PHASE 2: JOINT STAKEHOLDER ENGAGEMENT for ROUTE ALTERNATIVES ASSESSMENT IN ITALY A. Route Alternatives Assessment – Brindisi 1 Methodology The overall objective of stakeholder engagement during the alternative assessment ( equivalent t o Route Refinement in other countries) of the ESIA is to gather additional information which is not available during desktop studies or field surveys as well as to verify data and identify social sensitivities that should be taken into account during the assessment. Stakeholders are a potentially important source for this data. It is also important to identify whether there is the potential for support or opposition from local communities or authorities towards the Project. The approach for undertaking stakeholder engagement during the alternatives assessment phase consisted of three main stages: • • • Stage 1: Notification to Authorities and Engagement with Key Stakeholders Stage 2: Broader Stakeholder Engagement Stage 3: Verification Activities 2 Stage 1: Notification to Authorities and Engagement with Key Stakeholders A key objective during Stage 1 was to identify any potential Project show stoppers associated with the route alternatives. A number of key issues and therefore stakeholders were identified as a priority to consult with during Stage 1. During this consultation, the team aimed to: • • • • formally introduce the Project and the Project team – or provide an update; collect any additional secondary data available; discuss the key issues identified for each stakeholder; and gain a better understanding of the local populations (local administration, demographics, presence of vulnerable groups, land use, livelihoods, etc. and any specific issues at the local level). In preparation for the field visit and as a first step in launching the Project locally, TAP organised an introductory meeting with the President of the Apulia Region and relevant Regional Department Managers (e.g. Economic Development, Tourism, Environment) to introduce the Project and the work to be undertaken by the Project team. The TAP team also consulted relevant authorities at the regional and local level in order to: • • • introduce the work of the Project team; request their support during implementation of field activities; and confirm the list of stakeholders to be engaged. 3 Stage 2: Broader Stakeholder Engagement The overall objective of the broader stakeholder engagement was to identify vulnerable groups and social sensitivities that should be taken into account during the assessment. Stakeholders provide a potentially important source for this data. It was also important to identify whether there is potential for support or opposition from local communities or authorities towards the Project. The main discussion areas during this stage of consultation were as follows: • • • formally introduce the Project and the Project team or provide an update; explain TAP’s stakeholder engagement approach; provide an overview of the field work; • • • • • 4 check completeness of the stakeholder groups identified; identify any key sensitivities such as sites of interest or vulnerable groups; gain a better understanding of the local populations (local administration, demographics, presence of vulnerable groups, land use, livelihoods, etc. and any specific issues at the local level); discuss the approach to consultation and the management of expectations, concerns and any misconceptions; discuss key issues and answer stakeholder questions to the extent possible at this stage of development of the Project. Outcomes of Stages 1 and 2 Consultation Activities Summary of Stakeholders Met Engagement activities during Stages 1 and 2 of the alternatives assessment process were carried out between October and December 2009. TAP team met around 50 stakeholders and used the following three main methods of stakeholder engagement: • Face to Face Meetings: 46 stakeholders met; • Focus Group: 1 Focus Group organised with 5 environmental NGOs; • P lenary meeting: 1 Meeting organised with inhabitants and owners along the Alternative 4D route. Face to Face Meetings Face to face meetings were held with: • • • • • • 11 public administration authorities; 11 utilities and infrastructure organisations; 3 universities and research centres; 4 trade unions; 16 industrial, agricultural and craftsmanship associations; and 1 religious representative. It was not feasible to meet with all identified stakeholders during this early consultation stage, so they were contacted and informed that they will be contactedin future for consultation at later stages. These are: • • • • • • Trade associations: AIAB (organic agriculture), APA (livestock farming), Federpesca and Legacoop (Fisheries association), Caritas (religious charity), Mesagne Municipality, NGOs: Fondazione di Giulio, Medicina Democratica, Ministry of Cultural Heritage (Archaeological Department, Architecture and Landscape Department), and Prefecture. Focus Group Discussion The following Environmental NGOs participated in the Focus Group Discussion: • • • WWF; Legambiente; Italia Nostra; • • LIPU; and Forum Ambiente Salute. Plenary Meeting A meeting was organised with inhabitants, landowners and stakeholders neighbouring the Alternative 4D route. Two hundred invitations were distributed and the meeting was broadly announced in media, but the number of attendees was significantly lower. The possible reasons for this could be that: • • • the local population (and in Italy in general) are unfamiliar with this type of public participation event; a gas pipeline Project does not raise major concerns; the TAP Project is not yet widely known publically, and the permitting process has not yet been initiated, so the invited stakeholders did not see any need to attend such a meeting at this stage. Summary of Discussions with Stakeholders The main general findings of the consultations were as follows: • • • • 5 No show-stoppers were identified on the new Alternative 4D route; The Apulia Region, the marine scientific researchers and several other stakeholders confirmed that Alternative 4D would be the preferable option; Most of the parties consulted appreciated the approach of early consultation adopted by TAP, especially considering previous tensions between industrial developers and the community in Brindisi; Farmers are familiar with gas pipeline installation, since the network is widespread in Italy, and the issue is perceived as routine, where there are no perennial crops (vineyards, olive trees). Stage 3: Verification Activities A consultation programme targeting national and local authorities to inform them on the results of the assessment was planned and initiated after completion of the Alternative Assessment Report (end of February 2010). The objective of the verification activities was to: • • • • validate the results of the alternatives assessment report; inform about the new base case; discuss any key concerns; discuss the objectives and format of the public disclosure meeting in Brindisi and the strategy to be adopted. TAP met Brindisi Municipality to explain the outcomes of the Route Alternatives Assessment and the reasons for judging Alternative 4D as the best alternative. The mayor informed TAP that the City parliament instructed the municipal administration on March 15th to initiate the establishment of a new Urban Development Plan (Piano Urbanistico Generale, PUG). A first strategy paper was issued on March 15th (Atto di Indirizzo), which earmarks the North of Brindisi for urban development as all other areas are blocked by other users (military, airport, industrial and energy production zones). The mayor suggested that TAP should revisit its current landfall location in order to avoid any interference with tourism and urban development. He indicated that alternative 3 seems to be a better option as it passes through an industrial area and would not add any constraint to the development vision for the city of Brindisi. The common understanding between the Municipality and TAP was to further assess Alternative 3 and to continue the consultation process in order to jointly identify a mutually acceptable solution. During verification activities TAP met the Ministry of Environment to inform them about the status of the Alternatives Assessment and of the stakeholder engagement activities. The Ministry confirmed that the route option should be accepted at local level before entering the permitting process. A routing through the contaminated site of Brindisi is not considered an advisable option by the Ministry’s representatives met, due to its costs and to the complexity of the related burocratic procedure. Further studies carried out on Alternative 3 concluded that this was also not acceptable, due to the crossing of an area with extensive industry infrastructure and buildings. The alternative also interferes with Natura 2000 protected area (Posidonia oceanica) and passes through areas of heavy soil contamination. Therefore the focus of the alternatives assessment was moved to the area of Lecce. B. Alternatives Assessment Stakeholder Engagement – Lecce 1 Methodology The overall objective of stakeholder engagement during the alternative assessment of the ESIA is to gather additional information which is not available during desk based studies or field surveys as well as to verify data and identify social sensitivities that should be taken into account during the assessment. Stakeholders are a potentially important source for this data. It is also important to identify whether there is the potential for support or opposition from local communities or authorities towards the Project. 2 Summary of Stakeholders Met Preliminary studies on Route 0a have shown that this route can be a real alternative to Route 4D in Brindisi. Therefore, TAP properly evaluated Route 0a and 4D to make a final decision. This evaluation required that the level of detail of Route 0a was comparable to Route 4D. It was therefore necessary to initiate a Stakeholder Engagement process in the municipalities affected to identify all socio-environmental advantages, disadvantages, potential impacts and risks. The following stakeholders were met during the alternatives assessment in Lecce: Public Authorities • Ministry of Cultural Heritage • • • • • • Puglia Region, Public Works Office Puglia Region, Environmental Sector Regional Authority for Cultural Heritage and Landscape Province of Lecce and Environment Sector of the Province Municipalities of Melendugno, San Donato di Lecce, Lequile, Cavallino, Lizzanello, Castri di Lecce, Vernole, Acaya e Roca Cultural Heritage Authority – Architecture (Soprintendenza). Environmental NGOs • • • • Italia Nostra, Lecce WWF Salento, Lecce SAVE Salento Legambiente Lecce Economic Entities and Associations • • • Snam Rete Gas Confindustria – Lecce Division Tourism Associations of Pisignano and Vernole 3 Summary of Discussions with Stakeholders The main environmental and social issues raised during these early phases of stakeholder engagement are summarised in the following Table B.1. These issues will be addressed by TAP by increasing the detail of information and analysis during subsequent phases of the ESIA. As no show-stoppers were identified during route alternatives engagement, TAP proceeded to the Scoping Phase. assessment stakeholder Table B.1 Key Environmental and Social Issues Raised during the Route Alternatives Assessment Stakeholder Engagement- Lecce Issue Title Issue Description Olive trees A concern was expressed about the possibility to re-plant mature or young olive trees on the working corridor and on top of the pipe. It was clarified that a strip of 8 m (safety zone) will be needed where deep rooted plans cannot be planted. SAIPEM advised that new Italian practices allow the planning of new trees within the safety zone but a review will be done to confirm this possibility. This issue was left open for further clarification. Details about the shore approach with micro-tunnel were requested to specifically identify where the pipe, on the sea floor would no longer be buried under the sand, It was agreed that Saipem would provide further material. Micro-tunnel Main Stakeholder(s) Who Raised The Issue •Municipalities representatives •Municipalities representatives Issue Title Issue Description Constraints on What will be the constraints on beach tourism, swimming, fishing, Beach tourism navigation. It was clarified that the route will be indicated on the and navigation nautical maps and that no anchorage will be allowed on the pipeline corridor. Pressure A concern was raised about the large extension of the pressure reduction reduction station (250x200 m) and its air emissions as well as risks Station and associated with the presence of the pipeline. It was explained that air pipeline emissions can derive from gas flaring and are an infrequent event pressure during equipment maintenance. The extension of the pressure reduction station will not be fully occupied by buildings but it is intended to guarantee a safety distance from the flare and the fencing. Coastal area Concerns were raised about constraints on the coastal area deriving and landscape from the coastal and landscape planning tools in force. TAP will protection further investigate. Local content Local industries should be involved in the construction of the pipeline and the pressure reducing terminal. TAP has already studied the territory and is also willing to work with the association to develop strategies to maximize local content. Off-shore TAP was advised that the region has requested offers for the contract biology of mapping the seabed to identify areas of coralligenous areas which will become future protected areas (SIC). Biocenosis characterization of the seabed will be required as part of the ESIA work. Expected impact on the fish population will also have been documented as part of the ESIA work. Recommendation to develop a Relazione Paessagistica (Landscape Cultural Impact report) addressing: heritage a. Cultural and landscape impacts b. Restoration of land and structures c. Impacts on cultural heritage elements Recommendation to develop Carta del Rischio Archeologico (Archaeology risk map). Recommendation to consider the requirements for the reconstruction of dry rock walls. Main Stakeholder(s) Who Raised The Issue •Municipalities representatives •Municipalities representatives •WWF •Confindustria •Apulia Region •Ministry of Cultural Heritage