PennDOT Emergency Projects Section 106 Consultation under FEMA

advertisement
PennDOT Emergency Projects
Section 106 Consultation under FEMA
Date:
County:
S.R.:
Section:
Lead Agency: FEMA
ER #:
Municipality:
Name:
To:
Catherine McManus
Federal Emergency Management Agency
From:
Brian Thompson, P.E., Director
Bureau of Project Delivery
Pennsylvania Department of Transportation
MPMS #:
As per agreement between the Federal Emergency Management Agency (FEMA), the Pennsylvania
Historical and Museum Commission (PHMC), and the Pennsylvania Department of Transportation, the Department
recommends that the above-referenced flood emergency project has a _____________________ Effect on historic
properties.
The following documentation is included or posted to Project PATH:
___ a copy of the Cultural Resource Field Assessment Form(s) or Package
___ Historic Resource Survey Data Sheet
___ a description of the project
___ the location of the project mapped on a USGS 7.5 Minute Topographic Map
___ one (1) copy of the archaeological survey report, and BHP report summary form
___ one (1) copy of the survey report, and one (1) copy of Pennsylvania Historic Resource Survey Forms
Architectural Historian: ___________________________
Archaeologist: ________________________________
If FEMA agrees with the Department recommendations, please notify the PHMC and our Department of
that agreement. If the PHMC does not object to the FEMA notification within 15 days, the Department will
presume concurrence and will proceed with this project without further review. If you have any questions please
contact Ira Beckerman @ 772-0830, or the Cultural Resources Professional(s) making this recommendation
cc:
BOPD Engineer:
PHMC, Douglas McLearen
PHMC, Regional Archaeologist and Architectural Historian
District Environmental Manager:
BOPD CR Section Chief: Ira Beckerman
Agreement by FEMA: _______________________________________ Date: ______________
To be completed by District Professional:
 No objection received from FEMA or SHPO.
Proceed with Project.
 FEMA disagrees with recommendation.
Do not proceed until CR Section is contacted
 Objection received from SHPO.
Do not proceed until CR Section is contacted
Date______________
By:_________________________________
Posting date:
______________
15 days after Posting:
______________