Time based work plan and achievement Up to November, 2015

advertisement
Time based work plan and achievement
Up to November, 2015
Project Name : Padma Multipurpose Bridge Project.
Ministry/Division/Agency: Ministry of Road Transport and Bridges, Bridges
Division, Bangladesh Bridge Authority
Sl
No.
Work Description
as per work plan
(major work)
Work as per work plan
start
end
1.
Main Bridge
November
2014
November
2018
2.
River Training
Work (RTW)
November
2014
November
2018
Total Achievement
Status
%
Mobilization of equipments and 16%
procurement of materials are going on.
Already 3 Nos. Test Pile has been
driven out of 10 Nos. for Main Bridge; 7
Nos. Test Pile has been driven out of 16
Nos. and 28 Nos. Anchor Pile has been
driven out of 64 Nos. for Viaduct.
28,400 Ton steel plate out of 1,29,000
Ton has been already in site for pile
driving work. It is running to construct
150 m wide channel along alignment of
Main Bridge.
Mobilization of equipments and 12%
procurement of materials are going on.
Construction of Contractor’s office,
accommodation, work shed, stack yard,
casting yard, material storage yard,
labor shed, temporary jetty for loading
and unloading materials and equipments
etc. are also going on. Source approval
of some materials has already been
given to the Contractor and some are
under process. Plant has been installed
for Geo-bag filling. Also Ready Mix
Plant has been installed for production
of concrete block. Casting of concrete
blocks is running. Casting of 6,80,000
Nos. concrete blocks out of 1,33,01,248
Nos. has been completed. Dumping of
geo-bags is running. Dumping of
4,76,000 Nos. geo-bags out of
2,11,75,000 Nos. has been completed.
In Janjira side, dredging is going on.
3.
Construction
Supervision
Consultant-2
(CSC-2) for Main
Bridge & River
Training Works
Janjira Approach
Road
November
2014
November
2019
Supervision of work is going on.
14%
October
2013
October
2016
53%
5.
Mawa Approach
Road
January
2014
July 2017
6.
Service Area-2
January
2014
July 2017
7.
Construction
Supervision
Consultant-1
(CSC-1) for
Approach Roads
& Service Area-2
Land Acquisition
October
2013
October
2018
Approach Road = 10.579 km. Work is
going on. Construction work of Toll
Plaza, Police Station and Fire Service
Station is going on.
Approach Road = 1.67 km. Work is
going on. Construction work of Toll
Plaza, Police Station and Fire Service
Station is going on.
It has been handed over 12 nos. duplex
building, 20 nos. motel mess. Rest of
work is going on.
Supervision of work is going on.
August
2006
June 2015
4.
8.
Munshigonj: Proposed land = 400.75
hectre; Acquisition land = 330.89
hectre; Possession taken by PMBP =
261.72 hectre.
Madaripur: Proposed land = 571.13
hectre; Acquisition land = 386.53
hectre;
Possession taken by PMBP = 386.15
hectre
Shariatpur: Proposed land = 710.18
hectre; Acquisition land = 514.36
hectre;
Possession taken by PMBP = 467.57
hectre
# Total proposed land for three districts
=1682.06 hectre;
# Total acquisition land for three
districts =1231.78 hectre;
# Total Possession of land taken by
PMBP in 3 districts =1515.44 hectre.
It will be required additional Tk. 200.00
crore approximately for land acquisition
to install platform for 400 KVA power
59.87%
67%
46%
9.
10.
Resettlement
June 2009
activities(Compen
sation and plot
handed over)
June 2020
Environment
June 2020
June 2009
line in the river.
a) Tk.550.74 crore additional grant has
been handed over to the PAP up to
November/2015.
b) 1370 Nos. plots has been handed over
out of 1416 Nos. to the PAP which is
recommended by the “Project Level Plot
Allocation Committee”
up to
November/2015. Among, It has been
handed over 367 Nos. Landless families
without any cost.
a) Tree plantation has been started from
2012 and 67,550 Nos. of tree plantation
has
been
completed
up
to
November/2015 in resettlement area and
service area on both side of the river.
b)Consulting firm Agriconsulting S.P.A
& SODEV Consult International Ltd.
has been started their work which is
going on for “Biodiversity Baseline
Survey and Preparing Monitoring Plan,
Identifying Location of the protected
Sanctuary and Developing a Sanctuary
Plan of PMBP”
c) MoU has been signed with
Geological Department of
Dhaka University to stablished a
Museum in the project area and
signing of contract agreement is
under process.
d) RFP work is going on from selected
short listed firms
for “Consultancy Services for Preparing
a Comprehensive Documentation of
Padma Multipurpose Bridge Project”.
Download