Version 5 Beaudesert and Henley in Arden Joint Parish Council (JPC) Report on the floods of 20th July 2007 By: The JPC Working Party which investigated the floods March 2008 Contents 1. Introduction 2. Floods July 2007 Background Recommendations Action List Appendices: 1. Report by W J Burton 3. Flooding in Stratford-on-Avon District recovery plan July 2007 PAGE 1 of 25 Version 5 1. Introduction Following the floods of July 2007, the JPC instigated a working party to report back to the council recommendations that should be followed through to minimize any further flood problems for the future. The working party consisted of Stephen Thirlwell (Chairman), George Atkinson, Stephen Dorow, Laurence Marshall and George Matheou. The Working Party met 4 times and received information from the following residents that were not members of the working party:- Peter Scholes and Mike Hammerman. The working party also commissioned a report from Mr W J Burton – an hydrography expert. This report was funded by both SDC and WCC. We are indebted to both those councils for funding this report as well as the assistance given to us by David Tiley of SDC. It was hoped that by the time this report was published that the Environment Agency report would have been published so that a detailed response could have also been given in tandem to this report. A copy of the SDC interim report on flood recovery is attached for information. Currently SDC is working with the Environment Agency, Severn Trent and Warwickshire County Council and will publish in April 2008 a report which will prioritise and offer a coordinated plan to direct future flood prevention. That report will be made available to the Parish Council as soon as practicably possible. It is understood that a report will also be forthcoming from the District Council which will be looking to the future regarding flood defences etc. This report should be read in tandem with the official report by Mr Burton (see Appendix 1) PAGE 2 of 25 Version 5 2. Floods July 2007 Background Prior to Friday 20th July 2007, The Parishes of Beaudesert and Henley in Arden had suffered continual light rain for nearly 36 hours resulting in the surrounding land being saturated. It should be noted that both parishes, for want of a better word lie in a valley. During the evening and night of Thursday 19th July the rain intensified, the River Alne was reported to be ready to break its banks on the morning of Friday 20th July. The rain did not ease off, the result of which is the River Alne broke its banks by the Bird in the Hand right down and past the Warwick Road Bridge. The flooding was caused by both pluvial (water running off the land) and fluvial (rise in the river) flooding resulting in flooding of the Stratford Road north of the town, Millfield Court, the High Street in general from the Northern entrance down to St Johns Church, the majority of the houses and businesses on the east of the High Street from the northern entrance down to St. Johns Church, Beaudesert Lane and Prince Harry road. There was also concern that houses that back on to Jubilee Play area in Castle Close could also flood. It was also reported that the River Alne suddenly dropped late Friday with a suggestion that some type of flood gates had been opened. It is known that the floods started to ease during the evening of Friday 20th July with part of the flooded High Street and Beaudesert Lane being accessible by foot late Friday evening. At 08.00 on Saturday 21 st July the mop up had started. It is also known that 42 private dwellings have applied for and received via SDC the grants that have been made available via the government and the Red Cross. The number of dwellings could be higher as not everyone might have registered for these grants. This figure does not take into account businesses that suffered as well as community assets like the Library and St Johns Church. During the working party’s work programme the drains on the High Street have been monitored. It is also reported that garden chairs and decking have had to be removed from the River Alne to alleviate possible future flooding. PAGE 3 of 25 Version 5 Recommendations There will no doubt be plenty of debate over the next few months, on whose responsibility certain tasks are, never mind calculations about the odds on further flooding. It should be remembered that flood defences within Henley are based on a 1 in 100 chance. Since Easter 1998 Henley has had 2 floods. There will probably be debates on the cause i.e. is it because of global warming. In the light of this 2 facts should be remembered, 1) our weather climate is on the change temperatures are rising, in January 2008 the outside temperature has been 12 degrees C if not higher! 2) Henley has had major floods twice since Easter 1998. The recommendations have not only looked at how to be better prepared, but also looked at being proactive in ensuring that work is done in the future to alleviate flooding problems, but planned maintenance work is built in as a standard for the future. It is therefore recommended to the council that the following actions are undertaken and followed through :1. That the Environmental Agency install an early warning system by way of an alarm that is audible through out the town when flooding is a probability. Such an alarm should be positioned within the centre of the town at a high level. 2. That the Parish council ensure both businesses and private dwellings have sufficient sand bags in preparation should such an event reoccur in areas that are prone currently to flooding 3. The Environmental Agency carry out regular de silting on the River Alne 4. The Environmental Agency confirm what flood alleviation programme is current for the River Alne. 5. The Environmental Agency survey and carry out both de silting and improvement works upstream from Henley on the River Alne with the aim of ensuring that the river flows freer and is not allowed to become over burdened with debris. 6. The County Council carry out a continual planned maintenance programme of the drains to ensure that the drains are clear of debris. 7. The County Council look to improve road side drainage so that drains can take future demand. 8. The District Council increase the road side gulley cleaning to ensure that debris is not deposited in the drains. 9. The Parish Council look at recommendations to divert the pluvial waters running off Jubilee play area. 10. The Parish Council follow through and gain the assistance of the National Flood forum to ensure that Henley’s risk of flooding is lowered. 11. Through the District Council work is undertaken to educate those people who have culverts and gullies within their boundaries and are kept clear of obstruction PAGE 4 of 25 Version 5 12. Stratford District Council to upgrade their planning guidance to ensure that all new builds within the current 1 in a 100 chance of flooding are flood resistant i.e. all services above the possible flood height such as power points positioned higher, water resistant plaster used etc. 13. In the next JPC news letter both email addresses and postal addresses for companies that offer flood defence protection are listed. This report should become a key working document for the JPC and modified as future flood reports become available to ensure that the risk of flooding is minimised within the town. It should be used as a proactive working tool to look forwards. Each agency and council should be written to separately to ensure that work is undertaken, Copies of this report along with copies of Mr Burtons report to be sent to the following: J Plaskitt MP for his assistance in getting these tasks outwith the JPC’s control undertaken J Maples MP – for information only - as Henley will be in the Stratford on Avon constituency after the next General Election Chief Executive of WCC Chief Executive of SDC Portfolio holder for Environmental Services SDC Head of service Environmental Services SDC David Tiley for info SDC Minister for the Environment Chief Executive of the Environmental Agency January 2008 Postscript February 2008 At the Parish Council Meeting on Monday 4th February 2008, the council heard from a Henley resident, Mr P Scholes, who with Parish Councillor Goodman walked the River Alne from Warwick Road towards Wootton Wawen past the mill. Photographs were also presented showing the state of the river. It was reported that the River is silted up, with apparently no maintenance work being undertaken, where the river has made islands there is evidence of a build up of rubble and brickwork. The Council resolved to write to the Environment Agency demanding a site visit to alleviate these problems which are impeding the flow of the river. As an ‘aide memoire’ there follows an action list of what is needed. Funding and responsibility for this is outwith the control of the Parish Council. It is imperative that the Parish Council takes ownership of this action list and continually reviews and updates the actions to ensure that the work is undertaken with in Henley. It needs to be an agenda item at every Parish Council meeting PAGE 5 of 25 Version 5 Flooding Action List Action Responsible Agency (ies) Outcome Installation of Flood Alarm - Warning Environmental Agency Parish Council To inform and prepare Residents Short Term Fix Environmental Agency Severn Trent Long Term fix To ensure that the flow of the River Alne is not impeded Environmental Agency Severn Trent Environmental Agency Severn Trent Warwickshire County Council Long Term Fix To ensure river remains free flowing Long Term Fix To ensure that river remains free To ensure that drains work to the max to aid clearance of water To ensure that the drains can cope with future demand October 2008 Improve performance June 2008 Sandbags – to ensure that all properties that are prone to flooding have sand bags Survey and remedial action River Alne – to include de silting, debris clearance through the parishes of Henley Beaudesert and Wootton Wawen Continual planned maintenance and de silting of River Survey the length of River Alne from source to reaching the Avon, to improve flow County Council to completely clear all drains of debris and to introduce a planned maintenance schedule of continual cleaning County Council implement an improvement programme on drains primarily on all roads that have been flooded and secondly through out the town District Council to increase road side gulley cleaning to ensure that debris does not get into drains through out the whole town Flood prevention Jubillee Play area to ensure that pluvial waters running down the land can be diverted from house close by Parish council to take advice from National Flood Forum to ensure that it can learn from best practise and build further to ensure future flooding is minimised Working with District Council to ensure that those people that have culverts and gullies that run through their land that culverts and gullies are kept clean Planning Guidance and Policy to be upgraded to ensure that future build is flood resistant Next Parish Newsletter to list web sites, telephone numbers and addresses of all companies that can offer personal flood defences. Future News Letters to carry updates on the flood work PAGE 6 of 25 Warwickshire County Council Stratford District Council drain prevention Target completion Date October 2008 May 2008 October 2008 October 2008 May 2008 October 2008 October 2008 Parish Council Parish council Long prevention term June 2008 Parish Council Stratford District Council Short prevention term June 2008 Stratford District Council Long prevention Term Parish Council ongoing October 2008 April 2008 Version 5 PAGE 7 of 25 Version 5 Appendix 1 _________________________________________________ W J Burton BSc CEng MICE MCIWEM 24 The Moorlands Malvern Wells Worcestershire WR14 4PS Telephone/Fax: 01684 567928 E-mail: wjburton@ukonline.co.uk _________________________________________________ STRATFORD-ON-AVON DISTRICT COUNCIL FLOODING AT HENLEY-IN-ARDEN 20th JULY 2007 - (with Addenda) General Report 1. Heavy rainfall over the Henley-in-Arden area on 20.07 combined with saturated ground conditions related to antecedent rainfall brought about extremes of both overland, over-highway and watercourse flow resulting in the internal flooding of a large number of properties in and around the town. Councillors Marshall and Matheou gave me a conducted tour of the affected area on 18.09. Councillor Marshall provided a list of questions which had been raised with him. Councillor Matheou provided a report on lessons he felt were learned from the flooding. Residents of Prince Harry Road have also promised a report about flooding in their area. 2. On the conducted tour we first visited the area to the north of Henley around the Bird-in-Hand public house. The R.Alne here had failed to pass all its flood flow through the twin arch road bridge. There had been much heading up at the bridge and water had overflowed onto the road, to then use the roadway as a supplementary flow channel. Some considerable depth of flooding on the road developed, up too 500mm in parts. High velocity flow was also reported in the over-highway flooding. The river channel itself to the east of the road was naturally and greatly overflowing its banks. All was a clear demonstration of the magnitude of the flood flow passing through the area. The extensive flooding prevailed in similar form down to the town boundary at the old railway viaduct and where the Henley Flood Alleviation Scheme (FAS) works commence. Various minor obstructions and deformations to the river channel were observed en-route. Whilst significant at low flow they would have been of little consequence or impact at the high flood flow prevailing on the day. 3. A check with the Environment Agency has confirmed that they have yet to fully analyse the flood return period of the event and also the performance of their flood alleviation works. My own analysis of, albeit smaller, watercourses around the area has found that their catchments were struck by rainfall of at least 1 in 200 and perhaps up to 1 in 1000 year return period. 78mm of rain falling in about 6 hours was recorded at Alvechurch, upstream of Henley. Consequent flood flows observed in watercourses around the area have been two and three times what would be expected from their catchments for the 1 in 100 year flood event. It is therefore likely that the R.Alne suffered a similar PAGE 8 of 25 Version 5 fate. The FAS works for example would have been designed to the normal Agency design standard of the 1 in 100 year flood flow, with some allowance or freeboard added to cover for some deterioration of the channel capacity and defence height with time and for the possible adverse impact of climate change. In practice this is often achieved by adding 20% to the design flood flow and then adding 300mm to the design height of the defences. Clearly the flow which passed through the area on 20.07 was perhaps 100% greater than the scheme design flow and overwhelmed the FAS works. Minor changes to the catchment area consequent on recent development, golf course landscaping etc are barely relevant once the whole catchment area has become so saturated and very run-off responsive to rainfall, as it did on the day. 4. At Millfield Court, just within the confines of the FAS works, the defences were overtopped and the ground floor of the building internally flooded. The ongoing new development on the opposite bank is, if current planning guidance is being followed, taking place on land which is above the 1 in 100 year flood level. It may well be therefore that areas of the site, and areas to be occupied by new houses, were flooded by the greater flow prevailing on the day. Existing recent development in the vicinity, with ground floor levels set to the longstanding Agency recommendation of 600mm above the 1 in 100 year flood level, was not internally flooded. Lower properties, cellars and basement car park areas though were naturally flooded. 5. The same situation prevailed on the High Street through the town. Newer and higher floor level properties survived; older, generally lower property was internally flooded. The problems in the High Street were further compounded by overland flow from the west side of the town running down to the High Street and migrating more to the east side. Gully capacity and highway drainage capacity is only capable at best of dealing with 1 in 5 year type flows. Whether a few gullies are blocked or not working again is barely relevant when flows far in excess of 1 in 100 year are looking to drain away to the river. The river at the same time is also backing up or tide-locking the various outfall runs of highway drainage systems anyway. The flooding problems experienced are also further compounded in water quality terms by the same rainfall completely overloading the public foul and combined sewer system. This is only designed to deal with 1 in 10 year type flows, so foul contamination of any floodwater is an unfortunate consequence. As the river moves over to the east from Beaudesert Lane downstream, so did the flooded area. A large number of quite newish properties in Prince Harry Road were therefore flooded before the river escaped the confines of the town. 6. In summary then the area generally seems to have been struck by a flood event of extreme magnitude, with overland, over-highway and watercourse flood flows in excess of any present day (or recent FAS) design or performance standard. It is of statistical and climate-change concern to the author that similar was said in relation to the floods of Easter 1998 only 9 years ago! Highway drainage at best is only designed to cater for 1 in 5 year order of flow; water company sewer systems at best contain 1 in 10 year order of flow and are supposed to bring about no internal flooding of property, in their own right, up to the 1in 30 year horizon. Environment Agency design standards and PAGE 9 of 25 Version 5 flood alleviation scheme standards at best consider Q100 order of flow with sometimes a 20% increase to allow for the possible adverse impact of climate change and then perhaps 300mm height added to any defence level. All pales into insignificance when in the area of Henley, flows of perhaps 100% increase over the 1 in 100 year flow have occurred. 7. Moving on to the difficult area of consideration of improvement options and lessons learned, the first thought that springs to mind might be to “do nothing” in the light of the apparent statistical “extremeness” of the event. This may indeed be the Environment Agency’s eventual response in relation to the FAS. In practical terms though there is certainly much merit in seeking to achieve the best hydraulic performance from what drainage exists in the area. The culvert/bridge structures are in the main in good order and of reasonable capacity. Those within the FAS have been thoroughly checked and capacityenhanced accordingly. The same cannot be said of most of the river channel sections outside the FAS extent. Clearance and resectioning is required throughout. Much however is in individual riparian ownership making the process difficult to promote or enforce. The provision of flood attenuating storage upstream of Henley does not look to be an option. There are no readily available areas to be topographically or hydraulically able to provide the necessary vast flood storage volume to have any significant effect on peak flood flow. Even several thousand cubic metres of mobilised flood storage would only contain or delay a 1 in 100 year order of flow for but a few minutes - and the flow that passed through on 20.07 for even less a time. The Agency would also have considered upstream storage as an alternative or supplementary to the FAS when it was originally promoted. 8. The highway drainage system and the public sewer system merit similar attention to achieve the best hydraulic performance. The highway drainage system looks to be in reasonable order. There will always be certain gullies and lengths of pipework in need of more attenuation than others. There are, unfortunately, rarely any proper records of the highway drainage system. The county council should be approached however to review their system and maintenance procedures accordingly. The same may be said of the public sewer system and the water company, but the water company generally hold very high quality records of their system. It should be born in mind that most of the piped drainage systems in Henley do appear to work reasonably well under “normal” heavy rainfall event conditions. 9. Probably the most economic option for Henley is to deal with extremes of flooding such as that experienced on 20.07 by building in flood “resilience” to the properties affected and implementing, as best as can be achieved with the short response times prevailing, a town flood warning and evacuation procedure. In refurbishing the flood-damaged property, consideration should be given to using flood resilient construction and materials, for example new concrete floors with stone or tiled finish, no skirting boards, and using waterproof plaster and wall finish up to some reasonable flood level. All electrical, plumbing, communication and security services should be routed and terminated above flood level. Non-return valves should be fitted to foul drainage connections and consideration should be given to the fitting of flood PAGE 10 of 25 Version 5 gates or barriers to all external doorways, windows and airbricks below flood level. Fixed furniture should be kept to a minimum and much should be removable/stackable. A flood warning and evacuation procedure could be geared into the Environments Agency’s Floodline service, certainly in relation to the main R.Alne flooding. For the smaller but still very flood-responsive tributary catchments though, the only warning that might be able to be issued in time would be little better than the type of warning given by the Met. Office on the days before when rapid accumulations in some areas “perhaps over 60/70mm” were predicted – which was right. I hope that my report answers the many questions raised with Councillor Marshall and supports the concerns and many of the lessons learned as set out in Councillor Matheou’s report. WJB/SDCHENLEY01/27.09.07 Addendum 1 – Prince Harry Road I have also received a copy of a report by Mr P Scholes on the flooding at Prince Harry Road. It mainly relates to the design, performance and maintenance of the river works carried out as part of the Bloor Homes development there. I have tried to discuss the detail/content of Mr Scholes report with the Agency. The present response is that the Agency has yet to fully analyse the flood return period of the event and the performance of the flood alleviation works and the river system through Henley. Many of their FASs, even quite recent ones, were overwhelmed by the flood flow on the day. They have therefore engaged consultants to carry out this analysis work across their area. Investigations and therefore any formal responses, are expected to take at least 3 months. I have however managed to glean some information which I offer as some sort of informal response. I understand that the river works carried out as part of the development were in the form of a two stage channel (base flow channel linked to elevated flood flow channel) all designed to carry the same design flow as the earlier FAS. There are no designed flood embankments as such to contain any higher flows within the two stage channel. The banking shown in Mr Scholes’ report as having once existed at the boundaries of the properties (Points A & B) does not appear to have been part of the works design. The higher constructed banking where Prince Harry Road runs alongside the channel (Point C) is a feature of the road/pavement design/construction rather than being an elevated flood embankment. I further understand that the two stage channel is maintained by the Agency, irrespective of its ownership. The maintenance extends to annual mowing/cutting-back of vegetation and desilting of the channel as necessary. I therefore believe that the river works at Prince Harry Road, as at Millfield Court and elsewhere, were simply overwhelmed by a flood flow in excess of the design flow and any spare capacity provided. The flooding of the gardens and properties was the unfortunate consequence. For a more detailed response than this, I feel that we will have to wait for the Agency’s deliberations. WJB/05.10.07 PAGE 11 of 25 Version 5 Addendum 2 – Back Lane On 17.10 I met with Mr S Dorow of Droitwich House, 125 High Street. He described and demonstrated the flooding mechanism that had internally flooded his house, the one behind, the various properties that back onto what is the ancient High Street and the Back Lane newer development running down to the river. The flooding here was simply an extension or outfalling of the High Street flooding discussed in 5. above. Floodwater ran from the main High Street at quite some speed into the spur of High Street and along the ancient High Street in looking for an outfall to the main river at some point. The highway drainage of the spur of High Street has only two gullies which were overwhelmed anyway. The gullies appear still partially blocked. Mr Dorow is to contact the Budbrooke office of the county council to establish the extent of the adopted area of the High Street spur and the ownership of the gullies and pipework therein and to then report the attention required to the gullies and to the flood-damaged road surface. Mr Dorow also reported a meeting with a Severn Trent Water officer, after an earlier, lesser flooding event, who offered to investigate the provision of more gullies in this part of the High Street. I suspect the officer later confirmed that such provision was not STW’s responsibility but failed to report back to Mr Dorow. There appeared to be few gullies or gratings serving the back of High Street area. The newer Back Lane development appeared to have a conventional gully and pipe system, presumably outfalling to the river at the rear. Floodwater similarly overwhelmed the old and newer Back Lane development, building up a head of water against the boundary walling to the river, exacerbating the flooding. However, it appears that eventually the river also overflowed the walling – certainly at the back of the property behind Droitwich House. With the eventual falling of flood level in the river the aforementioned walling, still with a head of water behind it, was pushed into the river, where it remains, obstructing at least the base flow in the river. Mr Dorow understands that there are crayfish in the river, the presence of which is delaying the removal of the walling by the Environment Agency. As stated in 8. above the highway drainage system and the public sewer system merit attention generally to achieve the best hydraulic performance. In terms of dealing with such extremes of flooding though, what is stated in 9. above also applies. Flood “resilience” needs to be built into the properties affected and some sort of town flood warning and evacuation procedure needs implementing. On a more practical front, overland flood routings might be investigated to more safely convey floodwater from the High Street spur and Back Lane area across to the river. This could be over road, path, paved area, garden area and between buildings. Care will be required though at the outfall of such routings to the river where non-return valves or gates will be required to prevent any high river level backing up into the routings. WJB/17.10.07 PAGE 12 of 25 Version 5 Addendum 3 – Jubilee Recreation Area On 17.10 I also met with Mrs C Goodman of Castle Close. She also described and demonstrated the flooding mechanism that had operated on the recreation area and threatened internal flooding of a number of properties in Castle Close backing onto the recreation area. Fortunately none were internally flooded but four were only a few millimetres above the consequent flood level generated. The recreation area and the wooded bank to the rear on the day became so saturated and run-off responsive that an extensive overland flow was generated which, without any flow-interrupting or flow-gathering features in the recreation area, simply ran over the gardens of the houses to gather at their rears. Fortunately all had an available flow route across the rear and down the side of the house and to the road frontage, all at a sufficiently low level, to convey the water just below levels where it might internally flood the house. It is essential that these routes are preserved and if possible improved by opening up and lowering. There would also be merit in the householders having door boards, air brick covers and a few sandbags to hand. The parish council, who effectively own the recreation area, might also look to some landscaping and drainage works on the area to control any future extreme rainfall event overland flow. The works would have to be consistent with the use of the area by children and some discussion should be had with the recreation area’s safety inspector. The council might first consider a small embankment feature around the lowest corner of the area against the rear gardens. This could not economically be constructed to provide a volume to control a flow of the magnitude of 20.07 but might wholly deal with lesser events and at least reduce the impact of extreme events. Installation of a rubble filled large soakaway behind the embankment would also assist in under-draining the naturally wet area in this lowest corner of the area. Consideration should also be given to the provision of a cut-off ditch along the upper boundary of the area to intercept overland flow from the woodland. A similar, but more costly, feature could be had by reconstructing the lateral footpath across the area, in the form of a single-sized stone-filled trench, perhaps 1m deep, topped with a geotextile sheet and normal footpath surfacing. WJB/17.10.07 PAGE 13 of 25 Version 5 Appendix 2 Flooding in Stratford-on-Avon District RECOVERY PLAN July 2007 3 October 2007 Version 5 Contact : Robert Walsh robert.walsh@stratford-dc.gov.uk for Stratford-on-Avon District Council PAGE 14 of 25 Version 5 1. Impact of the 2007 Floods on Stratford-on-Avon a. Areas most severely affected b. Households affected c. Businesses affected d. Assessment of impact 2. The response – management and delivery 3. Short term actions undertaken 4. Recovery Policies 5. Action Plan PAGE 15 of 25 Version 5 1. Impact of the July 2007 Floods on Stratford-on-Avon The District has been severely affected by flooding in the summer of 2007. Heavy rain caused the River Avon to rise on 9 July 2007. This caused flood water to enter 33 homes in the District On 20 July pluvial flooding was caused by heavy rain throughout the day, which the drainage system was unable to cope with. As the surface water entered the river networks there was then progressive fluvial flooding with the Avon, Stour, Arrow and Alne rivers rising rapidly and then bursting their banks in many places between 20th and 23rd July. As a result, over the weekend (Friday – Sunday) roads were blocked; properties damaged; homes contaminated; residents evacuated and made homeless. Stratford-on-Avon District Council’s emergency response centre was operational from 2.30p.m. on Friday 20 July. It operated constantly until 5.00 p.m. on Saturday 21 July, after which it reverted to office hours. 200+ calls were dealt with over the weekend, and the District Council provided regular information on the changing position within local communities. Operation of the The Emergency Planning Group for Warwickshire came together at 20.00hrs on Friday 20th July and coordinated activities over the next 48 hrs. This included a number of Warwickshire County Council, County Highways actions: Closure of 60+ roads at early stages and during heavy rain as events occurred 300+ flood warning signs sited across county Main roads, where damage had occurred, traffic management installed and debris cleared quickly Key bridges routinely inspected. a. Areas most severely affected The particular nature of the floods over 20-21 July 2007 (initial pluvial flooding due to surface water run-off, followed by fluvial flooding through rising river levels) left almost every settlement in the Stratford-on-Avon District damaged by flooding. Evidence of flood damage being collected by the District Council indicates over 100 communities suffered homes or businesses being flooded. Settlements known to have been severely affected include: Alcester Bidford-on-Avon Southam Shipston-on-Stour Welford Wellesbourne b. Households affected The District Council has collated available information on properties entered by flood water. This information has been gathered from the following sources: Telephone calls from residents during the emergency itself. Requests for collection of flood-damaged goods. PAGE 16 of 25 Version 5 Responses to requests for information made to elected Members and Parish Councils. Information on those presenting as homeless as a consequence of the floods. Rest Centre records. Applications for Council Tax relief. Registered Social Landlords. Initial assessment of the areas for which figures have so far been collated indicated 2.4% of households known to have been entered by floodwater. This level of flooding across the District would equate to some 1,500 homes. This estimate includes residents of 5 residential caravan sites situation in areas known to have flooded. These are sites where a mobile home is the permanent residence. In addition, there are 18 Multiple Licensed Holiday Caravan Sites, which have permanently sited mobile homes, in the District. Many of the latter are owned by an individual, rather than the site owner. The restriction on their license is that they can only live in the caravan for a maximum of 10 months a year. As a consequence a high proportion of these people live in the caravan for 10 months of the year, and spend 2 months on holiday, often abroad. The Council raised this issue with the DCLG on 10 August 2007. On 15 August 2007 the DCLG verbally indicated that these homes could be included in the Council’s submission under the Flooding Recovery Grant Scheme. There are an estimated 500 caravans which have been entered by floodwater on these sites (average 50 caravans on the 10 sites in areas known to have been severely affecting by flooding). The total number of residences across the District entered by floodwater or sewage as a result of the July 2007 floods is therefore estimated as 2,000. A database has been established to manage records and prevent duplication of results. All households in areas believed to have been flooded, together with those known to have had to move to alternative accommodation are being surveyed to establish the extent of any damage, and relevant information about the householder. This survey will, of necessity, take some months to carry out. c. Businesses affected The number of individual businesses directly affected by being flooded is relatively small, with 91 known businesses flooded, with estimates of a further 100 spread across the District. Shipston-on-Stour; Wellesbourne; Henley-in-Arden; and Alcester were worst hit numerically, but the nature of the flooding saw hospitality businesses spread all the way across the District entered by floodwater. d. Assessment of impact It is known that many properties flooded have been contaminated by sewage. In addition, homes around the Shipston-on-Stour area have been contaminated with oil from local business premises. 36 households have been evacuated into temporary accommodation as a consequence of the floods, and 14 remain in temporary accommodation provided by the Council. PAGE 17 of 25 Version 5 The Department of Communities and Local Government state that In the case of recovery from severe flooding, it should be assumed that 50% of displaced victims require accommodation for up to 3 months; 30% for up to 6 months, and 20% for up to 12 months. Research conducted by the Government Office for Yorkshire and Humberside estimates that 40% of businesses forced to close temporarily as a result of flooding never reopen. Similar floods to those of July 2007 were experienced in April 1998. Following the 1998 floods, bookings through the Tourist Information Centre dropped by a third, and visitor numbers by 40% compared to the previous year. The potential impact of the July 2007 floods on the local tourism economy is therefore significant, irrespective of the number of properties actually flooded. Business density in the district is exceptionally high; at almost twice the national average, ranking the district in the top 5 per cent of authorities nationally. In line with these figures the average business size in Stratford is small by national standards, with a mean of 7.41 employees compared to 11.51 in Coventry and Warwickshire, and 12.22 across the West Midlands. The immediate impact of the floods on businesses has mainly been upon town centre retail and service businesses in the towns affected. There are instances of flooding to commercial and industrial premises outside these areas but not on the same scale as in those towns. The problems being experienced by the tourism sector which was already suffering reduced bookings from a wet summer, have been greatly exacerbated by the floods and the continuing pessimistic press reports have further depressed this already vulnerable sector. In agriculture, market garden crops in south Warwickshire have been lost and extensive damage to fencing and pollution to be cleaned up. Overall, Towns and villages towns across the County have suffered from a general loss of trade as visitors and shoppers stay away, as well as experiencing staffing and stock difficulties through transport disruption SQW consultants have been engaged by Advantage West Midlands to undertake an assessment of the economic impact of the floods and the effectiveness of measures to address that impact. Warwickshire County Council, in partnership with Stratford-on-Avon District Council are working closely with SQW to enable a more robust assessment of the environmental and economic impact to be quantified. Data outlined in this report will be refined as a result of the SQW analysis 2. Short term actions undertaken In the immediate wake of the flooding, the following actions were undertaken to assist residents affected: Council’s emergency centre staffed 23-27 July specifically to deal with flood queries. From 30 July onwards the emergency numbers have been answered through the Council’s Contact Centre. Comprehensive flooding contacts and advice for home owners provided via the Council’s website. Flood damaged bulky waste collected free of charge PAGE 18 of 25 Version 5 Up to date information of both road closures and flood levels provided by press office for emergency services and media. Surveys undertaken amongst staff to register damage to household, businesses, infrastructure, other facilities and services Surveys undertaken on impact on all Parishes and Wards. PAGE 19 of 25 Version 5 3. Resourcing Longer Term Support The Council has built a record of the extent of flood damage in the District, and is working to refine that picture as described above. This information was provided to the Government Office of the West Midlands on Thursday 9 August 2007. A ‘Flood Recovery Group’ has been created to oversee recovery phase work. This group will meet on a monthly basis until all relevant work has been completed. The following funding has been secured to assist the District’s recovery: 4. £623,500 from the Department of Communities and Local Government in the form of a flood relief grant to assist individuals and families affected by flooding. £180,000 collected from the public through the Red Cross’s National Floods Appeal. The money can be used in order to provide grants to individuals to alleviate hardship as a result of the floods, (particularly targeting the elderly and households with children under five and those in financial hardship, such as on means tested benefits) and to some registered Community Groups. £100,000 from Advantage West Midlands (AWM) for specified projects to benefit the local economy. In addition SDC will seek to recover eligible costs incurred by application to the Bellwin scheme. Recovery Policies The Council’s priority is to help people to get back on their own feet, not to make them dependent on others for their future wellbeing. Support will be provided in line with the following policies. We will provide the same level of automatic support whether those affected were insured or not. This will help residents with insurance to meet their own obligations. We will provide the same level of support irrespective of tenure. We will provide an additional level of funding to the most vulnerable households affected. These will be those: o On means-tested benefits o Over the age of 75 o With disabilities o Families with young children (under 5) The Council will seek to reduce the risk of future flooding, improve the response to future emergencies, and increase public confidence, as well as helping those who were affected in July 2007. PAGE 20 of 25 Version 5 5. Action Plan Having considered the issues facing the District following the floods of July 2007, an action plan for dealing with these issues has been developed. This is presented below. The Plan identifies the key issues to be addressed, the specific actions for dealing with each of these issues, the resource needed for each, areas of responsibility and targets. It is intended to be dynamic with actions (e.g. XI – XIII) reviewed at a future stage. Delivery of the actions themselves will be monitored on an ongoing basis. The outcomes from this work in terms of strengthening public confidence and community resilience, will be assessed through a survey in summer 2008, identified under action XIV. Activity Timescale Resource Lead Comments / implications Organisation Status DEAL WITH PHYSICAL DAMAGE TO RESIDENTS GOODS (i.) Collect and 23 July 2007 - No charge SDC Now dispose of completed. made to flood-damaged residents. goods Cannot be funded through Bellwin scheme. To be funded through £50,000 allocated from DCLG Flood Recovery Grant. PROVIDE INDIVIDUAL FINANCIAL SUPPORT TO MEET NEEDS OF INDIVIDUAL HOUSEHOLDERS FLOODED 21 Version 5 Activity Timescale (ii.) Provide grant of £250 to all householders who experienced internal flooding Commences August 2007. Will continue until applications cease Resource Lead implications Organisation £250 per SDC household for 2,000 households = total cost of £500,000. To be funded from DCLG Flood Recovery Grant (iii.) Provide To be £150 per SDC grant of £150 to determined household for vulnerable following 1,000 households (on approval by households = means-tested Executive. total cost of benefits; or over £150,000. the age of 75; or Grants can be To be with disabilities; awarded using funded from or family with data collected Red Cross young children for action (i). Grant (under 5). SUPPORT LOCAL ECONOMY AND BUSINESS (iv.) Provide Ongoing from N/A Business Link advice to 23 July 2007 individual businesses affected by flooding Comments / Status 713 grants paid to 2 November 2007. Caravan Park owners have not permitted distribution of grant application forms, as they are concerned this will affect their licensing position. Flood Recovery Group has agreed to contact the owners to stress information gathered will not be used for that purpose. Awaiting approval from Executive to accept the Red Cross Grant. Achieved 22 Version 5 Activity Timescale (v.) Grants to individual businesses affected by flooding (vi.) Promote specified events and festivals to highlight that the District is ‘open for business’ Ongoing from 28 August 2007 a) Stratford Food Festival, 28-30 September 2007 b) Christmas on Avon Festival, NovDec 2007 c) International ArtsFest, May 2008 Resource implications Up to £5,000 per business (Must be member of FSB) We have requested confirmation from AWM of the amount that has been awarded for each festival, and the conditions attached, but have still to receive this. We have requested confirmation from AWM of the amount that has been awarded for each festival, and the conditions attached, but have still to receive this. We have requested confirmation from AWM of the amount that has been awarded for each festival, and the conditions attached, but have still to receive this. Lead Organisation Federation of Small Businesses Comments / Status Achieved Stratford Town Management Partnership We have requested confirmation from AWM of the amount that has been awarded for each festival, and the conditions attached, but have still to receive this. We have requested confirmation from AWM of the amount that has been awarded for each festival, and the conditions attached, but have still to receive this. We have requested confirmation from AWM of the amount that has been awarded for each festival, and the conditions attached, but have still to receive this. Stratford Town Council and Stratford Town Management Partnership Orchestra of the Swan 23 Version 5 Activity Timescale Resource implications (vii.) Improve August 2007 – £50,000 the Public July 2008 provided. Realm Lead Organisation SDC; Britain in Bloom Committees REDUCE RISK AND IMPACT OF FUTURE FLOODING (viii.) Conduct September Attendance Environment public meetings 2007 within existing Agency in areas most resources affected by floods. (ix.) Attend August – Attendance Town and meetings to December within existing Parish Councils discuss floods 2007 resources as requested by Town and Parish Councils (x.) Prepare Deadline Within SDC comprehensive January 2008 existing schedule of how resources each Parish was affected by flooding and the factors that contributed to it. (xi.) Agree Deadline Development SDC (WCC; costed and April 2008 of action plan Environment prioritised plan within existing Agency; of action to resources. Severn Trent reduce risk of Executive will Water are future flooding. be asked to critical to the allocate success of this) unspent funds from the DCLG Flood Recovery Grant to deliver the higher priority actions. Comments / Status £13,000 awarded to 6 Britain in Bloom Committees. 7 meetings held across the District. On target On target 24 Version 5 Activity Timescale Resource implications (xii.) Improve Deadline Executive will response to April 2008 be asked to future allocate emergencies. unspent funds from the DCLG Flood Recovery Grant to fund this action. (xiii.) Prepare Deadline Executive will and distribute a February 2008 be asked to Flood allocate Awareness unspent funds leaflet to all from the residents in the DCLG Flood District. Recovery Grant to fund this action. ASSESSING PUBLIC CONFIDENCE (xiv.) Public July 2008 Within consultation existing exercise carried consultation out, including budget survey of Citizens Panel Lead Organisation SDC Comments / Status Detail will depend on funding decision SDC Form and detail will depend on funding decision SDC Also used to assess impact of actions carried out. 25