Capital Programme Review 2004
Project Appraisal Form
Tennis and Basketball courts
PROJECT TITLE
DETAILS OF
PROJECT
There are 17 tennis courts and 7 basket ball courts in the parks.
Most tennis courts require resurfacing: four are currently
unuseable. Fences have decayed and in many cases do not allow
access for mechanical sweeping. There is no regular maintenance
regime in place.
An independent consultant was retained to survey the facilities and
to recommend action.
The programme set out below provides for resurfacing of all courts
over five years plus reconstruction of those at Auriol where tree
roots and slippage are causing problems.
While there is an issue about whether all the courts should be
retained some certainly will be and the programme does not need
to be delayed while a conclusion is reached.
BASELINE
CRITERIA
Investment that will achieve key
corporate objectives or key service
priorities.
State which criteria(s)
are meet and why.
Leave blank any
which are not met.
Investment required to meet Health and
Safety or other new legislative
requirements.
Will provide safe conditions for people to
play
Will enable DDA responsibilities to be
discharged
Investment required for the business
continuity of the Council.
s necessary to allow use of the courts
to continue
Will improve the appearance of the physical
environment
Investment that will improve service
efficiency including cost savings or
income generation.
Investment identified in the Council’s
Asset Management Plan.
PRIORITISATION
State which one of the
four prioritisation
categories are met
and why.
1
2
3
4
Capital Appraisal Page 1 of 3
Necessary to maintain the assets in
useable condition
Investment essential and urgently
required to meet one of the
baseline criteria.
Investment important and urgently
required to meet one of the
baseline criteria.
Essential if tennis is still to be played in the
parks. Will improve the appearance of the
physical environment and support the street
car initiative. Will enable the Council to
provide safe playing conditions
Investment important but not
urgently required to meet one of
the baseline criteria.
Investment will assist but is not
urgently required to meet one of
the baseline criteria.
12/02/2016
Capital Programme Review 2004
Project Appraisal Form
A Project outcomes
Tennis can continue to be played in the parks
and benefits
B Consequences of
not undertaking
the project
C Project scope,
what is included /
excluded
D How does project
fit within corporate
priorities and
service objectives
E Consultation
required - who and
when
F
Availability of
project
management
resources
G Time scale /
Progressive elimination of the game. Used courts give parks a derelict
appearance.
Renewal of playing surface and fencing where necessary. Provision of large
gates to enable mechanical sweeping and wheelchair access.


Contributes to improving the appearance fo the physical environment
Contributes to maintaining a safe environment
Users and friends groups for each park. Council to agree programme
priorities.
Procurement and projects staff or consultants appointed by them.
Work to be undertaken during winter months
constraints
H Risks of delivering
to timetable and
cost


Delay in determining programme content;
High tenders
I
Contingencies
Included in cost estimates
J
Accountable
Officers, for the
project planning
and execution
Procurement and projects
K Ward(s) affected
Capital Appraisal Page 2 of 3
Most
12/02/2016
Capital Programme Review 2004
Project Appraisal Form
CAPITAL EXPENDITURE (£000’s)
L1
L2
L4
L5
Estimated cost of works and/or
equipment
£175,000
Consultancy or other fees £10,000
Total Scheme Costs £185,000 (£25K in 2005/6, £100K in 2006/7 for
(L1 + L2) Auriol reconstruction, £10K DDA works in 2005/6,
£25K 07/08, £25K 08/09)
External Sources of Finance Not applicable though may be scope to apply S106
(amount and detail) monies
L6
Net Costs to Council
(L4 – L5)
£185,000
L7
Spend profile, £000s
2005/06
£35,000
L8
2006/07
£100,000
2007/08
£25,000
2008/09
£25,000
Alternative Solutions Take courts out of use.
(Other solutions considered – cost
and implications)
L10
Have External Sources of Finance Not applicable but note possibility of S106
Been Considered (details)
L10
Revenue Implications Loss of interest per 25K investment @5% £1750.
(full year cost/ savings and detail)
L10
Can Revenue Implications Be No
Funded From Committee Base
Budget (details)
Accountable Officers for the project appraisal
Project Manager name and signature A Forzani/J Vadgama ……………
Date ……………………
Chief Officer name and signature Steve Davies ……………….……….. … Date ……………………