3 Layout In this section we present an overview of the changes which are considered in the ILC layout. While some of these changes are consequences of the proposed changes in the subsystem designs and are integral part of the SB2009 proposal, some have come about through continuing system design and development prior to the SB2009 re-baseline studies. Figure 3.1 shows schematic layouts of the ILC as proposed in the Reference Design Report (RDR), and as foreseen today in the SB2009 proposed new baseline. Figure 3.1: Schematic layouts of the ILC as proposed in the Reference Design Report (RDR) on the left, and as foreseen today in the SB2009 proposed new baseline on the right. The most obvious changes are in the central region, or specifically, the Damping Rings (DRs). Shortly after the publication of the RDR, the circumference of the DR’s was changed from 6.7 to 6.4 km to correct a inconsistency between the orbital revolution frequency of the rings and the RF frequencies of the injector buncher systems. This 6.4 km, six-fold symmetric ring design was located around the interaction region and elevated by 10 m above the Beam Delivery systems along with the e- injector and e+ KAS, (keep alive source). This allowed some independence in operation of the injectors and rings from personnel access to the Beam Delivery Systems (BDS). When considering the detail component layout of the six-fold ring, which has to accommodate RF systems, wigglers, circumference chicanes and injection and extraction systems, a different philosophy was explored. It is a two-fold design ‘race track geometry’ with long straight sections which included the same systems as in the previous design. The lattice of the arc sections was Layout20091130A changed to a new very flexible one, where the emittance and momentum compaction could be separately adjusted. These changes were accepted in 2008 before the SB2009 formal process was begun. For further detail regarding DR component layouts, see Section 4.5. These changes in geometry stimulated discussions regarding alternate layouts of the central region. Of particular interest are the changes made possible with the race track design, where the beam injection and extraction occur at nearly the same point in the center locations of one of the two long straight sections. Therefore, one can consider a DR to offset horizontally from the BDS and Interaction Region, but in the same plane, with short beam transfer lines between them. This, then, led to discussions of a compact and efficient central region, which incorporated all of the E+/injection systems, DR’s, BDS and Interaction Region in a single central campus. The long linac tunnels containing both the main linac and RTML beamlines would then extend outwards in either direction without interruptions. Here, the use of the word efficient refers to minimizing the necessary underground volume of tunnels, caverns and shafts. These ideas were combined with the construction scheme of the main linacs on the basis of the single-tunnel scheme, the Low Power option and Single Stage Bunch Compression into the AD&I Studies and the SB2009 Design. The single-tunnel linac layout incorporates the proposed single-stage bunch compressor. This singlestage bunch compressor ends up with the beams at ~ 5GeV as opposed to 15 GeV in the two-stage design. However, the changes of the geometry (distance along the beam line) to reach 15 GeV is minimall. The major change is that in the E- linac the total E+ generating system is moved to the central region, and therefore, the E- and E+ linacs are now identical, except for a short extra linac hardware to compensate for the beam energy loss incurred by the use of undulator to produce photons for positron generation. (the 2009 e+ conservative design has ~ 1.5 GeV more loss than the RDR). This means that changes in accelerating gradient, gradient distribution or maximum design energy, are easily accommodated. Changes of gradient of the order of 10% would not require little in the way of fundamental changes in the layout or of infrastructure support from CF&S. The central region is more complex and more difficult to describe. It is also difficult to display schematically unless a large artificial ratio is used between the longitudinal and transverse scales. Figure 3.2 shows the concept of beam lines which share tunnels in this region and these are included in the real tunnel schematics which can be found at ILC layout diagrams at http://ilc.kek.jp/SB2009/TUNNEL%20DRAWING%20SET%20(11-20-2009).pdf . Figure 3.2: Topological diagram of the beamlines in the ILC central area. Layout20091130A Many of the design details and changes of these systems are described in Section 4. The following is a discussion of the general layout and the design philosophy. The goal was to minimize the underground volume, as stated above, while developing the individual system designs and interfaces with CF&S beyond where they were at the time of the RDR. As the injectors and beam delivery systems which share beam line tunnels, are very varied in there support requirements (power supplies, RF, instrumentation etc), it was decided at an early stage of the studies that there would continue to be a single support tunnel for the central region. This is unlike the linac where each of the ~10+ km linac is comprised of repetitive units each extending over ~30 m. Even in the presence of this support tunnel, there is a reduction of ~5 km out of ~14 km in tunnel length in central region, not including the DR’s. The “Low Power” option, with half the number of bunches, enables, but does not require, a half circumference damping ring. This layout accommodates either of 3.2 or 6.4 km rings. It is because the 1 km straight section, which includes the injection and extraction from both rings, does not change in location or geometry with a change in circumference. The larger ring would have arcs with an increased radius, and again, an almost identical straight section for the RF and wigglers. Much of the effort to date has been on the region where the E+ production systems and the beam delivery systems co-exist. In the RDR, the E+ production system had to co-exist with the 150 GeV Ebeam which after the E+ system continued on to the IR. There were conceptual designs at the time of the RDR, whereas today, the designs now address many more practical engineering issues. For example, there are short sections of tunnel which will need “alcoves”. The alcoves will require to implement locally different tunnel cross-sections which are dependant on the local geology. Many of these issues were duplicated in the “Keep alive source” (KAS) in the RDR. The KAS has now been replaced by an “Auxiliary Source”, where an E- beam uses the same target, capture, booster systems as the gamma beam from the undulator. In the SB2009 design, now, there is only one vault which is designated to handle high radiation environment. (still to be determined but see below on MPS) The transition from a linac with a wide acceptance in energy and transverse phase space, to a small acceptance undulator or to a tight BDS requires both protection collimation and abort systems. In SB2009 a single section of collimation and abort system will protect both the undulator and the BDS in an integrated fashion, since the undulator is located at the end of the linac leading into the BDS. This is expected to offer an improvement in day to day operation which is difficult to quantify The E- injector easily fits into the SB2009 layout, whose geometry choice is primarily determined by the requirements from the E+ injector side. A natural asymmetry in the length of E- and E+ sides is exploited to incorporate a E+/- timing delay drift length which is expected to amount to a few hundred meters. It is highly desirable as stated in the RDR, that one injects into (fills) an empty DR bucket which has just been empted by extraction. This puts constraints on the difference in path lengths travelled by the electrons and positrons through the RTMLs, linacs and BDS’s and the DR circumference. At the time of the RDR, while this issue was well known, a fully worked-out beamline implementation solution was not presented, because with that layout and 6.4 km DR’s the path length correction had to be kilometers. In the SB2009 layout and with the 3.2 km rings, this correction can now be a few hundred meters. There are other examples where the SB2009 designs and layouts are more complete and detailed than the RDR. This is due to both the continuing design work over the time since the RDR but also driven by the AD&I studies of the SB2009 proposal. In some places this complicates comparisons. The detail system designs and their pro’s and con’s are based on these layouts and are discussed in Layout20091130A detail in the following sections. Figure 3.3 shows the overall schematic machine layout and Figure 3.45 gives the schematic directional beamline layout. Figure 3.3: Overall Schematic Machine Layout Layout20091130A Figure 3.4: Schematic Directional Beamline Layout Layout20091130A