Lucknow Drainage Improvement Project Fact Sheet 7 March 2015 The Australian Government, Victorian State Government, East Gippsland Shire Council, and private businesses have been working collaboratively to improve drainage in the Lucknow area north of Princes Highway. This work addresses the current needs of the area and considers the future development needs of the land north and south of Lanes Road. Whelans Group Investments Pty Ltd is the construction company employed for the project. Previous Fact Sheets East Gippsland Council has issued six fact sheets from 2012 to 2014 detailing the progress of the design work; the reasons behind the concept; what the project will achieve, how the project will be delivered. These fact sheets are available on the East Gippsland Shire website www.eastgippsland.vic.gov.au or can be mailed out by phoning 5153 9500. Construction commenced on Wetland Retarding Basin 1 (WLRB1) in the Broadlands area with topsoil being stripped and stockpiled onsite, followed by bulk excavation to below finished areas where the wetland base required clay fill. Concurrent works occurred in part of the fill allotment site with topsoil being stripped in a cell pattern, fill excavated from WLRB1 was placed and compacted in the allotment site and topsoil placed back on fill areas. Patties Foods arranged for existing buildings to be removed or relocated from land on the corner of Princes Highway and Phillips Lane to facilitate filling of this site. Phillips Lane has been closed from 7am – 5pm Monday to Saturday when large construction vehicles are traversing between WLRB1 and the fill allotment site. The road has been open outside of these times. Eastern end of WLRB1 has been filled and compacted with clay to floor and walls of the wetland. The clay has been treated with lime and gypsum. Stockpiled topsoil has been relocated onto WLRB1 floor and walls. Required density testing has been undertaken on the subgrade at each successive layer of fill. Water trucks have been operating on site to minimise dust generation and assisting with the placement of lime and gypsum. Wildseed Nursery Pty Ltd (subcontractor engaged by Whelans) located in Nicholson has commenced wetland plant establishment in preparation for planting. This Fact Sheet (Fact Sheet 7) The purpose of this fact sheet is to advise that construction is well underway, provide an update on construction progress and outline next stages. What has happened since the last Fact Sheets? Whelans Group Investments Pty Ltd commenced site establishment in November 2014 including setting up environmental controls, site fencing, traffic management controls, site survey, set out of works and location of services. www.eastgippsland.vic.gov.au Lucknow Drainage Improvement Project Fact Sheet 7 March 2015 What will happen next? What land will be affected by construction? The western end of WLRB 1 will be completed and works will commence on the installation of the large drainage pipes under Phillips Lane that will connect the two wetlands. Land which will be affected by the construction works include: land that was previously owned by Patties Foods Pty Ltd and Broadlands Estate, which has been transferred in ownership to the Council and land on the corner of Princes Highway and Phillips Lane. These works will necessitate escalation of the current closure on Phillips Lane to a full road closure between 23 March 2015 and 3 April 2015, weather permitting. Appropriate signage will be put in place detailing proposed detours. We thank traffic users for their patience and every endeavour will be made to have Phillips Lane reopened at the earliest possible time. Rock beaching will be placed at the outlet of the pipes into WLRB1 after the headwall has been placed. Landscaping of WLRB1 will commence in the coming month, with over 90,000 plants to be planted across the wetland and surrounding reserve. Erosion control / weed matting and organic mulch will also be installed on the walls of the wetland. Wildseed will engage Gunaikurnai Land and Waters Aboriginal Corporation (GLaWAC) staff during the planting stages of the project. The allotment fill site will be finalised and the area will be fertilised and sown down with pasture grasses. Any future wetland construction requirements that will be triggered by development, to the area north of Patties Foods Ltd, will be the responsibility of future developers. How to find out more about the East Bairnsdale project? A special page has been set up on the East Gippsland Shire website to provide current information on the project: www.eastgippsland.vic.gov.au/Plans_and_Projects This page will be updated on a regular basis so that you can follow the project on line. For further information please contact East Gippsland Shire Council Telephone: (03) 5153 9500 Email: feedback@egipps.vic.gov.au Web: www.eastgippsland.vic.gov.au Construction will commence on Wetland Retarding Basin 2 (WLRB2). Further details about the work schedule and Project’s progress will be provided in Council fact sheets. www.eastgippsland.vic.gov.au