Schematic Design (SD)
Outdoor
Service Area
List existing recycling and dumpster locations on the existing condition site plans.
Indoor
Jen provides feedback about where recycling locations need to be and gives an overview of indoor
recycling requirements
Walkway
Ray and Sarah provide feedback about locations
Access
List other buildings that utilize the dumpster and recycling sites shown on existing condition site plans.
Building
Material
Assessment
and Salvage
Building Material Walkthrough –
Fixtures,
Furniture
and
Equipment
Assessment
and Salvage
Initial walkthrough by the design team TO DETERMINE what valuable and reusable materials are
available for:




Reuse in this project,
Reuse in other campus projects,
Reuse by the general public, or
Recycled (required and suggested).

Submittal requirement: Valuable & Reusable Building Material Inventory [Initial list at this
time]
Designers and customers begin thinking about what will and will not be reused in the finished project
and during temporary housing.
The information on this page can be found in the UNC Design Guidelines, Chapter II. Project Development Process, B. Project Development
Sequence, b) Schematic, (1) Existing Site Conditions and (4 ) Schematic Design Submittal.
Design Development (DD)
Outdoor
Service Area
 Before DD documents are prepared, the design team and the Office of Waste Reduction and
Recycling meet to discuss outdoor service area requirements and equipment to be used.

Include specification section 02475 with any relevant site or space planning requirements for this
project

Include specification section 11170 listing specifications, installation information, and suppliers for
solid waste handling equipment to be purchased BY the project—at a minimum, this will include
compactors.

Detailed plan sheets showing outdoor service area enclosure(s), including:
o screen wall details
o electrical requirements
o lighting
o drainage
o a list of buildings that the site(s) are intended to serve

An initial summary sheet listing all the outdoor service area equipment to be used. This will
include:
o the type of equipment (example: 8 yd. cardboard dumpster) ,
o the estimated cost,
o whether the project, FP&C or the customer is purchasing them, and
Page 2 of 8
o
Indoor
Walkway
Access
Building
Material
Assessment
and Salvage
the locations (if there’s more than one building in the project).

Before DD documents are prepared, the design team and the Office of Waste Reduction and
Recycling meet to discuss indoor recycling locations and any special situations

Include specification section 02475 with any relevant site or space planning requirements for this
project

Include specification Section 12300 Manufactured Casework listing specifications for recycling
cabinets

Clearly marked locations of all indoor recycling locations -AND- detail sheets showing the plans
for any recycling cabinets to be built by the project

An initial summary sheet listing all the indoor recycling sites. This will include the:
o indoor recycling locations,
o which locations will use cabinets,
o whether the project, FP&C or the customer is purchasing them, and
o the amount reserved for cabinets that are not being built by the project.

Before DD documents are prepared, the design team and the Office of Waste Reduction and
Recycling meet to discuss walkway recycling locations and any special situations

Include specification 02870 listing the walkway recycling containers to be used and their
placement.

Clearly marked plans showing the locations of all walkway recycling locations

An initial summary sheet listing all the walkway recycling sites. This will include the:
o walkway recycling locations,
o whether the project or FP&C is purchasing them, and
o the amount reserved for walkway bins (assuming that FP&C will be purchasing them).

Staging plans and site drawings should include plans for access to the building (if occupied) and
adjacent buildings such that deliveries and recycling/waste collection services can be maintained.

Demo plans shall note the requirement of contacting the Office of Waste Reduction and Recycling
to remove indoor and outdoor containers (including dumpsters) as the project phasing affects
different areas.
Based on Valuable & Reusable Building Material Inventory :
Reuse in project

Based on inventory:
o Discussion and initial decisions
o Design team and construction manager at risk

Submittal requirement: Decisions are to be integrated into specs and drawings: 01505,
02070, and appropriate specifications and drawings
Reuse in other projects:

Circulate list to Facilities Planning and other design teams

Submittal requirement: Salvage to be listed in 01505, 02070 and appropriate specifications
and drawings
Outside salvage/recycle:

Market research

Design team, construction manager at risk and the Office of Waste Reduction and Recycling ,
Construction Manager at Risk, Office of Waste Reduction and Recycling assists

Submittal requirement: Any potential recyclables are to be listed in 01505 as a rough list of
required and suggested materials. Any salvage is to be listed in 02070 and appropriate
specifications and drawings
Page 3 of 8
Fixtures,
Furniture
and
Equipment
Assessment
and Salvage
Fixture, Furniture & Equipment Walkthrough –
Initial walkthrough by the design team TO DETERMINE what valuable and reusable materials are
available.

Submittal requirement: Fixture, Furniture & Equipment Inventory
o initial list at this time
o detailed information and quantities on FF&E (Brand, year, etc.).
o movable items
o fixed items (list in 01505, 02070, add language to appropriate specifications and show
details on plans (demo and others as needed)
Reuse in project:

Based on inventory:
o Discussion and initial decisions

UNC Design Manager, Design Team, consultants (move coordination, interior design,
etc.), UNC Interior Design Services, Office of Waste Reduction and Recycling
Reuse elsewhere on campus:

UNC Design Manager, Design Team, Facilities Services Shops, Office of Waste Reduction
and Recycling (assists)

Circulate inventory to departmental business managers
Surplus:
01060
01505
02070

UNC Design Manager, Design Team, Construction Manager at Risk, Surplus, Office of
Waste Reduction and Recycling (assists)

Based on inventory:
o Discuss presale or warehouse.
o Research markets.
Standard wording
INITIAL lists for building materials and non-moveable FFE of:

Reuse in this project,

Reuse in other campus projects,

Reuse by the general public, or

Recycled (required and suggested).
INITIAL plan for building materials and non-moveable FFE:
o Storage for reuse in Project
o Transfer for reuse on campus
o Delivery to Owner (Surplus and Shops)
The information on this page can be found in the UNC Design Guidelines, Chapter II. Project Development Process, B. Project Development
Sequence, c) Design Development Phase, (1) Design Development Submittal, (b) Site and space planning information for waste and recycling
collection, (t) Maintaining services and access to buildings during construction, and (p) Construction Waste Management.
Construction Documents
Outdoor
Service Area
 Before Construction Documents are prepared, the design team and the Office of Waste Reduction
and Recycling meet to confirm outdoor service area requirements and equipment to be used.

Include specification section 02475 with any relevant site or space planning requirements for this
project

Include specification section 11170 listing specifications, installation information, and suppliers for
solid waste handling equipment to be purchased BY the project—at a minimum, this will include
compactors.

Detailed plan sheets showing outdoor service area enclosure(s), including:
o screen wall details
Page 4 of 8
o
o
o
o
Indoor
Walkway
Access
Building
Material
Assessment
and Salvage
electrical requirements
lighting
drainage
a list of buildings that the site(s) are intended to serve

A FINAL summary sheet listing all the outdoor service area equipment to be used. This will
include:
o the type of equipment (example: 8 yd. cardboard dumpster) ,
o the estimated cost,
o whether the project, FP&C or the customer is purchasing them, and
o the locations (if there’s more than one building in the project).

Before Construction Documents are prepared, the design team and the Office of Waste Reduction
and Recycling meet to confirm indoor recycling locations and any special situations

Include specification section 02475 with any relevant site or space planning requirements for this
project

Include specification Section 12300 Manufactured Casework listing specifications for recycling
cabinets

Clearly marked locations of all indoor recycling locations -AND- detail sheets showing the plans
for any recycling cabinets to be built by the project

A FINAL summary sheet listing all the indoor recycling sites. This will include the:
o indoor recycling locations,
o which locations will use cabinets,
o whether the project, FP&C or the customer is purchasing them, and
o the amount reserved for cabinets that are not being built by the project.

Before Construction Documents are prepared, the design team and the Office of Waste Reduction
and Recycling meet to confirm walkway recycling locations and any special situations

Include specification 02870 listing the walkway recycling containers to be used and their
placement.

Clearly marked plans showing the locations of all walkway recycling locations

A FINAL summary sheet listing all the walkway recycling sites. This will include the:
o walkway recycling locations,
o whether the project or FP&C is purchasing them, and
o the amount reserved for walkway bins (assuming that FP&C will be purchasing them).

Staging plans and site drawings should include plans for access to the building (if occupied) and
adjacent buildings such that deliveries and recycling/waste collection services can be maintained.

Demo plans shall note the requirement of contacting the Office of Waste Reduction and Recycling
to remove indoor and outdoor containers (including dumpsters) as the project phasing affects
different areas.
Based on Valuable & Reusable Building Material Inventory :
Reuse in project

Based on inventory:
o Discussion and FINAL decisions
o Create a plan for storage of materials
o Design team and construction manager at risk

Submittal requirement: Decisions are to be integrated into specs and drawings: 01505,
02070, and appropriate specifications and drawings
Reuse in other projects:

Circulate FINAL list to Facilities Planning and other design teams

Create a plan for transfer and storage

Submittal requirement: Salvage to be listed in 01505, 02070 and appropriate specifications
and drawings
Page 5 of 8
Outside salvage/recycle:
Fixtures,
Furniture
and
Equipment
Assessment
and Salvage

Final list

Market research

Design team, construction manager at risk and the Office of Waste Reduction and Recycling,
CONSTRUCTION MANAGER AT RISK, Office of Waste Reduction and Recycling assists

Submittal requirement: Any potential recyclables are to be listed in 01505 as a FINAL list of
required and suggested materials. Any salvage is to be listed in 02070 and appropriate
specifications and drawings
Fixture, Furniture & Equipment Walkthrough –
Walkthrough by the design team TO DETERMINE what valuable and reusable materials are available.

Submittal requirement: Fixture, Furniture & Equipment Inventory
o FINAL list
o detailed information and quantities on FF&E (Brand, year, etc.).
o movable items
o fixed items (list in 01505, 02070, add language to appropriate specifications and show
details on plans (demo and others as needed)
Reuse in project:

Based on inventory:
o Discussion and FINAL decisions
o Create a plan for transfer and storage

UNC Design Manager, Design Team, consultants (move coordination, interior design,
etc.), UNC Interior Design Services, Office of Waste Reduction and Recycling
Reuse elsewhere on campus:

UNC Design Manager, Design Team, Facilities Services Shops, Office of Waste Reduction
and Recycling (assists)

Final list of who’s getting what (re-circulate list to departmental business managers if
necessary)

Create a plan for transfer and storage
Surplus:
01060
01505
02070

UNC Design Manager, Design Team, Surplus, consultants (move coordination, interior
design, etc.), Construction Manager at Risk, UNC Interior Design Services, Office of Waste
Reduction and Recycling

Based on inventory:
o Decision as to presale or warehouse made
o Research markets
o Create a plan for transfer and storage
Standard Wording
FINAL lists for building materials and non-moveable FFE of:

Reuse in this project,

Reuse in other campus projects,

Reuse by the general public, or

Recycled (required and suggested).
FINAL plan for building materials and non-moveable FFE:
o Storage for reuse in Project
o Transfer for reuse on campus
o Delivery to Owner (Surplus and Shops)
The information on this page can be found in the UNC Design Guidelines, Chapter II. Project Development Process, B. Project Development
Sequence, d) Construction Document Phase, (1) Construction Document Design Submittal, (a) A sheet of drawings containing…, (g) These
specifications related to recycling and waste management…, and (5) Final Movable Fixture, Furniture, & Equipment (FFE) Inventory.
Page 6 of 8
Pre Bid
Outdoor
Service Area
Not applicable
Indoor
Walkway
Access
Building
Material
Assessment
and Salvage

Invite the Office of Waste Reduction and Recycling to Pre-bid meeting

Review requirements, specification and list of required and supplemental recycling with
bidders

Design team, Construction Manager at Risk, Office of Waste Reduction and Recycling
Fixtures,
Furniture
and
Equipment
Assessment
and Salvage

Department fills out surplus forms and arranges for moving (move consultant and contractor).

Shops salvage and report back to design team and the Office of Waste Reduction and
Recycling.

Surplus receives goods and or provides special pick ups if prearranged.
01060

Explain process and requirements (include meeting requirement before project
starts).
01505
02070
The information on this page supplements the UNC Design Guidelines, Chapter II. Project Development Process, B. Project Development
Sequence, e) Bidding Phase.
Pre Construction
Outdoor
Service Area
Indoor
Walkway
Notify the Office of Waste Reduction and Recycling Contact to remove the following from areas
affected by construction:



dumpsters and carts
indoor containers
walkway bins
This is to happen at the start of each segment of phased construction.
Access

Work with the Office of Waste Reduction and Recycling to ensure that traffic plans do not
impede access to dumpsters or other waste removal services for occupied buildings.
Building
Material
Assessment
and Salvage

Invite the Office of Waste Reduction and Recycling to Pre-bid meeting.

Review requirements, specification and list of required and supplemental recycling with
bidders.

Design team, Construction Manager at Risk, Office of Waste Reduction and Recycling
Fixtures,

Department fills out surplus forms and arranges for moving (move consultant and contractor)
Page 7 of 8
Furniture
and
Equipment
Assessment
and Salvage
01060

Shops salvage and report back to design team and the Office of Waste Reduction and
Recycling

Surplus receives goods and or provides special pick ups if prearranged
Hold separate meeting to review these sections and discuss the draft solid waste management plan.
01505
02070
The information on this page supplements the UNC Design Guidelines, Chapter II. Project Development Process, B. Project Development
Sequence, f) Construction Phase, (1) Pre-bid Conference.
Construction
Outdoor
Service Area
Immediately notify the Office of Waste Reduction and Recycling of any deviations from plans or
specifications and provide a copy of the appropriate change order.
Indoor
Walkway
Access
Immediately notify the Office of Waste Reduction and Recycling of any changes that will affect service to
occupied buildings or dumpsters.
Building
Material
Assessment
and Salvage
Implementation and documentation

Draft and Final Solid Waste Management Plan

Monthly reports and weight tickets (receipts)

Meetings as necessary to discuss reports or practices
Fixtures,
Furniture
and
Equipment
Assessment
and Salvage
The information on this page supplements the UNC Design Guidelines, Chapter II. Project Development Process, B. Project Development
Sequence, f) Construction Phase, (2) Periodic Observation, and (3) Submittal Review.
Project Completion
Outdoor
Service Area
Indoor
Walkway

Order all recycling/solid waste equipment for the project. The final list should have been part of
the CD phase.

Arrange for installation of the recycling/solid waste equipment per drawings and specifications
in the Construction Documents.

Coordinate installations with the Office of Waste Reduction and Recycling.

Office of Waste Reduction and Recycling provides any equipment not purchased as part of the
project, labels equipment, coordinates collection schedules with staff and contractors,
and provides billing information to the accounting department.
Page 8 of 8
Access
Building
Material
Assessment
and Salvage
Fixtures,
Furniture
and
Equipment
Assessment
and Salvage


Resume normal access to buildings.
Provide the Office of Waste Reduction and Recycling with a summary of ACTUAL
recycling, reuse and salvage activities for the project. This is to include, but is not limited
to:
o quantities landfilled, recycled, reused, and salvaged;
o a break down of the types of materials recycled, reused and salvaged; the
percent of total waste of each of the categories listed;
o the destinations of these materials;
o the economic impact of these activities on the project; and any success stories or
challenges incurred.
The information on this page supplements the UNC Design Guidelines, Chapter II. Project Development Process, B. Project Development
Sequence, f) Construction Phase, (4) Project Close-Out Responsibilities.