10. Maintenance Planner for ‘September’ 2014
Highway Patrol
Highway patrolling is carried out regularly with two teams round the clock. The patrol
team monitors the traffic flow and encroachments into NH property, emergency
action in case of accidents like first aid, calling ambulance, information to all
concerned, clearing vehicles from road way to ensure smooth traffic flow. The
various other activities carried out like removal of parked vehicles, safety
arrangement to breakdown vehicles, removal of private approaches, timely
assistance to road users in emergency & keep utmost vigilant for road safety to road
users and road assets.
Turf Maintenance
Turf maintenance is being carried out using the grass-cutting machine @ Km 50+000
to 60+000, Km 80+000 to 90+000 & Km 110+000 to 121+000 as per monthly task.
Sl.No
Week
Chainage
1
I
2
II
3
III
4
IV
Km 50+000 – Km 52+000,Km 80+00 – Km
82+000,Km 110+00 – Km 112+000
Km 52+000 – Km 54+000, Km 82+000 –
Km 85+000, Km 112+000 – Km 115+000
Km 54+000 – Km 57+000, Km 85+000 –
Km 87+000, Km 115+000 – Km 118+000
Km 57+000 – Km 60+000, Km 87+000 –
Km90+000, Km 118+000 – Km121+000
Remarks
Land Scalping
Watering to the plants was carried out as and when required. Basin formation and
blowing of soil to the plants were carried out. Removing the unwanted plants was
carried out. Replacing of dead/missed plants is in progress.
ROW Clearance
Removal of Undesirable growth and vegetation in areas within the ROW is being
carried out regularly using the manpower. Watering is carried out as and when
required for the ROW trees. The clearance work carried out between Km 40+000 to
60+000, Km 80+000 to 90+000 & Km 110+000 to 121+000.
Avenue plantation
Replacing of Dead/missed avenue plants has been carried out during this month
from Km 28-121
Cleaning of MCW & SR
Cleaning of MCW & SR is being carried out using power Broomers and man power to
the entire project based on observation on daily basis.
Debris / Road Obstruction
Our patrol team & maintenance team removed debris on the carriage way
regularly by using men & machinery.
Culverts
The total no of culverts is 186. As per the schedule the cleaning of culverts are to be
done once at 6 months frequency. The cleaning of culverts between KM 55 to KM 60
- 14 nos., KM 84 to KM 90 – 9 nos. & KM 120 to KM 121– 6 nos. is completed during this
month.
Drainage
The total length of concrete drain is 21625m. As per the schedule the Clearing of
concrete drains are to be done at 4 months frequency. The clearing work carried
out between Km 33.650-34.700R (1050), Km 35.700-37.700L (200), Km76.340-76.850R
(510), Km 92.00-92.240R (240), Km 100.305-100.455L (150), Km 100.305-100.525R ( 220)
Building Maintenance
Building maintenance such as Toll plazas @ 103+000 & 53+000, Rest areas @ 72+000
RHS, 119+000 LHS & Truck lay bye @ 113+000 LHS & RHS, 70+000 LHS & RHS are done
regularly.
Shoulder Maintenance
Shoulder maintenance is maintained by using the approved borrow gravel with
compaction using the Roller is in progress and grader is used for removal of excess
soil and for levelling the shoulder.
Electrical
Street lighting, High mast, Feeder Pillar and Building lighting are being maintained
regularly. Rectification of Damaged electrical poles, Replacing of fused bulbs &
other electrical faults are progressed and in progress on daily basis with our electrical
team.
Encroachment removal
Encroachments were cleared from Km 28+000 to Km 121+000 on both LHS & RHS on
daily basis with our detected team. Periodic Removal at service roads and ROW
areas will also be taken up as scheduled.
Repair works
Repair works will be taken up at required locations like PGR’s, RCC Handrails,
Boundary stones, Median kerb, Culvert head walls will be carried out during this
month.
Painting works
Painting of faded locations like Median kerb, Pedestrian fencing & Road marking
have been carried out during this month in-between km 60-121.