SPECIFICATION 820 CONCRETE FOR STRUCTURES Copyright MAIN ROADS Western Australia MAIN ROADS Western Australia Contract xxx/xx Specification 820 Concrete for Structures Document 04/10134 Issue 17/06/13 Page 1 of 28 SPECIFICATION 820 CONCRETE FOR STRUCTURES REVISION REGISTER Date Clause Number Description of Revision Authorised By 17/06/2013 820.30 Volume of Permeable Voids added A/SDSE 23/10/2012 820.11 Part 3 of Clause amended A/SES 24/06/2011 820.02 Replaced reference WSSSP43 to ATIC – Specification SP43 A/SDSE 820.07 Replaced all references WSS – SP43 to ATIC Specification SP 43 Added last line to Clause (3) which refers to application form for CMRS Moved clause description ‘Certification’ from Clause (2) to Clause (3) 28/05/2009 Reference to WSS – SP43 820.02 SDSE 820.07 “ 820.07 Added Certification Clause (3) & Hold point Clause (4) 820.28 (2) Hold point Annexure 820B Added Concrete Request for Registration Form 12/06/2008 820.11.1 Total mass limit increased to 2.8 kg/m3 SDSE 06/06/2008 820.11 & 820.26, 820.54.03. 2 Amendments to AAR requirements and bridge deck surface finish SDSE 18/04/2008 820.07 & 820.28 Clauses amended SDSE 28/02/2008 820.28 Inclusion of S40 Aggregate Grading Envelope at Figure 2 SDSE MAIN ROADS Western Australia Contract xxx/xx Specification 820 Concrete for Structures Document 04/10134 Issue 17/06/13 Page 2 of 28 CONTENTS Clause Page No GENERAL ...................................................................................................................... 5 820.01 SCOPE ........................................................................................................... 5 820.02 REFERENCES ............................................................................................... 5 820.03 DEFINITIONS ................................................................................................. 6 820.04 – 820.05 NOT USED ..................................................................................... 7 PRODUCTS AND MATERIALS ..................................................................................... 7 820.06 820.07 820.08 820.09 820.10 820.11 GENERAL ...................................................................................................... 7 CEMENT ........................................................................................................ 7 AGGREGATE ................................................................................................. 8 WATER .......................................................................................................... 8 ADMIXTURES ................................................................................................ 8 ACTION REQUIRED FOR THE CONTROL OF ALKALI AGGREGATE REACTIVITY (AAR) ................................................................................. 9 820.12 SOLUBLE SALTS ......................................................................................... 10 820.13 LIMITATIONS ON SHRINKAGE ................................................................... 10 820.14 – 820.25 NOT USED ................................................................................... 10 DESIGN OF CONCRETE MIXES ................................................................................. 10 820.26 820.27 820.28 820.29 820.30 GENERAL .................................................................................................... 10 DURABILITY ................................................................................................ 11 CLASS OF CONCRETE FOR MIX DESIGN................................................. 11 TRIAL MIXES ............................................................................................... 13 TRIAL MIXES FOR VOLUME OF PERMEABLE VOIDS (VPV) .................. 14 SUPPLY AND DELIVERY OF CONCRETE ................................................................. 14 820.31 820.32 820.33 820.34 820.35 820.36 820.37 820.38 820.39 CONCRETING PLANT ................................................................................. 14 BATCHING AND MIXING ............................................................................. 14 TRANSPORT ............................................................................................... 15 TEMPERATURE AT POINT OF DELIVERY ................................................. 15 MIX CONSISTENCY .................................................................................... 15 ADDITION OF WATER TO THE MIX AFTER MIXING ................................. 15 SAMPLING OF CONCRETE FOR STRENGTH ........................................... 15 STRENGTH OF CONCRETE DELIVERED .................................................. 16 CURING AND TESTING OF SPECIMENS FOR DETERMINATION OF COMPRESSIVE STRENGTH ................................................................ 16 820.40 – 820.50 NOT USED ................................................................................... 17 OPERATIONS .............................................................................................................. 17 820.51 GENERAL .................................................................................................... 17 820.52 PLACING CONCRETE ................................................................................. 17 820.53 CONSTRUCTION JOINTS ........................................................................... 17 820.54 COMPACTION ............................................................................................. 18 820.55 FINISHING OF UNFORMED SURFACES .................................................... 19 820.56 CURING OF CONCRETE ............................................................................ 19 820.57 PROTECTION OF CONCRETE SURFACES ............................................... 20 820.58 – 820.80 NOT USED ................................................................................... 20 MAIN ROADS Western Australia Contract xxx/xx Specification 820 Concrete for Structures Document 04/10134 Issue 17/06/13 Page 3 of 28 AS BUILT AND HANDOVER REQUIREMENTS .......................................................... 20 820.81 – 820.90 NOT USED ................................................................................... 20 CONTRACT SPECIFIC REQUIREMENTS ................................................................... 20 820.91 – 820.99 NOT USED ................................................................................... 20 ANNEXURE 820A ........................................................................................................ 21 CLASS OF CONCRETE ............................................................................................ 21 ANNEXURE 820B ........................................................................................................ 22 CEMENTITIOUS MATERIALS FOR CONCRETE ...................................................... 22 REQUEST FOR REGISTRATION BY MANUFACTURER ......................................... 22 MAIN ROADS Western Australia Contract xxx/xx Specification 820 Concrete for Structures Document 04/10134 Issue 17/06/13 Page 4 of 28 SPECIFICATION 820 CONCRETE FOR STRUCTURES GENERAL 820.01 SCOPE 1. The work under this specification consists of the mix design, the supply and delivery, placing, compaction, finishing, curing and protection of high strength concrete for the following structures: a) Bridgeworks b) Pedestrian Overpasses/Underpasses c) Manufacture of Box Culverts and d) Other major structural works 2. Concrete for general non-structural works is covered in Specification 901 CONCRETE - GENERAL WORKS. 820.02 REFERENCES 1. Australian Standards, MAIN ROADS Western Australia Standards and MAIN ROADS Western Australia Test Methods are referred to in abbreviated form (e.g. AS 1234, MRS 67-08-43 or WA 123). For convenience, the full titles are given below: Australian Standards AS 1012 AS 1141 AS 1379 AS 1478 AS 2758.1 AS 3582.2 AS 3799 AS 3972 Methods of Testing Concrete Methods for Sampling and Testing Aggregates Specification and Supply of Concrete Chemical Admixtures for Concrete, Mortar and Grout Aggregates and Rock for Engineering Purposes Concrete Aggregates Supplementary Cementitious Materials for use with Portland and Blended Cement - Slag - Ground Granulated Iron Blast Furnace Liquid Membrane-Forming Curing Compounds for Concrete Portland and Blended Cements Australian/New Zealand Standards AS/NZS 3582.3 Supplementary Cementitious Materials for use with Portland and Blended Cement – Amorphous Silica MAIN ROADS Test Methods WA 910.1 Chlorides and Total Soluble Salts in Soil and Water MAIN ROADS Western Australia Contract xxx/xx Specification 820 Concrete for Structures Document 04/10134 Issue 17/06/13 Page 5 of 28 Other Standards Cement & Concrete Association of New Zealand – Report No TR3, Alkali Silica Reaction Australian Technical Infrastructure Committee (ATIC) Specification SP43 - Cementitious Materials for Concrete MAIN ROADS Specifications Specification 201 Specification 819 Specification 821 Specification 822 Specification 901 820.03 820.03.01 1. apply: QUALITY SYSTEMS FALSEWORK FORMWORK STEEL REINFORCEMENT CONCRETE - GENERAL WORKS DEFINITIONS DESIGN For the purpose of this Specification the following definitions a) Concrete in general shall consist of a mixture of cement, water, and coarse and fine aggregate. Where specified on the Drawings, blended cement as defined in Clause 820.07 (paragraph 1) shall be used. b) Water/cement ratio is the ratio by mass of the total water content of the mix available for hydration to the total cement in the mix. c) Aggregate/cement ratio is the ratio by mass of the total aggregate in the mix (measured in the saturated surface dry state) to the total cement in the mix. d) The compressive strength of concrete shall be defined as the average 28-day crushing strength of a minimum of three standard 100 mm diameter by 200 mm long cylinders taken from the same sample and made, cured and tested in accordance with AS 1012. 820.03.02 SPECIAL PROCESSES 1. The placing, compacting, finishing and curing of concrete are identified as SPECIAL PROCESSES in accordance with Specification 201 QUALITY SYSTEMS. 820.03.03 Special Processes ADDITIONAL QUALITY SYSTEM REQUIREMENTS 1. The information to be submitted by the Contractor as part of their Quality Plan shall include, but not be limited to, the following:- Quality Plan a) Details of the methods to be used in maintaining evidence generated during each special process. The number of personnel required together with proof of any relevant training and experience shall be included. b) Verification of the compliance of any proposed heat accelerated curing method with the Specification requirements such as steam curing. MAIN ROADS Western Australia Contract xxx/xx Specification 820 Concrete for Structures Document 04/10134 Issue 17/06/13 Page 6 of 28 820.04 – 820.05 NOT USED PRODUCTS AND MATERIALS 820.06 GENERAL 1. Concrete required under this Contract shall be supplied from either an approved off-site batching plant and delivered by truck agitator or an on-site batching plant. 2. In its finished state concrete shall be sound and dense and durable and free from honeycombing and shall have the strength and other properties specified. 3. Concrete shall comply with AS 1379, except as varied by this Specification. 820.07 CEMENT 1. Unless specified otherwise, all cement used in the Works shall comply with the requirements of Type GP cement as specified in AS 3972 and Australian Technical Infrastructure Committee (ATIC) Specification -SP43. The Contractor shall provide manufacturer's test certificates showing all cement has been sampled, tested and conforms in all respects with the AS 3972 and ATIC – Specification SP43 Testing 2. Blended cement shall be a combination of Type GP cement and ground granulated iron blast-furnace slag complying with AS 3582.2 and ATIC – Specification SP43 . The densified silica fume to be added to the blended cement shall be finely divided and comply with AS/NZS 3582.3 and ATIC – Specification SP43. Blended Cement Certification 3. Cement for manufacture of concrete shall comply with the requirements of ATIC – Specification SP43. The Cementitious Material Registration Scheme (CMRS) shall be used to confirm that the cement complies with ATIC – Specification SP43. The standard application form for CMRS registration is given in Appendix 820B. 4. Prior to manufacturing of concrete the Contractor shall confirm that the cement complies with ATIC – Specification SP43 and shall provide the CMRS registration number for the cement to the Superintendent for approval of the cement. HOLD POINT 5. The Contractor shall use cement in approximately the chronological order in which it is delivered from the manufacturer. Transportation units and storage bins for bulk cement shall be weatherproof and shall be constructed so that there is no dead storage. The Contractor shall demonstrate that the storage bins for bulk cement do not have any dead storage. If dead storage exists the bins shall be emptied completely at least once every three months. Cement delivered in bags shall be stored in weatherproof structures having floors raised above the ground. Cement that is more than three months old shall not be used. 6. Concrete manufactured from cement not conforming to this Specification or from cement that has deteriorated and become unsuitable for use shall be rejected. MAIN ROADS Western Australia Contract xxx/xx Specification 820 Concrete for Structures Document 04/10134 Issue 17/06/13 Page 7 of 28 820.08 AGGREGATE 1. Fine aggregates for concrete shall be natural sand and shall comply with the requirements of AS 2758.1. The maximum amount of water absorption for fine aggregates shall not exceed 1.5 percent. Testing 2. Coarse aggregates for concrete shall be crushed igneous rock or crushed or screened river gravel conforming to the requirements of AS 2758.1. All coarse aggregates shall be single-sized. Graded coarse aggregates shall not be used. The maximum amount of water absorption for coarse aggregates shall not exceed 2.5 percent. 3. The durability of coarse aggregates shall be assessed according to test methods of AS 2758.1. The acceptance criteria for these tests shall be that for a concrete exposure classification C unless otherwise specified. 4. All aggregates proposed for use in the Works shall comply with the requirements of the "Alkali-Reactive Materials" clause of AS 2758.1. . 5. The Contractor shall provide proper means of storing the aggregates. Each nominal size of coarse aggregate and fine aggregate shall be kept separated and suitable precautions shall be taken to prevent the aggregates from being contaminated by the ground or by wind blown dust or other foreign matter. 6. The grading of the individual aggregates shall conform to the overall limits for these materials given in AS 2758.1. Sampling for the purposes of carrying out tests shall be in accordance with AS 1141. 820.09 WATER 1. Water used in concrete manufacture and curing shall be clean, potable and free from amounts of suspended material or organic matter or alkali salts or any other impurities which may adversely affect the properties of the concrete or have harmful effects on any reinforcement or prestressing system or other fixture embedded therein. 2. Water for concrete shall have a total soluble salts content of not greater than 1 500 milligrams per litre when tested in accordance with MRWA Test Method WA 910.1. Testing 3. The Contractor shall arrange that a suitable supply of water is available at the batching plant. Contractor to Supply 820.10 ADMIXTURES 1. Admixtures may be used in concrete to modify workability but will not be permitted for the purpose of reducing cement content. However, the admixture shall have no harmful effect whatsoever upon the quality of the concrete or upon any reinforcement or prestressing system or other fixture embedded therein. 2. Any admixture shall comply with the requirements of and be used in accordance with AS 1478. 3. Calcium chloride and other chloride-bearing admixtures shall not be used in concrete containing any type of steelwork or steel reinforcement. MAIN ROADS Western Australia Contract xxx/xx Specification 820 Concrete for Structures Document 04/10134 Issue 17/06/13 Page 8 of 28 4. Where two or more admixtures are proposed for incorporation into a concrete mix, their compatibility shall be certified by the manufacturers and the certificates shall be provided to the Superintendent before use of the admixtures. 820.11 ACTION REQUIRED FOR THE CONTROL OF ALKALI AGGREGATE REACTIVITY (AAR) 1. The total mass of reactive alkali in the concrete, including any admixtures, shall not exceed 2.8 kg/m3. The method of determining the alkali content shall be in accordance with Appendix C of Report 3 (TR3) by the Cement & Concrete Association of New Zealand. Testing 2. All aggregates for use in concrete shall be tested for their susceptibility to AAR in accordance with MRWA test method WA624.1 or RTA T363 (Roads and Traffic Authority, NSW). 3. Where the aggregate source has previously been classed as acceptable in accordance with WA624.1 or RTA T363, may be exempt from re-testing at the discretion of the Superintendent. 4. Aggregates shall be classified in accordance with Table 820.1. a) For aggregates classified as non-reactive by WA624.1, no action for control is required b) For course aggregate classified as having potential for slow/mild AAR by WA624.1 with mortar bar expansion between 0.10% and 0.40% at 21 days (fine aggregate between 0.15% and 0.45%), the concrete mix shall either: i. incorporate a proportion of fly ash that is 25% by mass of the total cementitious materials: or ii. be a blended cement (65% Ground Granulated Iron Blast-Furnace Slag + 35% Type GP cement). Fly ash and ground granulated iron blast-furnace slag shall comply with the requirements of AS3582.1 and AS3582.2 respectively. c) Aggregates classified by WA624.1 as having potential for substantial AAR shall not be used. % Expansion at 21 Days Coarse Aggregate Fine Aggregate Aggregate Reactivity Classification < 0.10, < 0.15, Non Reactive ≥ 0.10 to < 0.40 ≥ 0.15 to < 0.45 Having Potential for Slow/Mild AAR ≥ 0.40, ≥ 0.45, Having Potential for Substantial AAR Table 820.1 AGGREGATE REACTIVITY CLASSIFICATION MAIN ROADS Western Australia Contract xxx/xx Specification 820 Concrete for Structures Document 04/10134 Issue 17/06/13 Page 9 of 28 5. The manufacture of concrete shall not occur before the aggregate source to be used has met the test requirements with respect to AAR and approved by the Superintendent. Hold Point 6. The Contractor shall provide the Superintendent with certified test results for both the coarse and fine aggregates for each aggregate source to be used for the manufacture of concrete. The Contractor shall not change the aggregate source without the approval of the Superintendent. 7. The Contractor shall not attempt to produce manufactured fine aggregate from an approved coarse aggregate, unless this action has been shown to have no detrimental effect with respect to AAR. Note: some glassy basalt aggregates are non-reactive in the coarse aggregate form, but can become reactive in crushed fine aggregate form. The incorporation of basalt dust may significantly increase the alkali content of the concrete, and cause deleterious AAR expansion in the presence of a reactive aggregate, in an otherwise non expansive concrete. 820.12 SOLUBLE SALTS 1. Sulphate and chloride ion contents shall be determined by testing of hardened concrete in accordance with AS 1012 Method 20. A representative sample of at least 20 grams of crushed and ground concrete shall be used, with the titrating solution being 0.01 to 0.02 N (normality). The Volhard method calibrated using a concrete with known chloride content shall be used for the test. 2. The sulphate content of concrete as placed expressed as the percentage by mass of acid-soluble SO3 to cement shall not be greater than 5%. 3. The mass of acid-soluble chloride ion per unit volume of concrete as placed shall not exceed 0.4 kg/m3. 820.13 LIMITATIONS ON SHRINKAGE 1. Concrete specimens shall be prepared from the nominated mix in accordance with AS 1012.13 for the purpose of shrinkage testing. The shrinkage of the specimens shall be measured in accordance with AS 1012.13. The shrinkage strain of the concrete specimens after 56 days of drying shall not exceed 600 x 10-6. 820.14 – 820.25 NOT USED DESIGN OF CONCRETE MIXES 820.26 GENERAL 1. The Contractor shall design a mix for each class of concrete specified and shown on the Drawings. The locations for these classes are summarised in Annexure 820A. MAIN ROADS Western Australia Contract xxx/xx Specification 820 Concrete for Structures Document 04/10134 Issue 17/06/13 Page 10 of 28 2. The Contractor shall not change the source and / or the formulation of the binder and the mix proportions of the concrete, unless they have been tested and approved by the Superintendent. 820.27 DURABILITY 1. The intent of this Specification is to provide durable concrete in the permanent works. 820.28 CLASS OF CONCRETE FOR MIX DESIGN 1. All concrete for the Works shall be as specified in Table 820.1 except that blinding concrete and make-up concrete shall be Class N20 in accordance with AS 1379. HOLD POINT 2. Type GP cement only shall be used in all classes of concrete except for class S50M. 3. Class S50M concrete shall use blended cement consisting of 32% Type GP cement, 60% ground granulated iron blast-furnace slag and 8% silica fume. 4. The combined grading shall be within the limits given in Figures 820.1 or 820.2 or 820.3 after making allowance for the permissible tolerances on individual aggregate grading specified in Clause 820.08. CONCRETE CLASS S35 S40 S50 Nominated strength 35 MPa 40 MPa 50 MPa Target strength for mix design 42 MPa 48 MPa 58 MPa Maximum aggregate size 10 mm 20 mm 20 mm Minimum aggregate/cement ratio 3.2 4.0 3.0 Maximum water/cement ratio 0.45 0.43 0.40 350 kg/m3 400 kg/m3 420 kg/m3 Minimum Cement Content TABLE 820.2 NOTE: Concrete Class S35 is to be used in the manufacture of Precast Parapet Panels only. MAIN ROADS Western Australia Contract xxx/xx Specification 820 Concrete for Structures Document 04/10134 Issue 17/06/13 Page 11 of 28 P E R C E N T A G E . P A S S I N G 100 80 65 60 42 40 45 35 31 24 30 23 20 12 2 0 16 9 2 2 0.075 0.15 0.3 0.6 1.18 2.36 4.75 9.5 19 SIEVE SIZE mm FIGURE 820.1 S50 AGGREGATE GRADING ENVELOPE 20mm P 100 E R C 80 E N T A 60 G E 65 42 40 P A S S I N G 45 37 35 29 30 23 20 12 2 16 9 2 2 0 0.075 0.15 0.3 0.6 1.18 2.36 4.75 9.5 19 SIEVE SIZE m m FIGURE 820.2 MAIN ROADS Western Australia Contract xxx/xx S40 AGGREGATE GRADING ENVELOPE 20mm Specification 820 Concrete for Structures Document 04/10134 Issue 17/06/13 Page 12 of 28 P E R C E N T A G E . P A S S I N G 100 80 60 60 46 40 37 28 30 20 14 20 16 12 5 0 4 0.075 0.15 0.3 0.6 1.18 2.36 4.75 9.5 SIEVE SIZE mm FIGURE 820.3 820.29 S35 AGGREGATE GRADING ENVELOPE 10mm TRIAL MIXES 1. The Contractor shall prepare a trial mix for each class of concrete to be used in the Works. Each mix shall use such aggregates that have been tested and approved by the Superintendent. The mixes shall be made using the plant and degree of quality control proposed for the Works. 2. Where the concrete is supplied by an off-site batching plant the Contractor shall arrange for the trial mix to be delivered to the site in a truck agitator or mixer truck of the type to be used for the supply of concrete to the Works. Surplus trial mix concrete may be placed as blinding or make-up concrete. 3. The Contractor shall measure the slump of the trial mix in accordance with AS 1012.3.1 and the value of the slump shall be agreed by the Superintendent. The slump shall be determined prior to the addition of any approved high range water reducer (superplasticiser). Slump Test 4. Once a mix design for a specific class of concrete is adopted the slump of the trial mix shall be deemed to be the slump for that class of concrete and all concrete of this class supplied to the Works shall have the same slump (prior to addition of any superplasticiser), within a tolerance as detailed in AS 1379. 5. The maximum slump of any concrete mix shall be 100mm unless a super-plasticising admixture is used in which case 100mm shall be the maximum slump before addition of the admixture. For concrete containing high range water reducer (HRWR), the initial slump prior to its addition shall not be less than 40 mm unless otherwise approved by the Superintendent. MAIN ROADS Western Australia Contract xxx/xx Specification 820 Concrete for Structures Document 04/10134 Issue 17/06/13 Page 13 of 28 6. The Contractor shall cast not less than 9 and not more than 21 compressive strength test specimens from the trial mix which shall be tested to determine that the strength requirements of this Specification are met. 7. The average 28 day compressive strength of all specimens made from a trial mix shall be not less than the target strength and 70% of all test results shall have compressive strengths within 3MPa of the mean. 820.30 Trial Mixes for Volume of Permeable Voids (VPV) 1. The maximum VPV values, as determined according to AS1012.21, shall not exceed the values given in Table 820.30. Maximum VPV values at 28 days (%) Concrete Class Test cylinders compacted by vibration S35/10 S40 S50 S50M 14 13 12 11 Test cylinders compacted by rodding 15 14 13 12 Table 820.30 VPV limits for various concrete classes 2. Unless otherwise specified, test cylinders shall be cured in accordance with AS 1012. A minimum of 2 cylinders per sample per trial mix shall be taken. Each cylinder shall be tested for VPV at 28 days in accordance with test method AS 1012.21. The average value of the test cylinders shall not exceed the values given in Table 820.30. 3. Should the VPV value exceed as shown in Table 820.30, the Contractor shall take steps to modify the concrete mix design and retest to ensure that the maximum specified VPV value is not exceeded. SUPPLY AND DELIVERY OF CONCRETE 820.31 CONCRETING PLANT 1. The batching plant shall be capable of producing the quantities of concrete at the rates necessary for the efficient and proper placement of concrete in the Works. 820.32 BATCHING AND MIXING 1. The Contractor shall provide and maintain and operate the batching equipment so as to accurately determine and control the amount of each separate ingredient entering the concrete to the tolerances specified in AS 1379. The amounts of cement and sand and each size of aggregate entering each batch of concrete shall be determined by weighing and the amount of water shall be determined by weighing or by volumetric measurement. 2. AS 1379. Mixing of concrete shall comply with the requirements of MAIN ROADS Western Australia Contract xxx/xx Specification 820 Concrete for Structures Document 04/10134 Issue 17/06/13 Page 14 of 28 820.33 TRANSPORT 1. Concrete shall be transported to the Works in a manner preventing contamination, segregation or loss of ingredients. Containers for transporting concrete shall be cleaned at the end of each day's work and whenever concreting is interrupted for more than 40 minutes. 2. In continuous pours the maximum time lag between truck loads on site shall not exceed 20 minutes. 3. Concrete shall be continuously agitated from the time of adding water to the mix until discharge is completed. The use of nonagitating equipment to transport concrete will not be permitted. 820.34 TEMPERATURE AT POINT OF DELIVERY 1. Placement of concrete will only be permitted providing: Hot Weather Concreting a) The concrete mix temperature during placement shall at no time exceed 32°C. AND, EITHER b) The ambient shade temperature is less than 38°C and falling. OR c) The ambient shade temperature is less than 38°C and rising, but placement can be completed before the ambient temperature exceeds 38°C. 2. To keep the concrete maximum temperature below 32°C it may be necessary to shield and/or wet the aggregate stockpiles, chill the mixing water or schedule concrete placement at night. 3. When the ambient shade temperature is greater than 32°C suitable means shall be provided by the Contractor to avoid premature stiffening of concrete placed in contact with hot dry surfaces. Where necessary the surfaces against which concrete is to be placed including reinforcement and formwork shall be sprayed with water to prevent excessive absorption of water from the fresh concrete. 820.35 MIX CONSISTENCY 1. The Contractor shall check the consistency of all concrete by measurement of the slump in accordance with AS 1012.3.1. The Contractor shall supply a minimum of one full set of Slump Testing equipment for this purpose for the period of the Contract. In general, slump tests shall be carried out close to the concrete discharge point. 820.36 Slump Test ADDITION OF WATER TO THE MIX AFTER MIXING 1. Excessive over-mixing shall not be permitted and any concrete which has been retained in the mixer so long that it requires additional water to permit satisfactory placing shall be rejected. 820.37 SAMPLING OF CONCRETE FOR STRENGTH MAIN ROADS Western Australia Contract xxx/xx Specification 820 Concrete for Structures Document 04/10134 Issue 17/06/13 Page 15 of 28 1. Sampling procedures for concrete shall conform to AS 1012 and from each sample of concrete taken for the purpose of checking the 28 day compressive strength not less than 3 test specimens shall be cast. 2. The Contractor shall have available not less than fifteen steel moulds for making concrete compression test specimens. For the period of large concrete pours the Contractor shall supply adequate extra moulds to meet the increased frequency of sampling required. 3. Where it is required to determine the compressive strength of concrete prior to 28 days, e.g. to determine stripping times for formwork or to assess when prestressing force may be applied, the Contractor shall cast additional test specimens and they shall be cured under similar conditions to the concrete they represent. 820.38 STRENGTH OF CONCRETE DELIVERED 1. Concrete from any class shall be deemed to conform with the strength requirements of this Specification if: a) Every concrete sample has a 28 day compressive strength greater than 95% of the nominated strength, AND b) The average 28 day compressive strength for any group of four consecutive samples is equal to or greater than the nominated strength. 2. Consecutive samples for the same class of concrete are not restricted to a single pour. 3. For a group of samples failing to comply with sub-clause 1(b) above that concrete represented by the lowest strength sample shall be liable to rejection. 4. If at any time during the progress of the Works any mix is found to be unsatisfactory or it becomes necessary to use materials differing from those originally approved then the Contractor shall prepare revised mix designs and prepare trial mixes for testing in accordance with Clause 820.29 prior to their use being approved. Otherwise for any particular class of concrete the Contractor shall not vary the properties of the materials used or their relative proportions from those of the approved trial mix. 820.39 CURING AND TESTING OF SPECIMENS FOR DETERMINATION OF COMPRESSIVE STRENGTH 1. Within 36 hours all test specimens taken for the purpose of checking compressive strength shall be placed under standard moistcuring conditions as defined in AS 1012. Continuous standard moistcuring conditions shall be maintained on the test specimens, until the required curing period has elapsed and the test specimens are removed for the purpose of compressive strength testing. Curing 2. If the requirements of sub-clause 1 above can not be satisfied through the utilisation of off site testing facilities then the Contractor shall be required to establish on-site curing and testing facilities. On-site facilities MAIN ROADS Western Australia Contract xxx/xx Specification 820 Concrete for Structures Document 04/10134 Issue 17/06/13 Page 16 of 28 820.40 – 820.50 NOT USED OPERATIONS 820.51 GENERAL 1. Requirements for falsework shall be in accordance with Specification 819 FALSEWORK. Falsework 2. Requirements for formwork shall be in accordance with Specification 821 FORMWORK. Formwork 3. Requirements for steel reinforcement shall be in accordance with Specification 822 STEEL REINFORCEMENT. Reinforcement 820.52 PLACING CONCRETE 1. Concrete shall be deposited as near as possible in its final position and shall be placed in a manner which will prevent segregation. It shall be spread in horizontal layers with the first layer not exceeding 350 mm in compacted thickness and the thickness of subsequent layers limited to 75% of the length of the immersion vibrators being used. Placing shall be continuous between specified or approved construction joints. 2. Where chutes are used to convey concrete their slopes shall be such as to avoid segregation. Concrete shall not be allowed to fall freely more than 2.0 m unless suitable chutes or baffles or other devices are provided to prevent segregation. 3. Screeding of the deck or top surface of the structure shall progress in a longitudinal direction with the screed boards operated at right angles to the centreline of the deck or top surface. Screed guides shall be accurately set and rigidly fixed in position. Guides shall be of robust construction and shall be capable of sustaining construction loadings without undue or permanent deflection. 4. Concrete shall not be placed in standing water. 5. All concrete in a batch shall be placed in its final position and compacted within 90 minutes of adding water to the mix. 6. Prior to the placement of any concrete, the Contractor shall certify to the Superintendent that all falsework, formwork, reinforcement and other embedded items, levels, placement procedures and curing procedures to be employed comply with the requirements of the Specification. 820.53 HOLD POINT CONSTRUCTION JOINTS 1. The location of all construction joints shall be as indicated on the Drawings. Construction joints shall be made on true vertical and horizontal planes, or as otherwise shown on the Drawings. The surface of the hardened concrete shall be treated to remove all laitance and expose the aggregate so as to provide a thorough bond with concrete cast subsequently. The roughened surface shall be thoroughly cleaned to remove loose chips and any foreign matter. MAIN ROADS Western Australia Contract xxx/xx Specification 820 Concrete for Structures Document 04/10134 Issue 17/06/13 Page 17 of 28 2. Immediately before fresh concrete is cast against the joint the hardened concrete surface shall be thoroughly wetted. 820.54 820.54.01 COMPACTION MINIMUM EQUIPMENT 1. Before commencement of each concrete pour, sufficient vibrators and spares shall be available and tested. The number of working vibrators required shall be not less than one for each 4 cubic metres of concrete placed per hour. The number of standby vibrators shall be not less than 25% of the number of working vibrators with a minimum of 1. HOLD POINT 2. The required number of vibrators for a given rate of placing concrete shall be continuously used during the pour. 3. Immersion vibrators shall be of the rotary out of balance type with a frequency of not less than 150 Hertz and, where the specified concrete finish is Class 2 or 3, shall be fitted with approved rubber caps. The largest practical size of vibrator should be used. 820.54.02 OPERATION 1. The concrete shall be properly compacted throughout the full extent of each layer so as to produce a concrete that is uniformly plastic, dense, free of all entrapped air and the finished work shall be a dense and uniform mass free of voids, segregation, honeycombing and showing a uniform face as specified when the forms are removed. Layers of concrete shall not be placed until layers placed previously have been thoroughly compacted. 2. Compaction of concrete shall be carried out by approved power-driven immersion vibrators applied in such a manner as will ensure the concrete is satisfactorily and uniformly compacted. Immersion vibrators shall penetrate the full depth of the layer and where the underlying layer is of fresh concrete, shall penetrate that layer a minimum of 100mm to ensure that successive layers are well knitted together. Immersion vibrators shall be withdrawn slowly to prevent the formation of voids. Vibrators shall not be used to work the concrete along the forms or in such a way as to damage formwork. 820.54.03 ADDITIONAL REQUIREMENTS FOR BRIDGE DECK CONCRETE 1. Compaction of deck concrete shall be carried out using approved vibrating screeds in addition to immersion vibrators followed by screeding with a "bull float" and finishing with a mechanical trowelling machine. 2. Concrete at the top surface of bridge decks must be a rough-textured surface suitable for bituminous surfacing. This surface can be produced with a rough mechanical trowelling or any method that is approved by the Superintendent. A smooth finish will not be permitted except at the locations to be covered with a preformed waterproof membrane. MAIN ROADS Western Australia Contract xxx/xx Specification 820 Concrete for Structures Document 04/10134 Issue 17/06/13 Page 18 of 28 820.55 FINISHING OF UNFORMED SURFACES 820.55.01 GENERAL 1. The type of finish and surface texture required in each part of the Works shall be as shown on the Drawings. 820.55.02 ALLOWABLE TOLERANCES 1. Unformed concrete surface finishes shall be as designated on the Drawings with reference to the classifications given in Table 820.4. Designated Finish Type of Concrete Finish Maximum Allowable Surface Irregularities U1 A wood floated finish to produce a uniform surface without surface pitting or cavities. 5mm abrupt or 15mm in a 3m template. U2 A high quality steel trowelled finish having a dense smooth impervious finish without surface pitting or cavities. Nil abrupt or 5mm in a 3m template. U3 A high quality mechanical steel trowelled finish having a dense impervious finish without surface pitting or cavities. 2mm abrupt or 5mm in a 3m template. U4 A wood floated surface with a broomed finish. 3mm abrupt or 5mm in a 3m template. TABLE 820.4 820.55.03 UNFORMED SURFACE FINISHES FOR CONCRETE BROOMED FINISH 1. Broomed surfaces shall be obtained by finishing with a wood float followed by brooming transversely to the principal slope direction, or perpendicular to the edges. The broomed finish shall contain grooves between 1mm and 3mm deep spaced between 2mm and 6mm apart so as to provide a non-slip surface. 820.56 CURING OF CONCRETE 1. Freshly placed concrete shall be protected from the sun, wind and rain and prevented from drying out too quickly. 2. Curing shall commence immediately after the concrete has achieved its final set. 3. The minimum curing period for structural concrete shall be 7 days. The minimum curing period for concrete Class S50M and any other concrete incorporating ground granulated blast furnace slag, silica fume or fly ash shall be 14 days. MAIN ROADS Western Australia Contract xxx/xx Specification 820 Concrete for Structures Document 04/10134 Issue 17/06/13 Page 19 of 28 4. methods: All concrete surfaces shall be cured by one of the following a) By covering with sand or hessian or foam which is kept permanently wet. b) By wrapping with polythene or similar film to provide an airtight cover. c) By maintaining the formwork in position for the required curing period. d) By spraying with an approved curing compound complying with the requirements of AS 3799. Such curing compound shall be applied in accordance with the manufacturer's published recommendations. 5. If the Contractor proposes to use a spray-on curing membrane on the top surface of the bridge deck the Contractor shall remove it by an approved means immediately before application of the surfacing. 6. Concrete deck slabs shall also be treated with an approved aliphatic-alcohol based evaporation retardant coating applied according to the manufacturer's published recommendations immediately after the surface has been initially screeded. 7. The Contractor shall ensure that the method of curing shall not result in any staining of exposed surfaces of concrete. 820.57 PROTECTION OF CONCRETE SURFACES 1. The Contractor shall protect all completed surfaces from damage and staining from any source including rain water and concrete spillage and grout spillage and contact with hardwoods and ferrous metals. Where a delay is likely prior to casting the next concrete pour such that reinforcement bars protruding from completed sections may cause staining to exposed parts of the finished Works, then the bars shall be suitably treated to prevent rusting. 2. Where any damage or staining has occurred to completed concrete surfaces the affected section shall be deemed to be nonconforming. The method of repair or removal shall in no way harm or damage the adjacent section of the Works. 820.58 – 820.80 NOT USED AS BUILT AND HANDOVER REQUIREMENTS 820.81 – 820.90 NOT USED CONTRACT SPECIFIC REQUIREMENTS 820.91 – 820.99 NOT USED MAIN ROADS Western Australia Contract xxx/xx Specification 820 Concrete for Structures Document 04/10134 Issue 17/06/13 Page 20 of 28 ANNEXURE 820A CLASS OF CONCRETE Class of Concrete S35/10 Works Component Precast parapet panels S40 Normal superstructures and substructures in non-marine environments Approach slabs End treatments and base slabs for major box culverts S50 Special superstructures S50M MAIN ROADS Western Australia Contract xxx/xx Reinforced concrete substructures in marine environments Specification 820 Concrete for Structures Document 04/10134 Issue 17/06/13 Page 21 of 28 ANNEXURE 820B ATIC CEMENTITIOUS MATERIALS FOR CONCRETE REQUEST FOR REGISTRATION BY MANUFACTURER Cement or Blend Details Product Name Type Proportions Manufacturer Place of Manufacture Source of Constituent Materials Cement Clinker Fly Ash Slag Limestone Gypsum Grinding Aids Supply Details Dispatching Supplier Contact Name Contact Phone No. Contact Address Suppliers ABN Send this form with the sample to: RTA Chemical and Materials Laboratory For RTA Laboratory Use Only: Date of Registration: Att: Laboratory Officer Registration No: Unit H, 75 St. Hilliers Rd, Auburn NSW 2144 MAIN ROADS Western Australia Contract xxx/xx Specification 820 Concrete for Structures Document 04/10134 Issue 17/06/13 Page 22 of 28 SPECIFICATION 820 GUIDANCE NOTES DELETE THESE GUIDANCE NOTES FROM FINAL DOCUMENT AFTER USING FOR REFERENCE All edits to downloaded TDP documents shall be tracked (most word processing software allows this to be done automatically). Deletions shall be struck through e.g. example. Insertions shall be in italics e.g. example. If all information relating to a clause is deleted then the clause number should be retained and the words "NOT USED" should be inserted. The proposed documents with tracked changes shall be submitted to the Project Manager for review, prior to printing the final batch of documents. When this final printing is carried out, the tracked changes option is to be turned off. The Custodian of this specification is the Structures Design and Standards Engineer. 1. CLASS OF CONCRETE 1.1 The description in Annexure 820A may need to be modified to clarify where each class of concrete applies. Class S50M concrete is a class that has been used for marine environments. Its performance is being monitored. Where this does not apply, the words, “ … except for class S50M … (through to and including) … material with silica fume’ in Clause 820.28.2 should be deleted. 2. STEAM CURING (Clause 820.91) 2.1 Clause 820.91 Steam Curing refers to precasting operations, and should be added if applicable. 2.2 This clause may be useful when the steam curing of PSC beams, piles, culverts or other concrete elements is required. 3. TRAFFIC RESTRICTIONS 3.1 If applicable, restrictions to traffic to allow maturation of concrete may need to be included – insert as Clause 820.92 where applicable. 4. LIMITATIONS ON MAXIMUM COMPRESSIVE STRENGTH 4.1 Subject to investigation for special projects – insert as Clause 820.93 where applicable. 5. LIMITATIONS ON SHRINKAGE (Refer also CLAUSE 820.13) 5.1 Subject to investigation for special projects – insert as Clause 820.94 where applicable. 5.2 Delete clause 820.13 if the specific value of shrinkage has been nominated and used in the design as given on the Drawings. Amend “Not Used” clause range accordingly. 6. VARIATION OF NOMINATED MIXES 6.1 Subject to investigation for special projects – insert as Clause 820.95 where applicable. MAIN ROADS Western Australia Contract xxx/xx Specification 820 Concrete for Structures Document 04/10134 Issue 17/06/13 Page 23 of 28 7. CLAUSE 820.35 MIX CONSISTENCY 7.1 For rural Contracts where mobile concrete batch plant facilities are used, one (1) slump test must be carried out on each truck delivered to Site. MAIN ROADS Western Australia Contract xxx/xx Specification 820 Concrete for Structures Document 04/10134 Issue 17/06/13 Page 24 of 28 CONTRACT SPECIFIC REQUIREMENTS TO ADD OR DELETE The following clauses are to be placed under the CONTRACT SPECIFIC REQUIREMENTS as required. Note that if more than 1 Clause is required the Clause numbers may be varied within the range allocated to this section to suit the requirements of the project and the remaining “Not Used” numbers adjusted accordingly. Also the Clause number and heading style should be altered to, “H2 DSB” so that it will be included in the specification Contents page. 820.91 820.91.01 STEAM CURING GENERAL 1. This section of the Specification covers the curing of precast concrete units in an atmosphere saturated with water vapour at a pressure not exceeding atmospheric pressure. 2. The method of control and the proposed curing cycle to achieve the specified concrete compressive strength are the responsibility of the Contractor, but shall be in accordance with this Specification. 3. The Contractor shall take measures to allow for the potential lower 28-day compressive strength obtained from test cylinders cured initially under in-situ conditions, as compared to those cured in accordance with the requirements of AS 1012. 820.91.02 STEAM COVERS 1. To prevent drying out, steam covers shall be placed over the units immediately following the casting and screeding operations in such a manner as to ensure free circulation of the steam around the concrete mass. 820.91.03 CURING CYCLE 1. After an initial "maturity " of 40°C hours, but not less than 2 hours after batching the last batch of concrete for the units, steam shall be admitted to the steam covers at such a controlled rate that the maximum average temperature rise shall not exceed 24°C per hour and the temperature rise in any one 15 minute period shall not exceed 6°C. (Note: The initial "maturity" period is calculated by dividing 40°C hours by the concrete temperature of the last batch of concrete placed in the unit. The concrete temperature is as measured on an indicating thermometer). MAIN ROADS Western Australia Contract xxx/xx Specification 820 Concrete for Structures Document 04/10134 Issue 17/06/13 Page 25 of 28 2. If the admission of steam to the steam covers is delayed by more than the initial specified "maturity" of 40°C hours after the completion of placing of concrete, water curing, shall be applied until steaming commences. 3. Steaming shall continue at a rate such that the temperature rise shall not exceed 24°C per hour, until a temperature under the steam covers of not greater than 75°C has been reached. The steam supply shall then be reduced to maintain the temperature at 70°C ± 5°C. 4. After the elapse of sufficient time at the maximum temperature for the required concrete properties to have been reached, steam shall be completely shut down. Steam covers shall not be removed nor any part of the concrete units and test cylinders disturbed in any way until the temperature under the steam covers has fallen to within 30°C of the ambient temperature. The rate of loss of temperature under the steam covers after shutting off steam shall not exceed 24°C per hour. 820.91.04 TEMPERATURE CONTROLS 1. Temperature shall be recorded by means of recording thermometers. The temperature sensitive parts of the thermometers shall be so positioned under the steam covers as to record the minimum temperature under the covers. One recording thermometer shall be used for each unit or group of units in line up to a total length of 25m. For greater lengths, additional recording thermometers shall be used and the distance between the temperature sensitive parts of the thermometers shall not exceed 25m. 2. The recording thermometers shall be set in operation immediately upon completion of casting and screeding. 3. Charts shall not be removed from any recording thermometers, nor the recording thermometers disturbed or moved in any way until after the removal of the steam covers. 4. retained. Charts from temperature recording thermometers shall be 5. The following information shall be recorded on the chart: a) date on which steaming commenced; b) unique identification and description of concrete unit; c) temperature correction, if any; d) time correction, if any; e) batching of concrete; f) temperature of concrete when placed; g) ambient temperature at time of removal of steam covers; and h) name of Contractor and manufacturer. MAIN ROADS Western Australia Contract xxx/xx Specification 820 Concrete for Structures Document 04/10134 Issue 17/06/13 Page 26 of 28 820.91.05 STEAM DELIVERY 1. Under no circumstances shall steam jets be allowed to impinge upon any part of the concrete units or of a test specimen, or of their formwork or moulds. Neither shall any steam delivery pipe be attached directly to any formwork or moulds in such a manner as may cause localised overheating of the concrete. 2. Sufficient steam jets or steam entry points shall be provided to ensure that a substantially uniform temperature is maintained under the steam covers such that the difference in temperature between any two points adjacent to the concrete units is not more than 10°C. 820.91.06 EXTENT OF STEAM CURING 1. Unless otherwise specified, steam curing shall be continuously applied until at least the 7 day compressive strength for the specified concrete grade is obtained. 820.91.07 PARTIAL STEAM CURING 1. Where steam curing is used only to obtain sufficient compressive strength for removal of forms or for lifting, curing shall be continued by one or a combination of the methods specified in Clause 820.56, for a minimum period of 7 days. 820.91.08 CURING OF TEST CYLINDERS 1. Concrete compression test cylinders shall be placed near the concrete units, and shall be so positioned under the steam covers as to be midway between 2 adjacent points of steam entry, subject always to their being no closer to any points of steam entry than half the width of the concrete units. Test cylinders shall be positioned in a group at the lower face of the concrete unit and shall in no case be placed on top of the concrete unit or its formwork. 2. Test cylinders shall remain in position under the steam covers until the steam curing cycle is complete. Test cylinders shall be suitably covered in such a way as to minimise moisture and temperature losses between the time of removal from the steam covers and the time of forwarding to an accredited laboratory for testing. Cylinders shall be transported in moisture proof containers. MAIN ROADS Western Australia Contract xxx/xx Specification 820 Concrete for Structures Document 04/10134 Issue 17/06/13 Page 27 of 28 SPECIFICATION AMENDMENT CHECKLIST Specification Name: No: 820 STRUCTURES Revision No: _____Title: CONCRETE FOR Project Manager: Name: _______________Signature: ______________Date:______ Checked By: Name: _______________Signature: _______________Date:______ Contract No: ______Contract Description: ______________________________ ITEM DESCRIPTION SIGN OFF All changes/amendments must be shown in Tracked Change mode until Note: approved. 1. Project Manager has reviewed Specification and identified Additions and Amendments. 2. CONTRACT SPECIFIC REQUIREMENTS addressed? – Contract specific materials/products/clauses added? (Refer Specification Guidance Notes for guidance). 3. Any unlisted Materials/Products proposed and approved by the Project Manager? – if “Yes” provide details at 15. 4. Standard Clauses amended? – MUST SEEK approval from MCP. 5. Clause deletions shown as ‘NOT USED’. 6. Appropriate INSPECTION & TESTING parameters included in Spec 201 (Test Methods, Minimum Testing Frequencies verified). 7. ANNEXURES completed (Refer Specification Guidance Notes). 8. HANDOVER and AS BUILT requirements addressed. 9. Main Roads QS has approved changes to SMM. 10. Project Manager certifies completed Specification reflects intent of the design. 11. Completed Specification – independent verification arranged by Project Manager 12. Project Manager’s review completed. 13. SPECIFICATION GUIDANCE NOTES deleted. 14. TABLE OF CONTENTS updated. 15 Supporting information prepared and submitted to Project Manager. Further action necessary: Signed: MAIN ROADS Western Australia Contract xxx/xx (Project Manager) Date:_______________ Specification 820 Concrete for Structures Document 04/10134 Issue 17/06/13 Page 28 of 28