Asset Management Plan Template for Bridges

advertisement
TRIM Document N°: D12#56469
Issue Date: 24 January 2012
ASSET MANAGEMENT PLAN TEMPLATE FOR
BRIDGES
This document is owned and controlled by the Director Operational Asset Management. The
Structures Operational Asset Management Manager is the delegated custodian. All
comments and requests for change should be submitted to the Structures Operational Asset
Management Manager.
Printed copies are uncontrolled unless marked otherwise
Authorisation
Reviewed by
Approved by
Revision
0
File No.: 08/5675
Manager Operational Asset Management
Regional Services Directorate
Director Operational Asset Management
Regional Services Directorate
Description of Amendment
Original Issue
Date
24/01/2012
Revision date
24/01/2012
Author’s Notes:
Introduction:
This template has been created to provide a uniform and consistent approach to preparing Asset
Management Plans (AMP) for bridges across all Main Roads’ Regions.
This page shall be deleted by the Author when creating the AMP.
In writing each section, the Author shall keep in mind the AMP Framework as described in
Section 1.
Template Revision Status:
TEMPLATE REVISION STATUS
Rev. No.
Date Issued
Description
Submitted
Endorsed
A
22-Aug-2011
Final issue for internal review
Michael
Kakulas
Peter
Newhouse
B
16-Sep-2011
Final issue for use
Michael
Kakulas
Peter
Newhouse
This table is to keep track of the revisions to this template. The Template Rev number in the
footer shall not be changed and the Author should be using the REVISION STATUS section of
the AMP.
Multiple Bridges:
This template has been specifically written to suit a single bridge. However, any number of
bridges could be included in the same plan if they are likely to be managed as one group of
structures. For example, they could be along the same section of road, constructed at the same
time and/or have similar physical and environmental characteristics. The Asset Manager shall
determine which bridges can be grouped in the one Plan. In this case, any differences between
the bridges shall be described by exception.
Text Legend:
Text in black should generally be left as is, but can be modified as required.
Italics and blue are comments to guide the author in what is required in that section and must be
deleted and replaced with the author’s text.
Black text in yellow highlight may need to be changed but has been included as a starting point
for the author. Irrelevant items shall be deleted. The highlight shall be removed in the final
version.
Appendices:
It is intended that the Appendix numbering is fixed. If an Appendix is not used, then state “Not
Used”. If additional appendices are required, then these should be added at the end.
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page ii
Styles Index:
The following styles are to be used. These are not to be modified and new ones should not be
created.
Heading 1
Heading 2
Heading 3
Heading 4
Table Caption
Dot Point
Appendix Heading 1
Para – used for general text
Table Body Text
Table Heading Text
Table Notes
The following styles are used in the document, but should not be used by the author. These are
included here for completeness only.
Author’s Notes
Author’s Notes in Table Body
Title
TOC 1
TOC 2
TOC 3
Footer
Table of Figures
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page iii
ASSET MANAGEMENT
PLAN
BRIDGE No. XXXX ON XXXX XXXX
OVER XXXX XXXX
Insert photo here of bridge
XXXX Region
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page iv
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page v
TRIM Document No. XX/XX/XX
Date Issued: XX XXXXXX XXXX
ASSET MANAGEMENT PLAN
Bridge No. XXXX on XXXXXX
over XXXXXX
This Asset Management Plan is owned and controlled by the Director XXXXXX Operations/Regional Manager
XXXXXX Region (delete as appropriate).
The Asset Manager Structures, XXXXXX Region is the delegated custodian. All comments and requests for
changes should be submitted to the delegated custodian.
AUTHORISATION
As the Director XXXXXX Operations/Regional Manager XXXXXX (delete as appropriate) in Main Roads Western
Australia, I authorise the issue and use of this Plan.
DIRECTOR XXXXXX OPERATIONS/REGIONAL MANAGER XXXXXX (delete as appropriate).
Date:
/
/
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page vi
This Asset Management Plan forms an integral part of the XXXXXX Region Asset Management
Strategy.
This Plan describes the physical attributes, levels of service requirements and risks associated
with Bridge No. XXXX. It also details the responsibilities, inspection, maintenance and upgrade
activities and financial resources required to minimise these risks while delivering the required
levels of service.
All staff involved with the management of this asset are expected to conform to the requirements
of this Asset Management Plan.
SUBMITTED:
Author Name
AUTHOR POSITION
AUTHOR ORGANISATION or REGION (if Main Roads)
ENDORSED:
Name
ASSET MANAGER STRUCTURES
XXXXXX REGION
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page vii
REVISION STATUS
The following table contains a summary of the revision status of this document.
REVISION STATUS SUMMARY SHEET
Rev. No.
Date Issued
Description
Submitted
Endorsed
0
XXXXXX
Issue for use
XXXXXX
XXXXXX
1
XXXXXX
XXXXXX
XXXXXX
XXXXXX
Insert additional rows as required
Prior to Rev 0 - Issue for Use, the Author shall keep track of draft issues by using the A, B, C etc
numbering system. These shall then be deleted at Rev 0.
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page viii
CONTENTS
1.
Framework for Asset Management Activities
2
1.1
1.2
Asset Management Plan
Bridge Management System
2
3
2.
Asset Description
4
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
Bridge History
Bridge Description
Cost
Design Criteria
Services
Land Ownership
As-Constructed Condition
Current Condition
Current Load Rating
4
4
5
5
6
7
7
7
9
3.
Key Drivers
11
3.1
3.2
3.3
3.4
Levels of Service
Regulatory Requirements
Stakeholder Requirements
Physical Environment
11
11
12
13
4.
Current Performance
14
4.1
4.2
4.3
4.5
Introduction
Levels of Service
Regulatory Requirements
Physical Environment
14
14
14
14
5.
Bridge Strategy
15
5.1
5.2
5.3
Corporate Strategy
Regional Strategy
Bridge Strategy
15
15
16
6.
7.
Risk Management
Operational Plans
17
19
7.1
7.2
7.3
7.4
7.5
Load Rating
Inspection Plan
Maintenance and Specific Work Plans
Contingency Plan
Financial Plan
19
19
21
25
25
8.
9.
10.
Responsibilities
Opportunities for Improvement
Asset Management Plan Update
27
29
30
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page ix
APPENDICES
Appendix A
Appendix B
Appendix C
Appendix D
Appendix E
Appendix F
Location of Bridge No. XXXX
General Arrangement Drawing(s)
Reference Documents
Definitions
Manufacturer Product Details
Photographs
31
32
33
34
35
36
TABLES
Table 1
Table 2
Table 3
Table 4
Table 5
Table 6
Table 7
Table 8
Table 9
Table 10
Table 11
Table 12
Table 13
Table 14
Bridge Component Description
Summary of Design Life for Different Components
Summary of Durability Criteria for Bridge Components
Services
Load Rating
Levels of Service
Risk Table
Inspection Plan
Routine Maintenance Plan
Preventative Maintenance Plan
Specific Works Plan
Contingency Plan
Financial Plan
Responsibilities of Various Agencies
4
5
6
6
9
11
17
20
22
23
24
25
26
27
FIGURES
Figure 1
Asset Management Framework
Main Roads Western Australia
Template Rev A
2
Asset Management Plan – Bridge No. XXXX
Page x
EXECUTIVE SUMMARY
This Asset Management Plan (AMP) outlines the required asset management activities for
Bridge No. XXXX. It has been developed as an operational guide and scheduling tool for use
by the Regional Asset Manager Structures, providing a framework around which the inspection,
maintenance, refurbishment and upgrading of the bridge can be assessed and undertaken.
Bridge No. XXXX on XXXXXX over XXXXXX is … add short description of bridge
Include brief statement about bridge strategy.
State who is responsible for the bridge.
There are no major issues with this bridge.
OR
The following is a summary of the major issues relating to the bridge.
Highlight any major deficiencies in the condition of the bridge. Describe how this is affecting the
current performance now or how it could affect it in the future.
List any major or exceptional risks with this bridge.
Highlight any major or exceptional inspection and maintenance activities required at the bridge
in the foreseeable future.
List any major financial commitments.
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page .1
1.
FRAMEWORK FOR ASSET MANAGEMENT ACTIVITIES
1.1
Asset Management Plan
This Asset Management Plan (AMP) is a working document to be used as a tool for the
management of Bridge No. XXXX. It describes the bridge, its operating environment,
associated risks, required levels of service and key activities to ensure that the bridge meets
these levels of service during its service life.
This AMP provides a detailed guide for appropriate asset management practices, processes
and activities specific to the bridge. When implemented, these will aid in efficiently managing
the physical and operational attributes of the structure so as to prolong its life whilst maintaining
defined levels of service.
Figure 1 diagrammatically shows a framework for the cycle of bridge management activities.
There are six phases to the framework which are mapped to the nine remaining sections of the
AMP. For reference, the section numbers corresponding to each phase are displayed on the
outer ring of the diagram. The framework shows how one phase feeds into the next.
Figure 1 Asset Management
Framework
10
2
9
8
Opportunities for
Improvement & AMP
Update
What are we
managing?
• Improvement to the asset
management activities
undertaken
• When should the AMP
be updated?
• As Designed Condition
• As Constructed Condition
• Current Condition
Description of the bridge:
3
How do we plan those
activities and who is
responsible?
How is bridge performing against key drivers?
• Levels of Service
• Key Stakeholders
• Regulatory Requirements
• Physical Environment
• Current Performance
• Responsibility Matrix
• Operational Plans
7
How do we determine
what activities are
required?
7
• Risk Assessment
• Inspection and condition
assessment
• Load Rating
6
Main Roads Western Australia
Template Rev A
4
What is the bridge
stratgey?
• Corporate Strategy
• Regional Strategy
• Bridge Strategy
5
Asset Management Plan – Bridge No. XXXX
Page .2
1.2
Bridge Management System
The Bridge Management System (BMS) is being progressively developed and will ultimately
contain the following modules:







Programme Management
Bridge Enquiry
Bridge Inventory
Inspections
Load Rating & Heavy Vehicles
Evaluation & Strategic Review
Administration
The BMS has many functions, including a suite of tools to assist asset managers to do their
work. In particular, it provides a system to develop optimum works programmes and capture
the cost of works against the bridge. The system records the decision making behind the
development of works programmes and supports consistent asset management planning across
regions in Main Roads.
The BMS contains bridge information and provides links to other systems containing bridge
information (e.g. IRIS). This information includes inventory data, condition data, planned and
completed work items, photographs, drawings and reports. In particular, there are electronic
links between the BMS and AMPs.
It is important that information is not unnecessarily duplicated in the BMS and AMPs. Where
information and data is available in the BMS, the AMP will provide summary information only
and reference the BMS as the source of more detailed information.
In general, the AMP is a strategic document, typically updated on a 5 or 7 yearly cycle
depending on bridge type. The AMP identifies required asset management activities such as
maintenance. The BMS is the system that is used to schedule and deliver work. It generally
contains more detailed information which is updated frequently depending on the type of
information.
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page .3
2.
ASSET DESCRIPTION
2.1
Bridge History
Provide short description of crossing history, e.g. Why was a bridge required at this location? Is
this the first crossing or is it replacing an existing structure. Or have there been major changes
to the bridge structure (e.g. new footpath added or additional lanes).
Could also add here, if relevant, the project under which the bridge was constructed and who
was the construction contractor, designer, project manager etc. Also include when construction
started and finished, and when the bridge was opened to traffic.
2.2
Bridge Description
Provide short description of the bridge; include total length, number of spans, overall width,
width between kerbs, type of bridge, construction methodology. Make reference to Location of
Bridge in Appendix A, General Arrangement Drawing(s) in Appendix B and Photographs in
Appendix F.
Also, include road configuration on the bridge e.g. traffic lanes, turning lanes, shoulders,
median, shared paths etc. Also include any allowance for future widening or changes to lane
configuration.
A detailed description giving key dimensions and materials used is provided in Table 1 below.
Add/delete as required. The component titles are prompts only.
Table 1
Bridge Component Description
Component
Description
Superstructure
Describe deck type and configuration (e.g. simply supported or continuous, number
of spans and length, deck width, precast or cast in-situ, box girder or flat slab etc).
Parapet and Barrier
Describe parapet and barrier type (including materials and protective coatings
used).
Pedestrian Walkway
Handrail
Describe balustrade type (including materials and protective coatings used).
Road Surfacing
Describe type and thickness of road surfacing. Add details of any waterproof
membrane on deck.
Approach Slabs
Describe approach slab.
Piers
Describe pier configuration and foundation type.
Abutments
Describe abutments (e.g. shape, type of walls and whether deck independently
supported).
Wing Walls
Describe wing wall type.
Anti-graffiti Coating
Describe location, type and manufacturer of anti-graffiti coatings. Full details in
Appendix E.
Expansion Joint
Describe location, type and manufacturer of expansion joints. Full details in
Appendix E.
Bearings
Describe location, type and manufacturer of bearing. Full details in Appendix E.
Traffic Barrier
Describe type of traffic barrier on the bridge and on the approaches/departures
including end terminations.
Drainage
Describe drainage system on bridge (i.e. none, scuppers that drain direct to river or
scuppers to a captive drainage system).
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page .4
2.3
Cost
The total original construction cost for the bridge, built in XXXX, including design fees and
contractor overhead and profit, was $XX.XM.
The current written-down value of the bridge is $X,XXX,XXX while the current replacement
value is $X,XXX,XXX.
2.4
Design Criteria
The information in this section would typically only be known for new bridges. For existing
bridges, under each section, add known information or state that the information is not known.
2.4.1 Structural Capacity
The design loads are given in the Final Structural Design Report referenced at Appendix C.
The bridge was designed for the following design vehicles: SM1600, T44, HLP 320 and all
Group 1 vehicles.
The bridge has a differential settlement allowance of XXmm at the abutments and XXmm at the
piers.
The vessel impact design loading is XXXXXX.
2.4.2 Geotechnical Capacity
Provide reference to geotechnical investigations, analysis and final design of the foundations.
Provide general description of the underlying geology and how this has affected the design and
construction of the structure (only relevant for new structures).
2.4.3 Design Life
The concept of design life is the expected time during which the structure will perform its
intended purpose with regular inspection and maintenance, but after which major refurbishment
works could be expected.
In accordance with XXXXXX (state reference here if available) the nominated design life for the
bridge is 100 years.
The design life for various components is given in Table 2 below. Add/delete as required.
Table 2
Summary of Design Life for Different Components
Component
Design Life
Structural components
100 years
Protective coatings to steelwork
25 years
Road surfacing of dense graded asphalt
15 years
Anti-graffiti paint
10 years
Bearings
50 years
Expansion joints
25 years
Electrical assets (e.g. switchboards)
15 years
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page .5
2.4.4 Durability and Exposure Classification
A separate Durability Plan was prepared for the bridge to achieve the specified design life for
the major structural components (ref. Appendix C). The Durability Plan provides an assessment
of the environment in which the structure is to be constructed and establishes minimum
performance requirements to achieve compliance with the design life.
The Durability Plan sets out a process to be followed during the design and construction of the
bridge to achieve an appropriate level of durability. It requires not only certain parameters to be
included in design but complementary specifications, method statements and process control
plans for adequate documentation of construction procedures and material supply. Verification
that this process has been followed is then documented through quality systems and inspection.
If no Durability Plan exists, then note as such and delete text above. Table 3 to be completed
based on current known information.
Table 3 below lists the main concrete components and their concrete grade, exposure
classification, and minimum and design cover. Add/delete as required. The component titles
are prompts only.
Table 3
Component
Summary of Durability Criteria for Bridge Components
Concrete Grade
Exposure
Classification
Minimum Cover
(mm)
Design Cover
(mm)
S40
B2
45
45
Deck
Precast beams
Columns
Pile cap
Concrete piles
Discuss what durability issues were identified in the Durability Plan and how these were
addressed in the design and construction processes? (e.g. acid sulphate soils, high salinity).
Add any specific information regarding durability of any steel components, e.g. steel piles or
girders.
2.5
Services
Details of the current services, including location and owners, are listed in the BMS and
summarised in Table 4 below. Where they exist, the Service Agreements are also available in
the BMS. Add/delete/modify table as required.
Table 4
Service
Power Cable
Services
Location
Details
Owner
RHS of deck in
girder void
3 × Ø 150mm PVC
Western Power
ITS Power and
Communications Cables
Lighting Power
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page .6
Gas
Traffic Signals
Spares for Future Use
2.6
Land Ownership
Provide details of land ownership for the bridge. Reference a cadastral plan to be included at
Appendix A.
2.7
As-Constructed Condition
This section describes the condition of the bridge immediately after the construction and
updated at the end of the defects liability period.
This section should outline any items that may not fully satisfy the design criteria, any cracks
evident in structure (including details and photos of the cracks for future reference, included at
Appendix F) and any items that may present a future durability concern. Reference the
Construction Report where one exists.
2.8
Current Condition
This section describes the condition of the bridge at the time of preparation or updating of the
AMP. It briefly describes the condition of the various bridge components and identifies any
components not at a satisfactory level. It also highlights any problem areas that could
deteriorate to an unsatisfactory level in the near future. It will also act as a reference point for
future inspections.
The condition is based on Level 1, 2 and 3 Inspections (delete as required). Refer BMS for
links to these documents. The BMS holds condition states for bridge components and the
Bridge Condition Index (BCI) for the condition of the bridge as a whole.
This section should also include monitoring results (e.g. settlement, cathodic protection etc)
either under the relevant section or under its own heading.
If the AMP relates to a new bridge, then this section is to remain blank with provision for future
inclusion. Suggested or possible headings/topics are listed below.
Include reference to relevant photos at Appendix F.
2.8.1 Substructure
Abutments



Wing Walls
Batters
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page .7
Piers



Footings/Pile Caps
Headstocks/Capbeams
Halfcaps/Corbels
Piles
Bearings
Anti-graffiti Coating
2.8.2 Superstructure
Deck
Parapets
Shared Path
Stringers/Beams
Deck Drainage
Lighting
Anti-graffiti Coating
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page .8
2.8.3 Services
Bridge services (e.g. power for lighting)
Cable Trays/Hangers
Water
Sewerage
Gas
Power
2.8.4 Traffic Barrier and Balustrade
Include on bridge and off bridge barriers.
2.8.5 Road Approaches, Approach Slabs and Expansion Joints
2.8.6 Water Course
For example, scour concerns for river crossings which may impact the bridge. Delete section if
not over a water course.
2.9
Current Load Rating
A load rating for the bridge was undertaken in XXXX and the results for the critical component
are summarised in Table 5 below. Add vehicles as appropriate.
Table 5
Vehicle
Main Roads Western Australia
Template Rev A
Load Rating
Load Rating
(%)
T44
XX.X
M Truck
XX.X
Tandem
XX.X
Triaxle
XX.X
Asset Management Plan – Bridge No. XXXX
Page .9
Standard Quad
XX.X
484 Quad
XX.X
HLP320
XX.X
HLP400
XX.X
SM1600
XX.X
The detailed load rating is available through the BMS.
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page .10
3.
KEY DRIVERS
There are a number of key drivers that impact on the management of the bridge. These are
Levels of Service, regulatory requirements, stakeholder requirements and the physical
environment. These drivers are discussed below.
3.1
Levels of Service
Main Roads has developed a number of Levels of Service (LOS) relevant to the management of
bridges. These LOS are called Investigatory Criteria. The Investigatory Criteria for various link
categories are discussed in the document “2006 AMP Standards Review Project – Review of
AMP Standards”. The definitions of the various link categories are found in the document
“Guidelines for Creation of New Links and Review of Existing Link Categories and Extents”
dated November 2010.
Bridge No. XXXX is on the XXXX which is defined as an “MFF” road link (multi-lane free flowing)
with the following Levels of Service, subdivided into three main categories: Configuration,
Condition and Road Use (modify values as required):
Table 6
Levels of Service
Value
Configuration
Width between kerbs
≥ 8.0m
Condition
Bridge strength
≥ 95% T44
Roughness (IRI)
≤ 3.4
Rutting
≤ 20mm
Road Use
Road closure due to flooding
Nil
The Levels of Service as described above support the LOS required for the XXXX Highway.
Any failures to meet the required LOS on the bridge will impact on the LOS on the Highway.
For example, any load restriction on Bridge No. XXXX will affect the heavy haulage transport
industry needing to use the XXXX Highway.
Similarly, the LOS on the XXXX Highway will impact on the LOS elsewhere on the State Road
Network. For example, load restrictions on the XXXX Highway may result in heavy haulage
having to use another part of the network (e.g. XXXX Highway).
The LOS on the State Road Network is of concern to the Managing Director of Main Roads who
is required to report on the asset LOS and other LOS to the Minister for Transport. The Minister
for Transport represents the main stakeholder of the transport infrastructure – the WA State
Government.
3.2
Regulatory Requirements
There is no external regulator in relation to the management of the bridge, so Main Roads sets
its own levels of service in liaison with the relevant stakeholders and based on national
guidelines and best practice established by bodies such as Australian Standards and
Austroads. These include Australian Standards AS5100 Bridge Design and Austroads Guide to
Asset Management Part 6: Bridge Performance.
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page .11
Outline here any changes that may need to be considered for the management of this bridge
either now or into the future. As an example, there may be increased loadings due to new Code
release (e.g. Austroads ‘92 to AS5100) or changes to guardrail standards (e.g. Level 2 barriers
in accordance with Austroads ‘92 to Regular Performance Level barrier in accordance with
AS5100).
Also outline here any Main Roads or Government policy changes, or any changes to State
Government Legislation.
Discuss any regulatory bodies that may have an indirect impact on the management of the
bridge. For example, the Department of Transport (Marine Safety) is the regulatory body
responsible for the marine safety of navigable waterways and Main Roads has a requirement to
meet any conditions set down by them.
3.3
Stakeholder Requirements
The purpose of this section is to list the key stakeholders and describe the future requirements
of the bridge from the stakeholder’s point of view.
Main Roads is the owner of the bridge, and maintains and operates the structure. The
responsibility for the management of the structure resides with Main Roads.
The organisations and agencies that are key stakeholders in the management of the bridge are
outlined below. Also outlined below are any future requirements that the stakeholders (other
than Main Roads) may have for the bridge.
3.3.1 Owner and Operator
Main Roads – responsible for maintaining the bridge in a safe and serviceable
condition and performing to the required levels of service (refer Section 3.1). Main
Roads’ main role is in developing, implementing and funding regular and ongoing
asset management activities so as to meet the level of service;
ii) Main Roads – responsible for operation and maintenance of all ITS cables,
underbridge and footpath lighting cables, and closed circuit television (CCTV)
cameras (list as appropriate);
i)
3.3.2 Service Authorities
i)
List as appropriate (e.g. Western Power, Alinta Gas, Water Corporation etc). Also
outline any changed requirements for the future (e.g. new services that may be
required).
3.3.3 Bridge Users
Outline demand factors for each, including past performance, factors affecting current demand
for services and factors affecting future demand for services. Use the following list as a guide.
Add/delete as appropriate:
ii)
iii)
iv)
v)
vi)
Vehicle commuters;
Public transport;
Freight, commercial and heavy vehicle transporters;
Pedestrians and cyclists;
Vessels.
3.3.4 Customer Service Advisory Council
The Customer Service Advisory Council provides input into the Customer Services Charter. Its
function is to provide community involvement and input into Main Roads’ organisational
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page .12
planning processes and strategic direction. The Council meets three times per year and
consists of industry and community members representing Western Australia’s diverse road
users. The Council provides advice and feedback, from a customer perspective, on the
development of strategy and policy in relation to Main Roads’ products and services, and levels
of service.
3.3.5 Others
Delete this heading or add any others as appropriate (e.g. Local Governments, mining or other
private companies, Department of Planning and Infrastructure etc). Also list any changed
requirements. Also, discuss any political issues affecting the bridge (e.g. in a marginal seat,
history of Ministerial complaints).
3.4
Physical Environment
The physical environment has the potential to affect the condition of the bridge. The key
environmental concerns in relation to the bridge are discussed below (add/delete as required).
3.4.1 Atmospheric
State expected atmospheric conditions affecting the bridge during its life. State the distance
from the coast and any special local conditions.
3.4.2 Ground
State expected groundwater level and any potential impact on the bridge structure.
State any potential for Acid Sulphate Soils (ASS) or other deleterious substances in the ground
water table (e.g. salinity).
3.4.3 Water
State water properties if bridge goes over water course (e.g. salt levels or other deleterious
substances). Also consider scour potential.
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page .13
4.
CURRENT PERFORMANCE
4.1
Introduction
The performance of the bridge relates to whether it meets the Key Drivers identified in
Section 3. This includes the required levels of service, which for bridges includes configuration,
bridge condition and road use. The performance of the bridge with respect to these key drivers
is discussed in turn below.
The author should keep the following in mind when discussing the current performance of the
bridge and how this relates to bridge condition.
The condition of the asset relates to individual or combined material deterioration of the various
components that comprise the bridge asset. Condition and performance are two interrelated
concepts and the following important distinctions and relationships between asset performance
and condition should be borne in mind:




4.2
The condition of the bridge is not a measure of its performance;
The performance of the bridge is not a measure of its condition;
The condition may impact on its performance (but not necessarily, depending on
severity); and
The performance of the bridge (or the performance expectation) may affect the condition
of the bridge (for example, vehicle overloading).
Levels of Service
4.2.1 Configuration
Discuss adequacy of the bridge width between kerbs.
4.2.2 Bridge Condition
Discuss bridge strength (referencing any load rating undertaken), roughness and rutting. The
last two would generally only relate to bridge approaches, but could also relate to timber bridges
with a road pavement surfacing (rather than a structural concrete deck).
4.2.3 Road Use
Discuss known road closures due to flooding.
4.3
Regulatory Requirements
Discuss here any non-compliance to current Codes, Main Roads policy, government legislation
etc.
4.4
Stakeholder Requirements
Discuss here where the bridge does not satisfy the requirements outlined in Section 3.3.
4.5
Physical Environment
Discuss the performance of the bridge in terms of its environment and specifically where a
component may not meet the specified design life or serviceability. For example, deterioration
due to corrosion, abutment scour, etc.
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page .14
5.
BRIDGE STRATEGY
A bridge strategy is required to ensure that the planning of asset management activities at the
bridge level are aligned with the higher level strategies for the Link, the Regional Network and
ultimately, the Main Roads’ Network.
The strategy provides broad guidance on what asset management activities are required
including any major upgrading works.
The strategies influencing the management of the bridge can be considered in a hierarchy
consisting of three levels – Corporate, Regional and Bridge. The bridge strategy needs to
support the regional strategy which in turn needs to support the corporate strategy.
These are described below.
5.1
Corporate Strategy
There are a number of corporate strategies relevant to the management of bridges. These form
part of Main Roads’ Strategic Plan 2k12 as listed below:







Strategic Approach to the Network
Excellence in Asset Management
Sustainable, Efficient Delivery of Projects
Network Operations Planning
Safe Road Network Access
Reliable and Efficient Road Network Access
Road Network and User Information
Details of these strategies can be found on the Main Roads’ website
www.mainroads.wa.gov.au.
Many of these strategies identify the importance of integrated planning across the Main Roads’
Network and the role of Asset Management Plans in supporting this objective.
5.2
Regional Strategy
The XXXX Regional Road Network Plan includes asset management planning and investment
requirements for the XXXX Region. It contains the future funding requirements to manage the
National Highways and State Roads within the Region over a 10 year planning horizon.
Underpinning this Network Plan are strategies included in the Link Plans which have been
developed for each link in the Region covering:



inventory details (e.g. road width)
condition data (e.g. roughness/rutting)
the number of bridges on the Link that do not meet the Investigatory Criteria – refer to
Section 3.1 (e.g. strength, width between kerbs).
The XXXX Regional Road Network Plan can be found on the Main Roads Intranet site for the
Road Asset Planning Branch. Link Plan XX containing Bridge No. XXXX is a standard report
generated in RAPID.
Describe here the specific regional strategy relevant to this bridge. For example, the Link Plan
may indicate that the bridge could become redundant in 15 years time due to a major bypass
being constructed, or a section of the Link may be duplicated and become a part of a major
highway extension. Another example is if the Link is part of a High Wide Load Route where the
strength and width of the bridge may be critical.
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page .15
5.3
Bridge Strategy
Describe here the bridge strategy which should align with the Regional Strategy. For example,
the bridge may require minimal maintenance as it will be demolished in the near future. In
another example, the bridge strategy will need to cover the asset management activities
required for future increased traffic volume and/or loadings.
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page .16
6.
RISK MANAGEMENT
Risk management is a systematic method of establishing the context, then identifying,
analysing, evaluating, treating, monitoring and communicating the risks associated with an
asset (or activity) to minimise losses and maximise opportunities.
Main Roads’ Corporate Risk Management Process provides guidance on identifying and
assessing risks associated with its assets, including Risk Rating Tables which enable risks to be
evaluated and ranked. For the purposes of identifying and assessing the risks associated with
Bridge No. XXXX, an onsite brainstorming session was held which included the Author, XXXX
from Main Roads and XXXX from XXXXX.
Table 7 below summarises the risks identified for the bridge and the proposed treatments.
Author to add, delete or modify as appropriate.
The purpose of the risk assessment is to identify, evaluate, rank and provide strategies or
treatments to minimise these risks. The risk assessment shall be undertaken in accordance
with the latest copy of Main Roads’ Corporate Risk Management Process (refer Appendix C).
The Risk Tables included in this document are to be used to evaluate each risk.
The risks are to be ideally brainstormed on site. As a minimum, the persons present at the
brainstorming session is the Author, the Asset Manager and Project Manager from the Region,
and one other person either from Main Roads or the Author’s organisation, not directly involved
in the preparation of the AMP. Treatment can either be identified as part of the brainstorming
session or at a later date by the Author.
Risks could come from failing to meet levels of service, or regulatory and stakeholder
requirements; or from an unforeseen environmental or design event.
In general, only significant risks should be included (e.g. Medium or above), however, events
which have been highlighted elsewhere in the AMP, but have a low risk level, should still be
included. Events which do not specifically put the asset at risk (e.g. items thrown from bridge)
should be included where relevant (e.g. over electrified railway), since the risk only exists
because the bridge exists.
Any residual risks identified in the Design Report are to be transferred here (applicable to new
bridges only).
Table 7
Risk Table
Risk
Cause
Consequences
Consequence
Rating
Likelihood
Rating
Level of
Risk
Treatment
Failure due to
deterioration of
concrete
components
Chloride ingress,
carbonation,
alkaline aggregate
reaction
Moderate
damage to asset
5
3
H
Inspection and
maintenance
Failure due to
overloading
Vehicle
collision
Person falls
from bridge
Vandalism
Visual
dilapidation
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page .17
Items thrown
from the
bridge
Train/Vessel
impact on pier
For any unusual or atypical risks identified, further text may be required here discussing the
failure modes and causes in more detail including explanation of the consequence level,
likelihood ratings and the treatment/strategy chosen.
Some of these may require contingency plans and the author should make reference to
Section 7.4 if applicable.
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page .18
7.
OPERATIONAL PLANS
The asset management activities required for Bridge No. XXXX are load rating, inspection and
maintenance. Supporting these activities are a number of operational plans. These are
outlined below.
7.1
Load Rating
Structures Engineering is responsible for arranging load ratings and therefore an operational
plan has not been provided.
The need for a load rating is assessed based on the outcomes and recommendations from the
inspections and/or condition surveys. Additionally, load ratings may be instigated as part of an
investigation of load capacity of the bridge to accommodate structural modifications or higher
design loadings.
The current load rating for the bridge is summarised in Table 5 of Section 2.9.
7.2
Inspection Plan
Bridge inspection is a vital asset management activity, and should therefore be carefully
planned in order to optimise the assessment of a structure and the data collected in a cost
effective manner.
All inspections shall be carried out in accordance with the relevant Main Roads’ inspection
guidelines which are referenced in Appendix C.
Inspection of Bridge No. XXXX requires access to the various components of the bridge. Given
the high road usage and vertical clearances, special care will need to be taken to achieve safe
working procedures. No special provisions, in the form of special access platforms or similar,
have been incorporated in the design. General requirements for inspections are (modify as
required):
Include here any specific access requirements that may be relevant for this bridge. Aspects to
consider include:





Safe parking location for inspector vehicles
Temporary access equipment (e.g. ropes/harnesses, ladders, transportable stairs,
cherry pickers, underbridge inspection unit)
Traffic management requirements (e.g. lane closures, spotters)
Whether Safe Working Procedures are required (e.g. inspection of enclosed box girders)
or whether they already exist
Any security requirements (e.g. keys to access abutment doors)
The Inspection Plan, including specific requirements for this bridge, is given in Table 8 below.
Author to amend table as required.
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page .19
Table 8
Inspection Plan
Type of
Inspection
Austroads
Inspection
Classification
Frequency/
Date
Responsibility
Specific Requirements
Annual Visual
Level 1
Annual
MRWA (Region)
Nil
Detailed Visual
Level 2
Generally 7 yearly
for concrete and
steel, 5 yearly for
timber.
MRWA (Structures
Engineering)
Nil
Extent and
frequency will vary
depending on risk
of failure and
previous
inspections
Condition
Survey
Level 3
Extent and
frequency will vary
depending on risk
of failure and
previous test
results
MRWA (Structures
Engineering or
Region)
Nil
Special
Level 3
Extent and
frequency will vary
depending on risk
of failure and
previous test
results
MRWA (Structures
Engineering or
Region)
Nil
“Special” inspections could include specific component cracking, support settlement
monitoring, cathodic protection, movement of ground & pile outer casings, modular
expansion joints, impact damage from an accident event or inspection of pier/abutment
bearings that are not readily accessible.
Note: if there are no specific requirements then leave “Nil” in the table.
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page .20
7.3
Maintenance and Specific Work Plans
7.3.1 General
The Maintenance and Specific Works Plans are updated with the latest Level 2 or 3 inspections,
taking into consideration environmental factors, bridge condition and potential risk to key
structural components of damage, deterioration or failure.
Maintenance and specific works are subject to the same access issues as described in
Section 7.2.
It is important to link the Maintenance and Specific Works Plans to asset condition and adapt
this plan as required throughout the life of the structure.
The key maintenance activities required for the bridge are summarised in Tables 10, 11 and 12
below for Routine and Preventative Maintenance (timber bridges only) and Specific Works.
Material manufacturer product details for future maintenance are included in Appendix E.
7.3.2 Maintenance Procedures
Bearing Replacements
The bearings are a special item that will generally have a design life less than the design life of
the overall bridge. Therefore, a bearing replacement procedure must be prepared for each
structure and outlined below. The procedure should cover the replacement of all the bearings
(including jacking points, maximum allowable jacking, procedure for removal and installation of
new bearing). Only include this section if a procedure exists (generally only apply to new
bridges).
Preventative Maintenance
All preventative maintenance activities shall be carried out in accordance with Main Roads
Timber Bridge Preventative Maintenance Standards (refer Appendix C). Delete if no timber
components.
Add any other maintenance procedures required here.
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page 21
Table 9
Routine Maintenance Plan
Routine maintenance involves small, mainly reactive work items which are normally anticipated with a budget timeframe, but their precise nature,
location and timing are not known in advance. Routine maintenance mainly consists of minor work items planned on a short term basis, usually about
two weeks or less.
A detailed Routine Maintenance Plan is presented below. Author to amend table as required.
Asset Grouping
Maintenance
Budget Estimate
as at XXXX
Frequency
Responsibility
Bridge Deck
Traffic Lanes – sweep or wash down to remove debris or dirt
$3,000/annum
As required
MRWA
$30,000/5 years
As required
MRWA
Traffic Lanes – clean and remove debris from expansion joints
$6,000/annum
As required
MRWA
Traffic Lanes – repair/replace signage
$4,000/annum
As required
MRWA
Guardrails – repair, tighten and adjust
$5,000/annum
As required
MRWA
Expansion joint cleaning
$500/annum
As required
MRWA
Scupper cleaning
$500/annum
As required
MRWA
Abutments – remove graffiti , repair anti-graffiti coating and repair
holes in stone pitching
$5,000/annum
As required
MRWA
Piers – remove graffiti and repair anti-graffiti coating
$4,000/annum
As required
MRWA
Services – repair switchboards, wiring, lighting, globes and other
electrical items
$6,000/annum
As required
MRWA (Metro
ISA)
Services – check tension in connecting bolts of light pole bases and
re-tighten if required
$1,000/annum
As required
MRWA
-
-
-
Traffic Lanes – repair road seal and approaches
Superstructure
Substructure
Electrical
Services
Nil
Routine maintenance activities may include, but not be limited to, removing debris from the roadway, cleaning expansion joints, ensuring free
drainage, repairing accident damage to railing and tightening bolts, minor crack repairs, removing graffiti, landscaping, and maintaining pavement,
signs, lines, and lighting.
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page .22
Table 10
Preventative Maintenance Plan
Preventative maintenance involves work items conducted at regular intervals of longer than one year. These work items are carried out before or at
an early stage in the development of defects (e.g. timber rot) aimed at preventing occurrence or progression of the defect. It is undertaken on a
proactive rather than reactive basis.
Based on this definition, a Preventative Maintenance Plan is only relevant for a timber or timber hybrid bridge.
A detailed Preventative Maintenance Plan is presented below. Author to amend table as required.
Asset Grouping
Maintenance
Bridge Deck
None
Superstructure
Substructure
Main Roads Western Australia
Template Rev A
Budget Estimate
as at XXXX
Frequency
Responsibility
-
-
-
Timber sealing
$XXXX
5 yearly
MRWA
Fastener maintenance
$XXXX
5 yearly
MRWA
Fungicide treatment
$XXXX
5 yearly
MRWA
Fastener maintenance
$XXXX
5 yearly
MRWA
Fungicide treatment
$XXXX
5 yearly
MRWA
Asset Management Plan – Bridge No. XXXX
Page .23
Table 11
Specific Works Plan
Specific Works are work items that include one-off repairs, refurbishment and upgrade works to retain the bridge as near as practical to its “as
constructed” condition or to improve the bridge characteristics such as strength, geometry and safety. Specific works also includes bridge
replacement. Specific works are planned, proactive work items and normally are scheduled at least two years in advance of the delivery year.
The detailed Specific Works Plan is presented below. Author to amend table as required.
Asset
Grouping
Specific Works
Bridge Deck
AMP
Section No.
Budget Estimate as at
XXXX
Date
Responsibility
Expansion Joints – replace expansion joint seal
$20,000
2015
MRWA
Railings – replace guardrail and balustrade protective coatings
$300,000
2020
MRWA
Surface – resurface bridge and apply waterproofing if required
$250,000
2030
MRWA
-
-
-
Superstructure
None
Substructure
Abutments – reapplication of anti-graffiti coating
$20,000
2020
MRWA
Piers – reapplication of anti-graffiti coating
$20,000
2020
MRWA
Electrical
None
-
-
-
Services
None
-
-
-
Specific Works usually involve repairs or modifications to structural components with some typical specific maintenance activities including repair of
cracked or spalled concrete, repair or replacement of an expansion joint, replacement of bearings and structural repair of guardrail following major
impact.
Specific maintenance requirements are identified from Level 2 or 3 inspections.
The AMP Section No. is the reference in this AMP that provides justification for the specific works.
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page .24
7.4
Contingency Plan
The recommended remedial and maintenance activities are aimed at reducing the overall
likelihood that an identified failure may occur. However, no matter how low the likelihood, there
can be no absolute guarantee that such an event will not happen. Contingency Plans aim to
minimise or manage the consequences of identified failures, should they occur.
Main Roads is required to provide a prompt response in the event of incidents on the road
network, including Bridge No. XXXX. This service is required to be available 24 hours a day, 7
days a week, having ready access to all necessary resources including skilled personnel, plant
and materials. In the event of an incident, Main Roads is also required to liaise with relevant
agencies, including the media.
The Risk Assessment (refer to Section 6) identified significant risks associated with the bridge.
The Contingency Plans to mitigate the consequences of risks that have a Moderate or higher
rating are summarised in Table 12: Author to modify table as required.
Table 12
Risk
Contingency Plan
Contingency Plan
Failure due to
deterioration of concrete
components
Failure due to overloading
Vehicle collision
Person falls from bridge
Vandalism
Visual dilapidation
Items thrown from the
bridge
Train/Vessel impact on
pier
Most of these events would involve isolating the bridge and diverting traffic while repairs were
being arranged. Author should include reference here to detour plan if one exists.
Any alternate route for any diversion of traffic must not only consider general vehicular and bus
traffic but also needs to bear in mind period-permit vehicles such as cranes and road trains and
any single trip permit vehicles such as floats and multiple axle trailers.
The Police may need to manage some of the incidents (e.g. person accidentally falling from the
bridge, vandalism or major traffic accidents).
7.5
Financial Plan
The inspection, maintenance and specific works expenditure estimates required for the bridge
over the next 10 years are outlined in the Financial Plan in the Table 13 below and reflect the
items discussed in Sections 7.2 and 7.3. The estimates shown are only for activities for which
Main Roads is responsible.
Costs given in the following Financial Plan for the bridge include traffic management and access
costs. They are based on the best information available at the time and should be reviewed
with each update of this AMP.
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page .25
Table 13
Financial Plan
2009/10
2010/11
2011/12
2012/13
2013/14
2014/15
2015/16
2016/17
2017/18
2018/19
Level 1 Inspections
800
800
800
800
800
800
800
800
800
800
Level 2 Inspections
3,000
Inspections
3,000
Level 3 Inspections
SUBTOTAL
30,000
3,800
800
800
800
800
3,800
800
800
30,800
800
18,000
18,000
18,000
48,000
18,000
18,000
18,000
18,000
48,000
Routine Maintenance Expenditure
Bridge Deck
18,000
Superstructure
10,000
10,000
Substructure
9,000
9,000
9,000
9,000
9,000
9,000
9,000
9,000
9,000
9,000
Miscellaneous
7,000
7,000
7,000
7,000
7,000
7,000
7,000
7,000
7,000
7,000
SUBTOTAL
34,000
34,000
34,000
34,000
84,000
34,000
34,000
34,000
34,000
84,000
37,000
37,000
37,000
87,000
Preventative Maintenance Expenditure
Bridge Deck
20,000
20,000
Superstructure
5,000
5,000
Substructure
5,000
5,000
Miscellaneous
1,000
1,000
SUBTOTAL
31,000
31,000
Specific Works Expenditure
Concrete Overlay
1,500,000
SUBTOTAL
1,500,000
TOTAL
68,000
37,000
37,000
37,000
87,000
1,568,000
Note: All figures are in dollars.
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page 26
8.
RESPONSIBILITIES
Table 14 indicates the broad responsibilities of various organisations in relation to Bridge
No. XXXX.
Table 14
RESPONSIBILITY
MRWA
Ownership and Overall
Responsibility

Funding

Responsibilities of Various Agencies
Metro ISA
Service
Owner 1
Service
Owner 2
PTA/
Brookfield
LGA
Maintenance
Pavement, signs and lines


Lighting
Routine – non-structural

Routine – structural
Specific – structural

Services – ITS



Services – power cables

Services – telecom cables (duct
for future services)
Drainage

Improvements and Upgrades

Planning

Inspections
Pavement, signs and lines

Lighting

Bridge structural components



Services – ITS

Services – power cables

Services – telecom cables (duct
for future services)
Load Rating

Review of AMP

Modify responsibilities as appropriate for the bridge. Add service providers (e.g.
Western Power, Water Corp, etc) or other agencies (e.g. Public Transport Authority,
Local Government Authorities, etc as appropriate).
Highlight below any items that the reader should be alerted to which are specific to this
structure. In the case of a bridge over railway where there is a Memorandum of
Understanding (MOU) covering responsibilities for the management of various
components on the bridge, the MOU should be referenced here and Table 14 amended
to suit the MOU. Some common aspects are provided below.
Main Roads delivers the maintenance of its road network through a number of regionally
based Integrated Service Arrangements (ISAs). Where Main Roads has the
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page .27
responsibility for maintenance on the bridge as shown in Table 14 above, this can be
delivered using the Integrated Service Provider (ISP).
The Metropolitan Region ISA covers the maintenance and repair of Main Roads'
electrical assets across the State such as the roadway lighting for the bridge.
Inspection and maintenance of service attachments to the bridge is the responsibility of
the individual service authorities. In accordance with the Main Roads' Standard
Conditions of Service Attachment, the service authority must take full responsibility for
the erection and subsequent maintenance of the attachment including all associated
costs, indemnify Main Roads against all claims arising from the erection of the service,
and relocate the service as may be requested by Main Roads.
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page 28
9.
OPPORTUNITIES FOR IMPROVEMENT
This section should be compiled after all of the other sections have been completed.
Any aspect of the bridge and its environment can be considered including:
- Improvement of the performance of the bridge
- Applications for new or emerging technologies
- New work practices (better work practices adopted from other organisations).
For example, a new coating technology for concrete durability is being considered for the
bridge, but a firm decision has not been made and therefore has not yet been included in
Operational Plans.
This section can also be used as a section where ideas can be collected and retained
when staff changes occur within the structures asset management area of Main Roads.
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page 29
10.
ASSET MANAGEMENT PLAN UPDATE
This AMP is a working document that should be updated on a regular basis as tests and
inspections are undertaken and new information becomes available.
As the key drivers and condition change over the lifetime of the structure, this Asset
Management Plan must be updated to reflect these changes. This is necessary to
ensure that Bridge No. XXXX is effectively managed in a sustainable and economic
manner, and continues to meet all the levels of service requirements.
The purpose of the AMP update process for the bridge is to:




assess the present condition;
assess the performance;
make comparisons with previous data and information in order to develop a
history of the bridge and predict future behaviour; and
update the Operational Plans.
It is intended that the AMP be updated as required by the Asset Manager Structures
(AMS), XXXXXX Region, but generally every 5 or 7 years (modify as appropriate for
timber or concrete/steel, respectively). This should preferably occur immediately after
the detailed inspection of the bridge. However, where significant changes to the key
drivers or the bridge occur within that timeframe, the impact of these changes shall be
taken into consideration. Earlier update of the AMP may be required under such
circumstances.
Every revision status is recorded in the Revision Table as shown at the beginning of this
AMP.
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page 30
APPENDIX A
LOCATION OF BRIDGE NO. XXXX
Include here extract from Bridge Map Book, Aerial Photo and Cadastral Plan
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page 31
APPENDIX B
GENERAL ARRANGEMENT DRAWING(S)
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page 32
APPENDIX C
REFERENCE DOCUMENTS
This AMP is to be read in association with the following:
Add list of documents, giving report numbers and TRIM document numbers where
available. Some standard documents and typical examples (highlighted) are included
below. Only include documents not referenced in BMS:
Report Description
Report Number
TRIM Document No.
2006 AMP Standards Review Project – Review of
AMP Standards
N/A
D07#120929
Corporate Risk Management Process
N/A
D09#70733
Guidelines for Creation of New Links and Review
of Existing Link Categories and Extents
N/A
D11#109464
Timber Bridge Maintenance & Refurbishment
Preventive Maintenance Standards
6706-02-2226
Routine Visual Bridge Inspection
(Level 1 Inspections) for Bridges
Guidelines
6706-02-2234
Detailed Visual Bridge Inspection Guidelines for
Concrete and Steel Bridges (Level 2 Inspections)
6706-02-2233
Detailed Visual Inspection Guidelines for Culverts
(Level 2 Inspections)
6706-02-2237
Sign Gantry Guidelines (Level 1 and Level 2
Inspections)
6706-02-2239
SWTC (for D&C or Alliance Contracts only)
Structural Design Report (new bridges only)
Durability Plan (new bridges only)
Geotechnical Analysis and Design Report (new
bridges only)
Construction Report (new bridges only)
Regional Road Network Plan XXXX
Link Plan XXXX
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page 33
APPENDIX D
DEFINITIONS
List definitions/acronyms as appropriate. Some common examples are provided below.
Put in alphabetical order
ADC – Austroads Design Codes
AMP – Asset Management Plan
AMS – Asset Manager Structures
BMS – Bridge Management System
IFC – Issued For Construction
IRIS – Integrated Road Information System
ISA – Integrated Service Arrangement
ISP – Integrated Service Provider
LGA – Local Government Authority
LOS – Levels of Service
MRWA – Main Roads Western Australia
PTA – Public Transport Authority
RAPID – Road Asset Planning Investment Database
SE – Structures Engineering
SES – Senior Engineer Structures
SLK – Straight Line Kilometre
SWTC – Scope of Works and Technical Criteria
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page 34
APPENDIX E
MANUFACTURER PRODUCT DETAILS
Material manufacturer product details are included for the below key materials.
Component
Product Name
Material
Manufacturer
Details on
Drawings
Manufacturer Product
Details Included in this
Appendix
Anti-graffiti
Coating
Imperite 300
Jotun Australia
Pty Ltd
Not applicable
Colour Palettes, Bridge
Painting Colour Schedule
Product Data Sheet and
Materials Safety Data
Sheet obtained from web
site (10/08/09) dated Oct
1999 and 27/03/2006
respectively
Bearings
Expansion
Joint
Elastomeric Laminated
Bearing Series U 590
diameter circular, Part No.
GUD-09, in accordance with
AS 5100.4- 2004 Table A16
laminated Elastomeric
Bearing – Diameter 590 Part
No. 161509C
Granor Rubber
& Engineering
Pty Ltd
5.33-ST-DG-061
Rev 0
Joint Type AC-75F
Granor Rubber
& Engineering
Pty Ltd
5.34-ST-DG-074
Rev 1,
Product general details
from web site (10/08/09)
5.34-ST-DG-075
Rev 1,
Details as per design
drawings
Main Roads Western Australia
Template Rev A
Product general details
from web site (10/08/09)
Details as per design
drawings
Asset Management Plan – Bridge No. XXXX
Page 35
APPENDIX F
PHOTOGRAPHS
Photo 1: View of Bridge No. XXXX taken from XXXX
Photo 2: View of Bridge No. XXXX taken from XXXX
Add photos as required showing defects, key features etc appropriately referenced in
AMP.
Main Roads Western Australia
Template Rev A
Asset Management Plan – Bridge No. XXXX
Page .36
Download