate remedial action
Technical business cases approved by Portfolio Holders
Effective budget estimation within outline Business Case
Service Plans developed by Heads of
Service
Role instigated to develop Phase 2 programme plan
Regular discussion at Corporate
Management Team
Establishment of Programme Board -
Agreed rescheduling of programme plan if deemed appropriate by the
Project Board
Technical infrastructure reviewed externally
Continual reviews by the project team
Revision of plans / solutions / expenditure where appropriate and with the appropriate approval
Head of Service
Head of Service
Head of Service
Head of Service