Thames Area Forum – Progress Report on Issues Raised The following issues were identified during Councillors Question Time and will be progressed by Democratic Services and updated regularly. Date of Meeting 20th July 2010 and 3rd February 2011 and 21st July 2011 Issue Raised Lytham Road Bridge (1) Concerns over the weight of buses going over the bridge on Lytham Road resulting in an adverse affect on the road surface and bridge foundations. Action Taken/ Outcome Status Peter Cross updated the Forum at its meeting on 3rd February 2011 as follows: There are some concerns about the structure of the bridge but no immediate danger. A consultant’s report is expected imminently which will indicate the remedial work required in the long term. The 7.5 tonne weight restriction is advisory to deter heavy goods vehicles from using the bridge. In response to questions , Mr Cross advised that all bridges had been assessed to see if they were structurally safe to carry 40 tonne vehicles. He added that bridges were inspected on a regular basis and that this had shown deterioration in the Lytham Road bridge resulting in a report being commissioned. Following a general discussion relating to the weight restriction signage, Mr Cross offered to meet with the resident concerned to discuss the issue further. Ongoing Update received on 28th February 2011: From today all buses are diverted away from Lytham Road bridge and alternative routes have now been agreed with Blackpool Transport and Stagecoach. Investigations into what action can be taken regarding the structure of the bridge are ongoing as well as identifying sources of funding to deal with the issue. This is likely to take a period of time and further updates will be provided as and when available. Update received on 17th May 2011 Ownership and responsibility for Lytham Road bridge have been disputed for many years but clarification has now been obtained and the bridge belongs to Blackpool Council. We are currently carrying out further investigation works and surveys in order to assist in preparing a conceptual design report on the options for demolition / strengthening and costs. Once completed Updated 1st September 2011 Thames Area Forum – Progress Report on Issues Raised and a decision is made on the preferred option, then bidding for monies can be made. In the current financial climate, the funding may not be immediately available. Mitigating safety measures can then be pursued, including temporary propping of the structure. Unfortunately until the bridge is either re-built or suitably strengthened the bus route can not be reinstated. I can confirm that the carriageway is to be re-aligned to divert traffic loading away from the bridge supports. This work will commence this week. Current update - received on 20th July 2011 Blackpool Council became a unitary authority in 1998 Stewardship of bridges was transferred to BC from LCC at this time No survey drawings were passed to Blackpool Council. Indeed there was a clear lack of information and / or structural assessments The lack of maintenance has been partly due to difficulty in access and the fact that the steel beams are encased in concrete. This together with insufficient knowledge the structural capacity made for lack of progress. In any event there is a joint agreement in place with network rail over maintenance and NR have not done any maintenance to this bridge either. Recent progress Updated 1st September 2011 A formal Structural assessment has been undertaken This led to doubt on whether the bridge had enough structural capacity to carry HGV’s including buses Followed up with several site investigations to provide confirmation of strength which took several months of planning and liaison with Network Rail as any SI has is on Thames Area Forum – Progress Report on Issues Raised their land on a ‘live’ rail network Current status The bridge has failed the structural capacity of 40 tonne loading and the superstructure is in very poor condition There are significant cracks in the superstructure This scheme is now escalated to the top priority of bridge maintenance The preferred option is to replace the bridge at a cost of £1.8M We have a meeting scheduled for 11th August with the DfT to discuss if any funding will be available If not then the Council will have to make a decision of how to take this forward Further updated received 19th August 2011 The DfT has rearranged the meeting due to take place on 11th August 2011 to 21st September 2011. 21st July 2011 Suggestion made that a better alternative to the zebra crossing would be to install railings to the top of the bridge from both Hampton Road and Station Road as this would prevent people crossing the road and thereby eliminate the risk. It was previously recognised that pedestrians use the pinnacle of Lytham Road Bridge to cross Lytham Road. The decision was taken to formalise the crossing point on Lytham Road Bridge by providing a Zebra crossing, this was done on the grounds of pedestrian safety. Completed It was recognised that the top of the bridge forms part of a natural desire line for pedestrians crossing Lytham Road whilst it also provides a good vantage point for oncoming traffic. The Traffic Management’s approach was to provide a safe crossing point and not to prevent pedestrians from crossing. This is the reason why railings were not installed on the bridge. 21st July 2011 Safety concerns raised due to Landaus racing up the bridge and being unable to stop. Updated 1st September 2011 Response from Traffic Management This has been sent to Alison Metcalf who is a representative for the Landau association and asked her to pass on the community's Completed Thames Area Forum – Progress Report on Issues Raised concerns regarding landaus. There isn't anything further that Traffic Management can do. 21st July 2011 Safety concerns raised due to the speeding up of vehicles to go over the top of the bridge resulting in potential damage to the road surface and the potential for vehicles sliding back during icy conditions. Response from Alison Metcalf – Landau Association Representative I am not sure what is meant by racing but I think it is possibly the fact that if there is an incline a horse is more likely to set itself into the collar in order to maintain the forward motion. I will pass on your query to those who use that road and will raise it at the next meeting, which will be sometime in early September. Response from Traffic Management I have checked the accident data and have observed traffic using Lytham Road Bridge. There have been no accidents in the past 5 years that list excessive speed as a causation factor and no reported incidents involving vehicles sliding in the ice. Completed I also note there is a speed camera on the northbound approach to the bridge and speed camera warning signs on the approach. The visibility of the crossing on the top of the bridge also acts as a deterrent to vehicles speeding up. 21st July 2011 Much support was expressed for keeping the bridge and concerns raised that funds that have been given to the Pleasure Beach could have gone into restoring the bridge. Pleasure Beach funds Funds were not given to Pleasure Beach, it was a repayable loan of £5 million, which the Council borrowed to lend and costs, at least, are covered. Support for Lytham Road Bridge Response from Traffic Management Blackpool Council currently has six highway structure strengthening schemes in their programme. The total estimated cost of the six schemes is approximately £5.5M. It is the Council’s aspiration to carry out these works over the next five years, subject to funding being available from the Department for Transport. The list of affected structures is as follows :- Updated 1st September 2011 Completed Thames Area Forum – Progress Report on Issues Raised 1. Lytham Road Bridge 2. Harrowside Bridge 3. Princess Street Bridge 4. Gas Works Subway 5. Squires gate Lane Retaining Wall/Parapet 6. Watson Road Bridge The first priority is the reconstruction of Lytham Road Bridge. The condition of the superstructure and the results of the assessment give cause for concern, particularly the half through parapet edge girders. The bridge is owned by Blackpool Council, though there is a joint agreement in place with Network Rail over maintenance. Before the works can be finalised, further discussions are required with Network Rail and the utilities to agree the method of works. The scheme is top of the Council’s list of current priorities. A minimum period of 9 months will be required for design and preparation of the tender documents, with a contract period of 16 weeks. It is acknowledged that there is public support for retaining the bridge. It is too early, however, to provide confirmation on the final proposed solution and whether this bridge will actually be retained to carry traffic. Additional issue from 20th July 2010 and 3rd February 2011 Request for filter lights for traffic travelling north along St Annes Rd to turn right into Marton Drive or Watson Road before traffic travelling south along St Annes Rd is given the green light. Updated 1st September 2011 This request is currently being reviewed. Information is awaited from a Private Finance Initiative contractor on the phasing of the lights and the time period to assess the potential knock on effect of making the suggested changes. A further update is expected in June. Response from Traffic Management - 5th July 2011 Due to the number of vehicle movements at this junction, the junction operates a 120s cycle time, which is the recommended maximum cycle time for busy junctions. In order to give northbound travelling vehicles priority to allow them to turn right into Marton Completed Thames Area Forum – Progress Report on Issues Raised Drive and Watson Road an early start would have to be configured into the signal phasing increasing the cycle time. All approaches to the junction have a pretty constant flow of traffic travelling through and no one approach has a heavier flow than any other, obviously the situation during AM and PM periods is different and due to the heavier traffic flow the cycle time does increase above the 120s time period. Allowing an early start for northbound travelling vehicles will result in additional delays and congestion through this junction. As a result there are currently no proposals to amend the signal timings at this junction. Additional issue from 20th July 2010 and 3rd February 2011 Request for filter lights for traffic travelling east along Squires Gate Lane should be allowed to turn right into the Industrial Estate or make a U-turn to travel west along Squires Gate Lane before the traffic travelling west. This is where the problem is caused to traffic exiting Balham Avenue to mainly travel west along Squires Gate Lane. When exiting Balham Avenue one has to wait for a gap In the traffic travelling east along Squires Gate Lane. By the time there is a gap in the traffic the traffic lights have turned to red and when they again turn to green, there is a long queue of traffic travelling west. I would however like to add that the this junction will be upgraded in the 2nd half of 2012 as part of the PFI contract, as part of this work the Council will be looking at how the junction can be improved for all road users by undertaking engineers measures to improve traffic flows as well as reviewing the signal phasing as a result of any possible engineering works undertaken on site. This request is currently being reviewed. Information is awaited from a Private Finance Initiative contractor on the phasing of the lights and the time period to assess the potential knock on effect of making the suggested changes. A further update is expected in June. Response from Traffic Management – 5th July 2011 Traffic movements have been observed on a number of occasions at this junction. Sufficient gaps are available in between traffic flows allowing vehicles to turn right into the estate or undertake U turns with ease within the existing phasing of the lights. The issue here is that there is insufficient storage/capacity for vehicles wanting to make this manoeuvre and if a number of vehicles wish to make this manoeuvre together it does result in block back at this point. I will review the signal phasing at this junction and if there is the possibility that any minor changes can be made then I will arrange for this to be done. Further update received on 19th August 2011 I have re-visited this and also spoken to the Design Team for the PFI Updated 1st September 2011 Completed Thames Area Forum – Progress Report on Issues Raised contract. The junction was upgraded last year as part of the PFI contract and as part of the design process surveys were undertaken on site. As I have said previously, I do not perceive there to be an problem for vehicles wishing to turn right or undertake U turns at this junction. This is further supported by the survey undertaken by the PFI contract, there is not a high number of vehicles wishing to make these manoeuvres and there are sufficient gaps in between traffic flows along Squires Gate Lane to allow vehicles to make these movements should they wish. It is therefore my view that there is no problem at this junction and there is no requirement to amend the signal times/phasing. 21st July 2011 Concerns raised regarding the frequency of the No.5 and No.7 buses and a suggestion was made for these routes to be revised. May I also add, if residents from Balham Avenue use this junction to undertake U turns to then travel west along Squires Gate Lane, it may be more appropriate for them to use Faringdon Avenue, St. Annes Road and Squires Gate Lane. This alternate route will bring them out at the same point on Squires Gate Lane. Response from Blackpool Transport Further to your recent enquiry raised at the Thames Area Forum concerning the infrequency of the 5 and 7 services in South Shore. I would advise you that we share your concerns and reliability is our current priority issue. Between November 2011 and January 2012 we are aiming to revise all of our timetables in order to improve reliability across the network. At the present time we are working flat out to resolve the reliability issues on services 1, 7 and 11. We have prioritised these three services because these are the services that perform the most poorly, all other services in terms of performance will be addressed by January. One of the key issues with the 5 is, not only does it travel along some of the most congested roads in Blackpool and meet a very large number of busy junctions but it is also an extremely busy service and a very frequent one. A delay occurring to one bus means that the next one very quickly catches up. In respect Updated 1st September 2011 Completed Thames Area Forum – Progress Report on Issues Raised of the 7, the principal difficulty appears to be lack of running time within Blackpool town centre and buses quickly seem to bunch as a result. I trust that this information helps to illustrate that we share your concerns and are doing our level best to resolve these issues. In the meantime please bear with us. As the old adage goes “Rome wasn’t built in a day ”. 21st July 2011 Concerns were raised regarding the build up of traffic on Watson Road and Station Road as a result of coaches accessing the Pleasure Beach. I have looked at the access arrangements to the Pleasure Beach car park and have witnessed some minor queuing on Bond Street on the north bound approach to the car park entrance. My understanding is the queuing exists in the morning for a short period before the Pleasure Beach opens. Completed There is a Pay and Display bay on the west side of Bond Street before the entrance and Double Yellow Lines on the east side of the road. These parking restrictions prevent coaches from parking on Bond Street. The queuing I witnessed soon dissipated and was due to the barrier arrangements at the car park entrance. I do not propose to alter the parking restrictions on Bond Street because the existing Pay and Display provides valuable parking for visitors and the Double Yellow Lines on the east side are required to maintain the steady flow of traffic. 21st July 2011 Following concerns raised, it was agreed that a report detailing the structural integrity of all bridges would be made available. Updated 1st September 2011 Response from Traffic Management The list of bridges in the South Shore area as follows :1. 2. 3. 4. 5. Lytham Road Bridge Harrowside Bridge Princess Street Bridge Squires Gate Lane Bridge & Retaining Wall Watson Road Bridge Completed Thames Area Forum – Progress Report on Issues Raised Structural assessments are currently being undertaken on all of these bridges to ascertain the weight limits. The first priority is the reconstruction of Lytham Road bridge. The condition of the superstructure and the results of the assessment give cause for concern. The second priority is Harrowside Bridge which requires replacing. Squires Gate Lane Bridge is a single span riveted steel plate girder which requires major maintenance including concrete repairs, metal repairs and painting. Waterloo Road Bridge – this is a four span riveted steel plate girder bridge which requires major maintenance including concrete repairs, metal repairs and painting. St Annes Road Bridge, Yeadon Way. – This is a post tensioned bridge which requires a post tensioned special inspection to investigate cracking to the webs. Watson Road bridge is a two span bridge. The eastern span is constructed from cast iron girders with a brick arch deck. The western span is a brick arch with cast iron girder widenings. The construction date is relatively late for cast iron and it is suspected that the girders have been “reused.” A full report is being prepared highlighting the funding required to undertake major maintenance of the structures for inclusion in a forward programme of maintenance. The Council currently has insufficient funding to carry out these works. A meeting has been arranged with the Department for Transport to request emergency funding. Updated 1st September 2011