PRODUCT SPECIFICATION ScyonTM MatrixTM cladding July 2012 Introduction The following information outlines the specifications for the James Hardie ScyonTM MatrixTM cladding that can be included into a project specification. Depending on the project, certain options can be deleted. Note: The ScyonTM MatrixTM cladding must be installed and maintained in accordance to the current James Hardie ScyonTM MatrixTM cladding installation Instructions. 1.1 GENERAL CONDITIONS OF CONTRACT Comply with statutory requirements/materials, labour and construction plant/materials and work, together with additional conditions including: attending pre-construction meeting: Quality Assurance Inspection & Test Plan: Warranties; and other. 1.2 SCYONTM MATRIXTM CLADDING Scyon™ Matrix™ cladding consists of Scyon™ cavity trim installed over vapour permeable membrane to which the pre-sealed Matrix™ panels are fixed. Manufactured from treated cellulose fibre, Portland cement, sand and water, cured by high pressure autoclaving manufactured to AS/NZS 2908.2 ‘Cellulose – Cement products Part 2: Flat sheets’ 1.3 NO SUBSTITUTIONS Substitutions are not permitted to any specified system, or associated components and products. 1.4 MANUFACTURER’S DOCUMENTS James Hardie documents relating to work in this section are: 1.5 ScyonTM MatrixTM cladding installation Instructions Alternate Eaves and Soffit Linings technical supplement James Hardie® Fire and Acoustic technical specification MSDS ScyonTM Matrix™ Physical Properties TERMITE PROTECTION Where the exposed slab edge is used as part of the termite barrier system, a minimum of 75mm of the exposed slab edge must be visible to permit ready detection of termite entry unless local building code regulations state a higher clearance Call 13 11 03 www.accel.com.au www.jameshardie.com.au 1/4 THIS TECHNICAL SUPPLEMENT MUST BE READ IN CONJUCTION WITH THE CURRENT TECHNICAL PRODUCT LITERATURE. JAMES HARDIE BUILDING PRODUCTS MUST BE INSTALLED IN ACCORDANCE WITH THE APPLICABLE TECHNICAL PRODUCT LITERATURE. ALL COMPONENTS AND ACCESSORIES MUST BE INSTALLED IN ACCORDANCE WITH THE RESPECTIVE MANUFACTURER’S SPECIFICATIONS. FOR THE PRODUCT WARRANTY, TERMS AND CONDITIONS REFER TO THE APPLICABLE JAMES HARDIE TECHNICAL PRODUCT LITERATURE. PRODUCT SPECIFICATION 1.6 GROUND CLEARANCE Install James Hardie external cladding with a minimum 150mm clearance to the earth on the exterior of the building or in accordance with local building codes if greater than 150mm is required. Also, maintain a minimum 50mm clearance between James Hardie external cladding and roofs, decks, paths, steps and driveways. Adjacent finished grade must slope away from the building in accordance with local building codes, typically a minimum slope of 50mm minimum over the first metre. Do not install external cladding in areas where it may remain in contact with standing water or debris. 1.7 MATERIALS AND COMPONENTS 1.7.1 SCYONTM MATRIXTM CLADDING Panels (a) Thickness: 8mm, (b) Sizes 1190mm (Length) 1190mm (Width) 1790mm (Length) 890mm (Width) 2390mm (Length) 590mm (Width) 2990mm (Length) 1190mm (Width) Cavity Trim (a) Thickness: 19 mm (b) Sizes 70mm (Width) 2450mm (Length) 1.8 FASTENERS 1.8.1 SCYONTM CAVITY TRIM FASTENERS For timber frames, use a minimum class 3 Fastener 65mm x 2.8mm ring shank nail. For steel frames 0.80mm – 1.60mm BMT, use a 52mm long Tri-Fixx® screw minimum class 3 1.8.2 FIX THE SCYONTM MATRIXTM PANELS TO CAVITY TRIM 1. C25mm 16 gauge 304 stainless steel brad nails when using brad nails ensure that brad nails are not used in high wind area, no greater than a wind category of N3. 2. 2.8x30mm corrosion resistant fibre cement nails minimum class 3. 3. 25mm countersunk stainless steel screws minimum class 4. 4. 25mm wafer or pan head stainless steel screws minimum class 4. 1.8.3 1.9 WITHIN 1KM OF COSTAL ENVIRONMENT OR CORROSIVE ENVIRONMENT All Fasteners to be a Class 4 minimum. FRAMING 1.9.1 WIND CLASSIFICATIONS Framing must be in accordance with AS 1684 - ‘Residential timber-framed construction’ and the framing manufacturer’s specifications. Call 13 11 03 www.accel.com.au www.jameshardie.com.au 2/4 THIS TECHNICAL SUPPLEMENT MUST BE READ IN CONJUCTION WITH THE CURRENT TECHNICAL PRODUCT LITERATURE. JAMES HARDIE BUILDING PRODUCTS MUST BE INSTALLED IN ACCORDANCE WITH THE APPLICABLE TECHNICAL PRODUCT LITERATURE. ALL COMPONENTS AND ACCESSORIES MUST BE INSTALLED IN ACCORDANCE WITH THE RESPECTIVE MANUFACTURER’S SPECIFICATIONS. FOR THE PRODUCT WARRANTY, TERMS AND CONDITIONS REFER TO THE APPLICABLE JAMES HARDIE TECHNICAL PRODUCT LITERATURE. PRODUCT SPECIFICATION 1.9.2 FRAMING STEEL Use of steel framing must be in accordance with AS 3623 - ‘Domestic metal framing’ and the framing manufacturers specifications. Use of steel framing must be in accordance with NASH Standard Residential and Low-rise Steel Framing Part 1 Design Criteria and the framing manufacturer’s specification. Framing members must have a base metal thickness (BMT) between 0.55 to 1.6mm. The steel framing must have the appropriate level of durability required to prevent corrosion. TIMBER Use of timber framing must be in accordance with AS 1684 - ‘Residential timber-framed construction’ and the framing manufacturer’s specifications. Use only seasoned timber. STUD REQUIREMENTS 1.9.3 Steel 64 x 35 mm Timber 70 x 35 mm or 90 x 35 mm THERMAL BREAK For steel Frames, it’s a building code requirement to install a thermal break behind direct fixed cladding. James Hardie recommends the HardieBreak thermal strip. For ScyonTM MatrixTM cladding with a steel frame, fix the HardieBreak Thermal Strip behind the ScyonTM Cavity Trim and in front of the vapour permeable membrane. Refer to the HardieBreak thermal strip installation guide for more information 1.9.4 MOISTURE MANAGEMENT A vapour permeable membrane must be installed under Scyon™ Matrix™ cladding sheets in accordance with the AS/NZS 4200.2 ‘Pliable building membranes and underlays – Installation’ and the manufacturer’s specifications. The membrane must have the following properties in accordance with AS/NZS 4200.1: Vapour barrier - low or medium Water barrier – high 2.0 SEALANT Polyurethane: James Hardie Joint Sealant. 2.1 CONSTRUCTION 2.1.1 2.1.2 2.1.3 2.1.4 ARRANGEMENT The Scyon™ Matrix™ cladding panels must be fixed to the Scyon™ cavity trim. The Scyon™ Matrix™ cladding panels can be installed in a horizontal or vertical orientation. The panels are installed with a 10mm expressed joint between adjacent panels, vertically and horizontally VERTICAL JOINT Join ScyonTM Matrix™ panels to James Hardie technical specification. (Refer to Figure 16, 17 and 18 of the Scyon™ Matrix™ Installation instructions) HORIZONTAL JOINT At horizontal panel joints, the JH backing strip is bonded to the back of the Matrix panels to form a socket to which the next course of panels are fixed over. The lower side of the JH backing strip can be bonded using either James Hardie joint sealant or double sided backing tape, such as Henkel C3 12mm wide double sided tape. (Refer to Figure 16, 17 and 18 of the Scyon™ Matrix™ Installation instructions for details of construction of a horizontal joint) FASTENER SIZE AND LAYOUT Call 13 11 03 www.accel.com.au www.jameshardie.com.au 3/4 THIS TECHNICAL SUPPLEMENT MUST BE READ IN CONJUCTION WITH THE CURRENT TECHNICAL PRODUCT LITERATURE. JAMES HARDIE BUILDING PRODUCTS MUST BE INSTALLED IN ACCORDANCE WITH THE APPLICABLE TECHNICAL PRODUCT LITERATURE. ALL COMPONENTS AND ACCESSORIES MUST BE INSTALLED IN ACCORDANCE WITH THE RESPECTIVE MANUFACTURER’S SPECIFICATIONS. FOR THE PRODUCT WARRANTY, TERMS AND CONDITIONS REFER TO THE APPLICABLE JAMES HARDIE TECHNICAL PRODUCT LITERATURE. PRODUCT SPECIFICATION 2.1.5 Fix ScyonTM MatrixTM cladding Panels to Cavity Trim using the fixings specified in James Hardie Scyon TM MatrixTM cladding installation Instructions, Table 1 Scyon Matrix Cladding Design Table. Panel fixing, and in accordance with the following requirements: Nails must finish flush with sheet surface. PAINTING Scyon™ Matrix ™ cladding must be dry and free from dirt before painting. Coating must be completed within 3 months of sheet installation. Minimum of two coats of exterior acrylic paint is required. 2.1 MAINTENANCE It is the responsibility of the specifier to determine normal maintenance requirements. The extent and nature of maintenance will depend on the geographical location and exposure of the building. As a guide, it is recommended that basic normal maintenance tasks shall include but not be limited to: Washing down exterior surfaces every 6-12months Periodic inspections should be made to ensure fasteners are adequately securing the sheets to framing. Re-applying of exterior protective finishes Maintaining the exterior envelope and connections including joints, penetrations, flashings and sealants that may provide a means of moisture entry beyond the exterior cladding. Cleaning out gutters, blocked pipes and overflows as required. Pruning back vegetation that is close to or touching the building. *Refer to your paint manufacturer for washing down and recoating requirements related to paint performance. TM and ® denote a trade mark or registered mark owned by James Hardie Technology Limited Call 13 11 03 www.accel.com.au www.jameshardie.com.au 4/4 THIS TECHNICAL SUPPLEMENT MUST BE READ IN CONJUCTION WITH THE CURRENT TECHNICAL PRODUCT LITERATURE. JAMES HARDIE BUILDING PRODUCTS MUST BE INSTALLED IN ACCORDANCE WITH THE APPLICABLE TECHNICAL PRODUCT LITERATURE. ALL COMPONENTS AND ACCESSORIES MUST BE INSTALLED IN ACCORDANCE WITH THE RESPECTIVE MANUFACTURER’S SPECIFICATIONS. FOR THE PRODUCT WARRANTY, TERMS AND CONDITIONS REFER TO THE APPLICABLE JAMES HARDIE TECHNICAL PRODUCT LITERATURE.