Ministry of Finance and Economic Development White Paper On Modernising the Public Procurement Framework Issues and Proposals for Consultation July 2011 Preface Total public sector investment has more than doubled over the last decade due to the substantial increase in the number of projects as well as in their project value. Moreover, the complexity of projects has also increased over the years. These developments have brought in new challenges, particularly in project preparation, procurement and execution. This is more so as the Public Sector Investment Programme has a pipeline of projects of around Rs 140 billion for the period 2011-2015. In addition, around Rs 125 billion are expected to be invested under Public Private Partnership arrangements. To address these challenges, Government has over the past few years implemented a series of reforms to modernise the public procurement system. Further reform of the system is being called for as indicated in the Government Programme 2010-2015, where it is proposed that “the public procurement system will be further reviewed, modernized, decentralized and supported by the implementation of an eprocurement platform.” The aim of the new system is to strike the right balance between speed of project implementation and transparency while at the same time ensuring value for money. The World Bank, COMESA and UNCITRAL advised Government in the review of the current procurement system. In view of the importance of public procurement in terms of good governance, accountability, transparency, fairness and value for money, it is essential that inputs are obtained from a wide array of stakeholders. In this regard, a White Paper has been prepared based on recommendations made by a Review Committee chaired by a representative of the Attorney-General’s Office and comprising key stakeholders involved in public procurement. The White Paper identifies key issues in relation to institutional arrangements, and procurement process and methods. This White Paper has been structured in a systematic manner to allow readers to grasp the key issues at hand followed by proposals for improving the existing system. This White Paper is being put forward to all stakeholders for wider consultations. Stakeholders are invited to submit their comment/suggestions on the issues and proposals contained in this White Paper at latest by 12 August 2011 to the following address: Director Procurement Policy Office 8th Floor, Emmanuel Anquetil Building Port Louis Fax no: 213-1003 E-mail address: pbeeharry@mail.gov.mu 1 1. Introduction 1.1 Our public procurement system has evolved over the last decade in line with the country’s economic development and government initiative to optimise the use of public resources. The introduction of the Public Procurement Act (PPA) in 2008 was a major step in Government’s reforms plan as it allowed Mauritius to harmonise its system with international norms and best practices. The existing legislation is based on the UNCITRAL model on procurement. 1.2 However, the country is now faced with a new challenge to increase the level of investment, accelerate the execution of infrastructure projects and improve the delivery of public services to achieve the ambitious target of one trillion rupees in GDP by the 2020s. This challenge has given rise to a need for a thorough review of our public procurement system. Moreover, promoting Public-Private Partnership (PPP) as a complement to traditional procurement also contributes towards the achievement of this goal. The framework for undertaking PPP projects is governed by the PPP Act. 1.3 Accordingly, the Public Procurement Framework has recently been reviewed by the World Bank, COMESA and UNCITRAL. The primary focus of the review assessment was to further modernise our Public Procurement Framework so as to improve the capacity of Public Sector Institutions to implement capital projects and deliver services in an efficient and costeffective manner to support the bold ambition for Mauritius to grow rapidly to a high income economy. 1.4 Both the World Bank and COMESA recommended the creation of an independent regulatory authority to strengthen compliance monitoring while ensuring greater transparency and integrity of the procurement process. 1.5 In August 2010, Government set up a Review Committee to propose changes that need to be brought to our public procurement legislation in the light of the observations and recommendations of the World Bank, COMESA and UNCITRAL. In its deliberations, the Committee also took note of the weaknesses and shortcomings identified during the course of implementation of the Public Procurement Act 2008 and the feedback obtained from stakeholders on our public procurement system. 1.6 The objective of the proposed reform in public procurement is to achieve stronger accountability, greater transparency and a higher pace of project execution whilst ensuring value for money. 2 2. Key Issues 2.1 The Review Committee submitted its report in February 2011. After analysis of the report, proposals have been formulated to address key issues. These issues together with proposals are described below. 2.2 INSTITUTIONAL ARRANGEMENTS 2.2.1 The current institutional setup comprises: - The Procurement Policy Office (PPO) as a policy making and oversight institution. - The Public Private Partnership (PPP) Committee, set up under the PPP Act, is responsible for dealing with all matters relating to PPP, including giving approval to contracting authorities to proceed with procurement of PPP projects. Under the PPP Act, a contracting authority is a Ministry or Government department, local authority or statutory corporation. - The Central Procurement Board (CPB) for the vetting of bidding documents and the conduct of the bidding process and approval of award in respect of major contracts. These functions of the CPB apply to projects undertaken under both the PPA and the PPP Act. - The Independent Review Panel (IRP) for review of procurement proceedings following applications from unsatisfied bidders. 2.2.2 Although the PPA is substantially compliant with the UNCITRAL Model Law on Public Procurement and the COMESA Procurement Directive, a major deviation has been the maintenance of the Central Tender Board under the new appellation of Central Procurement Board (CPB). The reasons which motivated the decision were: - It was not considered appropriate to do away with such an institution overnight without building up trust in the new public procurement system. - It was felt more appropriate to go for gradual decentralization while building capacity of public bodies to handle higher value contracts. Issues 2.2.3 However, as the provisions concerning the CPB in the PPA were copied from the Central Tender Board Act, a number of problems cropped up. The CPB assumed that in view of its operational independence it is not accountable to the PPO the policy making and oversight authority and also not answerable to the IRP during hearings in respect of procurement awards that were 3 challenged by unsuccessful bidders. Moreover, compliance monitoring could not be properly done as access to the relevant files was denied. 2.2.4 Ownership of decisions with respect to contract awards by public bodies was jeopardized given that the CPB is also responsible for the evaluation of bids. This was viewed as being very serious by funding institutions, which could not get the comfort that the implementing public bodies were satisfied with the evaluation and selection of the contractor. 2.2.5 A Review commissioned by the World Bank in 2010 on the Mauritian PPP Legal and Institutional Framework revealed that the CPB does not have the required knowledge or understanding of PPP projects and PPP feasibility studies. Evaluation of PPP proposals requires not only a ranking between proposals as is the case for conventional procurement but an assessment of value for money, affordability, fiscal risk and risk transfer elements of the proposals compared to expectations based on the PPP feasibility study. The Review concluded that the CPB is not the appropriate body to carry out the procurement function for PPP projects. 2.2.6 The Review of the PPP framework also highlighted that the definition of contracting authorities as per the PPP Act is restrictive in the sense that it does not cover all public enterprises. There is thus no standard practice across the public sector. This not only exposes the implementation of PPP projects to legal and procedural uncertainty but also to the risk that these enterprises could enter into long-term contracts (outside the requirements of the PPP Act) that could become unaffordable, not provide the public sector with better value for money, and expose the public sector to significant fiscal risks. Proposals 2.2.7 Public Procurement Authority 2.2.7.1 In the place of the PPO, it is being proposed that an independent and strong regulatory authority, the Public Procurement Authority (hereinafter referred to as the Authority), be set up to regulate conventional procurement and to perform the following functions: Formulate policy and review legislation Monitor compliance with the PPA Develop and implement procurement performance assessment system Review of thresholds applicable for major contracts that would require CPB’s clearance Investigate into cases of non-compliance/malpractice and recommend disciplinary action against officers in breach of the PPA Debar/disqualify bidders/suppliers - 4 - Build capacity Collect and analyse data Provide guidance to public bodies on procedural matters 2.2.7.2 The independence of the Authority would be strengthened if the following provisions are to be adopted: - The Chairperson and the Director General of the Authority to be appointed by the President of the Republic on the recommendation of the Prime Minister after the Prime Minister has consulted the Leader of the Opposition The contracts of the Chairperson and the Director General can be terminated only on grounds as stipulated in the PPA The Authority not to be subject to the direction or control of any other person or authority - 2.2.7.3 With time as the Authority gathers experience, it may also be envisaged to consider providing it with some financial autonomy. In the event that there is consensus on the type of financial autonomy, a mechanism has to be worked out accordingly. 2.2.8 Public Private Partnership Committee 2.2.8.1 It is proposed to strengthen the PPP Committee by improving its composition and functions. In addition to its existing functions, the PPP Committee would be responsible for overseeing all the stages within the PPP procurement process, namely, advice on the most appropriate procurement method, vet all procurement documents, provide clearance for the evaluation team proposed by the contracting authority and review evaluations carried out by the evaluation team. The PPP Committee would carry out quality control throughout all stages of the PPP procurement process thus ensuring its integrity. 2.2.8.2 This proposal implies that the responsibility for PPP procurement would be transferred from the CPB to contracting authorities. As stated at paragraph 2.2.5, the latter being involved in the preparation of projects through the feasibility study stage would be in a better position to prepare procurement documents, invite and evaluate bids and approve and award PPP projects. 2.2.8.3 To broaden the definition of contracting authority in the PPP Act to include the Rodrigues Regional Assembly as well as any Public Enterprise. The latter would include state-owned and state-controlled institutions. 2.2.8.4 The membership of the PPP Committee would be broadened to include the Ministries of Housing and Land; Energy and Public Utilities; Local 5 Government; and Environment. This would help to increase its capacity for technical analysis and to identify and address issues relating to land, utilities, permits and clearances at an early stage of the project cycle. 2.2.9 Central Procurement Board (CPB) 2.2.9.1 For conventional procurement the CPB to continue to exist with its role and functions to be modified as follows: - Provide guidance to public bodies on operational matters With regard to procurement exceeding the prescribed thresholds (prescribed thresholds to vary taking into account the capacity of public bodies to handle procurement) vet bidding documents and procurement notices give its no objection prior to award Make framework arrangements and administer their implementation for procurement of standardized and common use items, and works and services of repetitive nature Collaborate with the Authority, amongst others, in the development of standard bidding documents the development of training programmes for procurement officials - - 2.2.9.2 For PPP projects, it is being proposed to transfer the responsibility for procurement from the CPB to the relevant contracting authorities under the oversight of the PPP Committee. The contracting authority would be responsible to prepare and launch the bidding documents, evaluate the bids received, approve and award the PPP project. 2.2.10 Independent Review Panel (IRP) 2.2.10.1 The IRP to continue to operate as a separate body responsible for attending to complaints from unsatisfied bidders and reviewing of cases of appeals relating to contract awards for both conventional and PPP procurement. Furthermore, its capacity to be reinforced and its decisions to be made binding. 6 2.3 EXEMPTIONS FROM SCOPE AND APPLICATION OF THE ACT Issues 2.3.1 PPA does not exempt procurements effected under bilateral agreements where technical assistance is obtained from other States. 2.3.2 Exemptions under the PPA are given to certain public bodies (exempt organisations) while generally an exclusion clause is provided for certain types of procurement where it is not practical to apply the normal procurement methods. 2.3.3 While procurement of defence and security items is excluded from the provisions of the law, there is no established guideline to assist the concerned public bodies to undertake such procurement. Proposals 2.3.4 Procurement undertaken pursuant to a treaty or other form of agreement with a State or States to be exempted from the provisions of the PPA as is the case under the UNCITRAL model law. 2.3.5 The PPA to provide for exemption through the exclusion of certain types of procurement applicable to all public bodies, as it is the practice in the EU, for example, transmission rights, procurement of goods for resale, acquisition of shares etc. This measure would allow the procurements other than those excluded to be subject to the application of the provisions of the PPA for greater transparency and consistency. 2.3.6 Procurement of defence and security items to remain outside the scope of the PPA, but be subjected to different set of rules/guidelines as is the practice in many developed countries. 2.4 PROCUREMENT METHODS 2.4.1 Restricted Bidding Issue 2.4.1.1 There is a risk of abuse of the Restricted Bidding method as there is no mechanism to shortlist suppliers in a transparent manner. 7 Proposal 2.4.1.2 It is being proposed that the mechanism for shortlisting suppliers/service providers/contractors be incorporated in the PPA to ensure fairness and transparency. 2.4.2 Request for Sealed Quotations Issue 2.4.2.1 Normally, the Request for Quotations is an informal method used for low value procurements, which, in the current legislation, is not included as a method of procurement. Instead, the PPA provides for Request for Sealed Quotations as a formal procurement method which is more or less similar to Restricted Bidding for procurements within a prescribed threshold. Proposal 2.4.2.2 The Request for Sealed Quotations as a procurement method to be replaced by Request for Quotations. Request for Quotations is being suggested for procuring low value items. 2.4.3 Emergency Procurement Issue 2.4.3.1 The PPA does not distinguish between ‘extreme urgency’ and ‘urgent’ situations. It prescribes Direct Procurement as the only method to cope with emergency situations even where some degree of competition could be introduced. Proposal 2.4.3.2 There is a need to differentiate between cases of extreme urgency and urgent situations. For extreme urgency cases, it is being recommended that the application of Direct Procurement be maintained. However, for urgent cases, Competitive Negotiations could be introduced as a new method of procurement. 8 2.4.4 Departmental Execution Issue 2.4.4.1 Presently Departmental Execution is limited to works being carried out directly by the public body itself or by another public body without entering into any contract. The possibility of creating a separate entity operating on commercial lines to provide specialised services for its parent Ministry and/or other public bodies without going through a bidding exercise does not exist under the current legislation. Proposal 2.4.4.2 Consideration could be given to a Public Body to set up an agency under its aegis to provide specialised services whenever the necessity is felt. In this context, enabling provisions have to be made to allow for specialised services to be delivered by in-house bodies. 2.4.4.3 Departmental Execution and the provision of services by in-house bodies to be included under the exclusion section of the PPA. 2.4.5 Direct Procurement Issue 2.4.5.1 The PPA defines Direct Procurement as the purchase of goods, other services and works from a single source without competition. However, in practice, both single source procurement and procurement of low value items through informal quotations are being carried under the Direct Procurement method. Proposal 2.4.5.2 It is being suggested that Direct Procurement be replaced by Single-Source Procurement. For low value procurements, use of Request for Quotations method is to be considered. 9 2.4.6 Framework Agreement Issue 2.4.6.1 There is no mechanism to undertake procurement of common use items in an economical manner as the current legislation is silent on framework agreements. Proposal 2.4.6.2 Consideration to be given for framework arrangements in order to achieve economies of scale and higher level of efficiency when procuring common use items and works and services of a repetitive nature. 2.4.7 Electronic Reverse Auction Issue 2.4.7.1 Not prescribed as a procurement method under current PPA although such a method would reduce cost and procurement lead time. Proposal 2.4.7.2 Electronic Reverse Auction as a new procurement method could be introduced to allow pre-qualified bidders to participate in a dynamic electronic competitive bidding process. This method, under defined conditions, would achieve higher efficiency by reducing cost and procurement lead time while promoting transparency and equal treatment to bidders. 2.5 BIDDING PROCESS 2.5.1 Eligibility conditions for State-Owned Companies 2.5.1.1 Issue The eligibility conditions for State Owned Enterprises to participate in public procurement are not defined in the PPA, to ensure a level playing field and equal opportunity for all bidders. Proposal 2.5.1.2 The eligibility conditions for State Owned Enterprises to be defined in the PPA. 10 2.5.2 2.5.2.1 Pre-qualification Procedures Issue The use of pass/fail methodology as the pre-qualification procedures is not explicitly stated in the PPA, though such methodology is provided for in the Standard Bidding Documents. Proposal 2.5.2.2 To ensure consistency and uniformity with regard to pre-qualification procedure, the pass/fail methodology to be stated in the PPA. 2.5.3 Other Procedures Issue 2.5.3.1 Provisions essential for achieving good procurement outcomes (e.g. provisions on publication of bid notices on websites, content of bidding documents, opening and evaluation procedures, record keeping) are contained in the User Guide and not in the PPA or its regulations and as such they do not have force of law. Proposal 2.5.3.2 Essential provisions contained in the User Guide to be dealt with in the PPA or its regulations. 2.5.4 Bid Security Issue 2.5.4.1 The PPA does not provide for Bid Securing Declaration as an alternative form of Bid Security which has been introduced to facilitate participation in bidding exercises. Proposal 2.5.4.2 The PPA to formally provide for Bid Securing Declaration as a form of Bid Security. 11 2.5.5 Preferential treatment Issue 2.5.5.1 Although the Republic of Mauritius obtains benefits from friendly countries, which also provide assistance in cases of emergency, there is no mechanism in the current procurement legislation to provide preferential treatment to such countries. Proposal 2.5.5.2 Consideration could be given for the inclusion of an enabling clause in the PPA for allowing a margin of preference to countries which provide Mauritius with grants and/or concessionary finance of at least 50% of the funding for a project. For example, a project of Rs100 million must benefit from a total of at least Rs 50 million of grant and/or concessionary loan to be eligible. 2.5.5.3 For a loan to be considered as concessionary, it must include a grant element of at least 30 percent. To determine if a loan is concessionary, the grant element is calculated by taking the difference between the Net Present Value (NPV) of the loan compared to borrowing at market rates. For example, if a loan has a longer maturity and/or lower interest rates than market instruments such that the NPV of the loan is Rs 30 million whilst that of the market instrument is Rs 50 million, the grant element is Rs 20 million i.e. a 40 percent grant element, making it concessionary. 2.5.5.4 The margin of preference would be applicable during the evaluation of bids received from bidders of those countries providing us with grant and/or concessionary finance. The quantum of preference would vary according to the extent of support being offered to Mauritius but would not exceed 5% of the value of the preferred bid. For example, in a tender for a water supply project, if the preferred bid would result in consumers paying Rs 5 per cubic metre and a project with preferences above would charge up to Rs 5.25 per cubic metre, the latter would be awarded the tender despite the higher price. However, if the price exceeded Rs 5.25 per cubic metre, the preferred bidder would be awarded the project. 12 2.5.6 Unsolicited Proposal Issue 2.5.6.1 The PPA does not allow for unsolicited proposals. An unsolicited proposal is a proposal which has neither been originated nor requested by a Public Body but comes from an external party. Proposal 2.5.6.2 The Public Body receiving an unsolicited proposal would first consider if the proposal is in the public interest and fits within the strategic priorities of Government. 2.5.6.3 If the proposal is accepted, it would be tested through a formal process which includes an open competitive exercise. Two methods are being proposed namely, the Swiss Challenge Method and the Bonus Method. After consultations, one of these methods could be retained. 2.5.6.4 Either the Swiss Challenge Method The party making the unsolicited proposal (referred to as the original proponent) would be given the opportunity to match the price of the preferred bidder in the event that the original proponent is not the preferred bidder. If the original proponent accepts to match the preferred bid price, the original proponent would be awarded the project. Or the Bonus Method The party making the unsolicited proposal (referred to as the original proponent) would be given a weightage equivalent to 5% of the total marks allocated to the technical score during the evaluation of bids. Following the bid evaluation exercise, the original proponent would only be awarded the project if it the preferred bidder. 13 2.6 CHALLENGE AND APPEAL Issues 2.6.1 The decisions of the IRP are not binding and as such do not guarantee fairness to a bidder whose application was found to have merit. 2.6.2 The procurement process is unduly delayed due to a complex challenge and appeal process. 2.6.3 The IRP does not have the appropriate resources to be able to resolve cases within the statutory period of 30 days. Proposals 2.6.4 The decisions of the IRP to be made binding to ensure fairness to a bidder whose application was found to have merit, unless reversed by a court of law. 2.6.5 In addition, the challenge and appeal process could be simplified to avoid undue delay to the procurement process. 2.6.6 The IRP to have the appropriate staff and resources to be able to effectively exercise its mandate. 2.6.7 With the introduction of Framework Agreement, it is proposed that challenge be entertained only during the bidding process and not at the time of individual call-off to avoid undue delays. 14 2.7 DISQUALIFICATION AND DEBARMENT Issue 2.7.1 Although disqualification and debarment lead to the same result, there are two sets of regulations for dealing with disqualification and debarment, which at times is a source of confusion. Proposal 2.7.2 As the process for disqualification and debarment are similar, their procedures could be merged into a single set of regulations. 2.8 PROCUREMENT INTEGRITY Issues 2.8.1 Section 51(1)(f) of the PPA deprives officers for a period of 2 years after leaving the public service from taking up employment in a position of authority in any private firm with which he has had procurement dealings. This provision has too wide implications. It would have been more appropriate not to allow such an officer to deal or negotiate on behalf of the contractor or supplier for a contract he had personally dealt with while in the service. 2.8.2 Section 51(2)(a) of the PPA stipulates that a close relative of a public official shall not participate in procurement proceedings or be awarded a contract in the public body where the public official is employed. This is not practical as strict compliance may deprive most bidders to do business with Government. Disclosure of interest and withdrawal from the procurement process by such official would be sufficient to preserve integrity of the process. Proposal 2.8.3 Section 51(1)(f) and 51(2)(a) of the PPA to be amended to prevent malpractices without, however, unduly penalising public officials and bidders. 15