BA 352 Quiz 3 Name __________________________ 20) A project in the initiation phase may have a rough order of magnitude estimate in the range of a. -25% to +75% b. -100% to -50% c. +80% to +90% d. 0% to + 15% 21) Which of the following is NOT a major process for Cost Management? a. Resource Planning b. Cost Budgeting c. Cost Control d. Activity Sequencing 22) This is often viewed as the part of the budget intended to address the “known-unknowns” that can affect a project. a) Reserve analysis b) Cost estimates c) Contingency reserves d) Cost of Quality 23) a) b) c) d) What is a technique used for dividing and subdividing the project scope and project deliverables? Decomposition Project Charter Rolling Wave Expert Judgment 24) The process of identifying and documenting the specific actions to be performed to produce project deliverables. a. Define Activities b. Define Meetings c. Define Actions d. Expert Judgment 25) Which of the following is the most commonly used type of precedence relationship? A. Finish-to-start (FS) B. Finish-to-finish (FF) C. Start-to-start (SS) D. Start-to-finish (SF) 26) The processes and their associated tools and techniques which are documented in the schedule management plan. a. b. c. d. Project Scope Management Project Integration Management Project Time Management Project Hope Management 27) The process of identifying and documenting relationships among the project activities is defined as? a. Define Activities b. Sequence Activities c. Develop Schedule d. Control Schedule 28) This process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model. a. b. c. d. Develop Schedule Decomposition Sequence activities Mandatory dependencies 29) The project scope statement contains ……………….. and …………………… that can impact the development of the project schedule. a. Assumptions, Constraints b. Assumptions, Solutions c. Constraints, Solutions d. Constraints, Restrictions 30) A. B. C. D. A measure of schedule efficiency expressed as the ratio of earned value to planned value is which acronym? A. TCPI B. SPI C. SV D. BAC 31) What method introduces the concept of buffers and buffer management? a. Critical chain method b. Critical path method c. Chronic path method d. Time management method 32) A methodology that combines scope, schedule, & resource measurements to assess project performance and progress is which. A. B. C. D. Work performance data Earned Value Management TCPI Cost variance 33) Cost Performance Index (CPI) is a measure of the cost efficiency of budgeted resources and expressed in the ratio of: a. CPI=EV/AC b. CPI=EV-AC c. CPI=AC+BAC-EV d. CPI=CV-EV-AC