Project Name Project Change Management Plan Date - Version Project Change Management Plan Introduction This document is intended to describe the Change Control process in place to support and promote project management best practices. The Change Control Plan is not intended to prevent changes, as it is recognized that change is inevitable. The Change Control Plan is instead intended to ensure that changes to important work products, processes, and other documented information are communicated to affected parties both within and without the Project Team. This Change Control Plan describes the process for proposing changes to work products and the process by which change-controlled work products can be updated. Justification A project without Change Control is a project that is out of control. This process will help to: Communicate major changes to work products to a larger audience; Provide a process for input into, and feedback about, proposed changes; And provide transparency into the project management activities. It should be noted that until a work product has been reviewed and entered into Change Control, the work product can be freely updated. Only after the work product has been thoroughly reviewed and accepted will changes to that work product be controlled. Audience The Change Control Plan is intended to be consumed by the following parties: Project Stakeholders, including: o Project Managers o Subject Matter Experts o Sponsors o Clients o Project Team Members o Anyone requesting that a work product be modified once it has been entered into Change Control. Version [#] Page 1 of 5 Project Name Project Change Management Plan Date - Version Change Controlled Work Products – Definition and Examples A work product that is under Change Control is one that is considered important to the success of the project; changes to these should be communicated to the project team and, potentially, to the greater stakeholder audience. The Project Team reserves the right to decide which work products should be placed under Change Control. The following are examples of work products that may be placed under Change Control: Project Charter Project Schedule Project Budget Risk Management Plan Communication Plans User Acceptance Testing Plan Project Close Criteria Post-Production Plan Training Materials The Project Team may determine that there are other work products that should be placed under Change Control, or that some of the above work products do not require entry into Change Control. Placing Work Products under Change Control Work products that are to be placed under Change Control must be reviewed and approved by the Change Control board (described below). Work products should be in a finished state, i.e., usable by Project Team members. The process by which work products are placed under Change Control should reflect the following flow: NO Work Product creation Work Product Work Product Review Acceptable? YES Enter work product into Change Control Until a work product is under Change Control, changes to that product can be made freely. However, once the review to place the work product under Change Control has approved the work product, changes must pass through the Change Approval process. Version [#] Page 2 of 5 Project Name Project Change Management Plan Date - Version Change Control Board The Change Control Board is an entity responsible for determining whether individual Change Requests to work products under Change Control should be approved. The Change Control Board will consist of members of the Project Team who have a vested interest in controlling change to work products, and should include at a minimum: Sponsor Project Manager Client Subject Matter Expert The Change Control Board is responsible for: Determining which groups should be notified of individual Change Requests to work products under Change Control Ensuring that said groups are notified Ensuring that appropriate time is provided to potentially affected groups, such that they can respond to the Change Request, approve or disapprove of the Change Request, and modify any other work product or processes that may be caused by the implementation of an individual Change Request. Approving or denying individual Change Requests The Change Control Board holds final say as to whether an individual Change Request is approved or denied. Change Approval Process The Change Approval Process allows for changes to be made to work products that are already under Change Control. The process is driven by the creation and review of Change Requests. The process by which Change Requests are reviewed and approved (or denied) should reflect the following flow: NO Change Request created Change Request submitted to Change Control Board Change Request acceptable for review? YES Change Control Board notifies potentially impacted groups YES Board approves? Potentially impacted groups provide feedback to Change Control Board NO Project Team notified of update to Work Product Version [#] Work Product updated Page 3 of 5 Project Name Project Change Management Plan Date - Version A Change Request must provide the following information: Work product to be updated Requested change to work product Reason for updating work product Impact if work product not approved Potentially impacted groups if work product updated The Change Control Board will review Change Requests, and determine whether the Change Request contains sufficient detail and content to review. If the Change Request is approved for review, the Change Control Board will determine if any additional groups, beyond those noted in the Change Request, should be notified of the Change Request. Potentially impacted groups are responsible for providing feedback to the Change Control Board in a timely fashion. Once a reasonable amount of time has passed, the Change Control Board will make a final determination as to whether the Change Request should be approved. If the Change Request is approved, the requesting party must update the work product and notify the Project Team of the update to the work product. The Change Control Board will meet on an at least weekly basis to review outstanding Change Requests. Inclusion in this meeting is in no way limited to the Change Control Board. Version [#] Page 4 of 5 Project Name Project Change Management Plan Date - Version Appendix A Change Request Form Change Request Number: __________ Impacted Work Product: ____________________ Requested Change to Document: ____________________ Reason for the Change: Impact of the Change: Impacted Groups External to the Project: Version [#] Page 5 of 5