sPECIFICATION

advertisement
PRODUCT
SPECIFICATION
ScyonTM MatrixTM cladding
July 2012
Introduction
The following information outlines the specifications for the James Hardie ScyonTM MatrixTM cladding that can be included
into a project specification. Depending on the project, certain options can be deleted.
Note:
The ScyonTM MatrixTM cladding must be installed and maintained in accordance to the current James Hardie
ScyonTM MatrixTM cladding installation Instructions.
1.1
GENERAL CONDITIONS OF CONTRACT
Comply with statutory requirements/materials, labour and construction plant/materials and work, together with
additional conditions including: attending pre-construction meeting: Quality Assurance Inspection & Test Plan:
Warranties; and other.
1.2
SCYONTM MATRIXTM CLADDING
Scyon™ Matrix™ cladding consists of Scyon™ cavity trim installed over vapour permeable membrane to which the
pre-sealed Matrix™ panels are fixed. Manufactured from treated cellulose fibre, Portland cement, sand and water,
cured by high pressure autoclaving manufactured to AS/NZS 2908.2 ‘Cellulose – Cement products Part 2: Flat
sheets’
1.3
NO SUBSTITUTIONS
Substitutions are not permitted to any specified system, or associated components and products.
1.4
MANUFACTURER’S DOCUMENTS
James Hardie documents relating to work in this section are:





1.5
ScyonTM MatrixTM cladding installation Instructions
Alternate Eaves and Soffit Linings technical supplement
James Hardie® Fire and Acoustic technical specification
MSDS
ScyonTM Matrix™ Physical Properties
TERMITE PROTECTION
Where the exposed slab edge is used as part of the termite barrier system, a minimum of 75mm of the exposed
slab edge must be visible to permit ready detection of termite entry unless local building code regulations state a
higher clearance
Call 13 11 03
www.accel.com.au
www.jameshardie.com.au
1/4
THIS TECHNICAL SUPPLEMENT MUST BE READ IN CONJUCTION WITH THE CURRENT TECHNICAL PRODUCT LITERATURE. JAMES HARDIE BUILDING PRODUCTS MUST BE INSTALLED
IN ACCORDANCE WITH THE APPLICABLE TECHNICAL PRODUCT LITERATURE. ALL COMPONENTS AND ACCESSORIES MUST BE INSTALLED IN ACCORDANCE WITH THE RESPECTIVE
MANUFACTURER’S SPECIFICATIONS. FOR THE PRODUCT WARRANTY, TERMS AND CONDITIONS REFER TO THE APPLICABLE JAMES HARDIE TECHNICAL PRODUCT LITERATURE.
PRODUCT
SPECIFICATION
1.6
GROUND CLEARANCE
Install James Hardie external cladding with a minimum 150mm clearance to the earth on the exterior of the building
or in accordance with local building codes if greater than 150mm is required. Also, maintain a minimum 50mm
clearance between James Hardie external cladding and roofs, decks, paths, steps and driveways. Adjacent
finished grade must slope away from the building in accordance with local building codes, typically a minimum
slope of 50mm minimum over the first metre. Do not install external cladding in areas where it may remain in
contact with standing water or debris.
1.7
MATERIALS AND COMPONENTS
1.7.1
SCYONTM MATRIXTM CLADDING
Panels
(a) Thickness: 8mm,
(b) Sizes
 1190mm (Length) 1190mm (Width)
 1790mm (Length) 890mm (Width)
 2390mm (Length) 590mm (Width)
 2990mm (Length) 1190mm (Width)
Cavity Trim
(a) Thickness: 19 mm
(b) Sizes
 70mm (Width) 2450mm (Length)
1.8
FASTENERS
1.8.1
SCYONTM CAVITY TRIM FASTENERS
For timber frames, use a minimum class 3 Fastener 65mm x 2.8mm ring shank nail.
For steel frames 0.80mm – 1.60mm BMT, use a 52mm long Tri-Fixx® screw minimum class 3
1.8.2
FIX THE SCYONTM MATRIXTM PANELS TO CAVITY TRIM
1. C25mm 16 gauge 304 stainless steel brad nails when using brad nails ensure that brad nails are not
used in high wind area, no greater than a wind category of N3.
2. 2.8x30mm corrosion resistant fibre cement nails minimum class 3.
3. 25mm countersunk stainless steel screws minimum class 4.
4. 25mm wafer or pan head stainless steel screws minimum class 4.
1.8.3
1.9
WITHIN 1KM OF COSTAL ENVIRONMENT OR CORROSIVE ENVIRONMENT
All Fasteners to be a Class 4 minimum.
FRAMING
1.9.1
WIND CLASSIFICATIONS
Framing must be in accordance with AS 1684 - ‘Residential timber-framed construction’ and the framing
manufacturer’s specifications.
Call 13 11 03
www.accel.com.au
www.jameshardie.com.au
2/4
THIS TECHNICAL SUPPLEMENT MUST BE READ IN CONJUCTION WITH THE CURRENT TECHNICAL PRODUCT LITERATURE. JAMES HARDIE BUILDING PRODUCTS MUST BE INSTALLED IN
ACCORDANCE WITH THE APPLICABLE TECHNICAL PRODUCT LITERATURE. ALL COMPONENTS AND ACCESSORIES MUST BE INSTALLED IN ACCORDANCE WITH THE RESPECTIVE
MANUFACTURER’S SPECIFICATIONS. FOR THE PRODUCT WARRANTY, TERMS AND CONDITIONS REFER TO THE APPLICABLE JAMES HARDIE TECHNICAL PRODUCT LITERATURE.
PRODUCT
SPECIFICATION
1.9.2
FRAMING
STEEL
Use of steel framing must be in accordance with AS 3623 - ‘Domestic metal framing’ and the framing
manufacturers specifications. Use of steel framing must be in accordance with NASH Standard
Residential and Low-rise Steel Framing Part 1 Design Criteria and the framing manufacturer’s
specification. Framing members must have a base metal thickness (BMT) between 0.55 to 1.6mm. The
steel framing must have the appropriate level of durability required to prevent corrosion.
TIMBER
Use of timber framing must be in accordance with AS 1684 - ‘Residential timber-framed construction’ and
the framing manufacturer’s specifications. Use only seasoned timber.
STUD REQUIREMENTS


1.9.3
Steel 64 x 35 mm
Timber 70 x 35 mm or 90 x 35 mm
THERMAL BREAK
For steel Frames, it’s a building code requirement to install a thermal break behind direct fixed cladding.
James Hardie recommends the HardieBreak thermal strip. For ScyonTM MatrixTM cladding with a steel
frame, fix the HardieBreak Thermal Strip behind the ScyonTM Cavity Trim and in front of the vapour
permeable membrane. Refer to the HardieBreak thermal strip installation guide for more information
1.9.4
MOISTURE MANAGEMENT
A vapour permeable membrane must be installed under Scyon™ Matrix™ cladding sheets in accordance
with the AS/NZS 4200.2 ‘Pliable building membranes and underlays – Installation’ and the manufacturer’s
specifications.
The membrane must have the following properties in accordance with AS/NZS 4200.1:
 Vapour barrier - low or medium
 Water barrier – high
2.0
SEALANT
Polyurethane: James Hardie Joint Sealant.
2.1
CONSTRUCTION
2.1.1
2.1.2
2.1.3
2.1.4
ARRANGEMENT
The Scyon™ Matrix™ cladding panels must be fixed to the Scyon™ cavity trim. The Scyon™ Matrix™
cladding panels can be installed in a horizontal or vertical orientation. The panels are installed with a 10mm
expressed joint between adjacent panels, vertically and horizontally
VERTICAL JOINT
Join ScyonTM Matrix™ panels to James Hardie technical specification. (Refer to Figure 16, 17 and 18 of
the Scyon™ Matrix™ Installation instructions)
HORIZONTAL JOINT
At horizontal panel joints, the JH backing strip is bonded to the back of the Matrix panels to form a socket
to which the next course of panels are fixed over. The lower side of the JH backing strip can be bonded
using either James Hardie joint sealant or double sided backing tape, such as Henkel C3 12mm wide
double sided tape. (Refer to Figure 16, 17 and 18 of the Scyon™ Matrix™ Installation instructions for
details of construction of a horizontal joint)
FASTENER SIZE AND LAYOUT
Call 13 11 03
www.accel.com.au
www.jameshardie.com.au
3/4
THIS TECHNICAL SUPPLEMENT MUST BE READ IN CONJUCTION WITH THE CURRENT TECHNICAL PRODUCT LITERATURE. JAMES HARDIE BUILDING PRODUCTS MUST BE INSTALLED IN
ACCORDANCE WITH THE APPLICABLE TECHNICAL PRODUCT LITERATURE. ALL COMPONENTS AND ACCESSORIES MUST BE INSTALLED IN ACCORDANCE WITH THE RESPECTIVE
MANUFACTURER’S SPECIFICATIONS. FOR THE PRODUCT WARRANTY, TERMS AND CONDITIONS REFER TO THE APPLICABLE JAMES HARDIE TECHNICAL PRODUCT LITERATURE.
PRODUCT
SPECIFICATION
2.1.5
Fix ScyonTM MatrixTM cladding Panels to Cavity Trim using the fixings specified in James Hardie Scyon TM
MatrixTM cladding installation Instructions, Table 1 Scyon Matrix Cladding Design Table.
Panel fixing, and in accordance with the following requirements:  Nails must finish flush with sheet surface.
PAINTING
Scyon™ Matrix ™ cladding must be dry and free from dirt before painting. Coating must be completed within 3 months
of sheet installation. Minimum of two coats of exterior acrylic paint is required.
2.1
MAINTENANCE
It is the responsibility of the specifier to determine normal maintenance requirements. The extent and nature of
maintenance will depend on the geographical location and exposure of the building. As a guide, it is recommended
that basic normal maintenance tasks shall include but not be limited to:






Washing down exterior surfaces every 6-12months
Periodic inspections should be made to ensure fasteners are adequately securing the sheets to framing.
Re-applying of exterior protective finishes
Maintaining the exterior envelope and connections including joints, penetrations, flashings and sealants that
may provide a means of moisture entry beyond the exterior cladding.
Cleaning out gutters, blocked pipes and overflows as required.
Pruning back vegetation that is close to or touching the building.
*Refer to your paint manufacturer for washing down and recoating requirements related to paint performance.
TM and ® denote a trade mark or registered mark owned by James Hardie Technology Limited
Call 13 11 03
www.accel.com.au
www.jameshardie.com.au
4/4
THIS TECHNICAL SUPPLEMENT MUST BE READ IN CONJUCTION WITH THE CURRENT TECHNICAL PRODUCT LITERATURE. JAMES HARDIE BUILDING PRODUCTS MUST BE INSTALLED IN
ACCORDANCE WITH THE APPLICABLE TECHNICAL PRODUCT LITERATURE. ALL COMPONENTS AND ACCESSORIES MUST BE INSTALLED IN ACCORDANCE WITH THE RESPECTIVE
MANUFACTURER’S SPECIFICATIONS. FOR THE PRODUCT WARRANTY, TERMS AND CONDITIONS REFER TO THE APPLICABLE JAMES HARDIE TECHNICAL PRODUCT LITERATURE.
Download