Time based work plan and achievement Up to November, 2015 Project Name : Padma Multipurpose Bridge Project. Ministry/Division/Agency: Ministry of Road Transport and Bridges, Bridges Division, Bangladesh Bridge Authority Sl No. Work Description as per work plan (major work) Work as per work plan start end 1. Main Bridge November 2014 November 2018 2. River Training Work (RTW) November 2014 November 2018 Total Achievement Status % Mobilization of equipments and 16% procurement of materials are going on. Already 3 Nos. Test Pile has been driven out of 10 Nos. for Main Bridge; 7 Nos. Test Pile has been driven out of 16 Nos. and 28 Nos. Anchor Pile has been driven out of 64 Nos. for Viaduct. 28,400 Ton steel plate out of 1,29,000 Ton has been already in site for pile driving work. It is running to construct 150 m wide channel along alignment of Main Bridge. Mobilization of equipments and 12% procurement of materials are going on. Construction of Contractor’s office, accommodation, work shed, stack yard, casting yard, material storage yard, labor shed, temporary jetty for loading and unloading materials and equipments etc. are also going on. Source approval of some materials has already been given to the Contractor and some are under process. Plant has been installed for Geo-bag filling. Also Ready Mix Plant has been installed for production of concrete block. Casting of concrete blocks is running. Casting of 6,80,000 Nos. concrete blocks out of 1,33,01,248 Nos. has been completed. Dumping of geo-bags is running. Dumping of 4,76,000 Nos. geo-bags out of 2,11,75,000 Nos. has been completed. In Janjira side, dredging is going on. 3. Construction Supervision Consultant-2 (CSC-2) for Main Bridge & River Training Works Janjira Approach Road November 2014 November 2019 Supervision of work is going on. 14% October 2013 October 2016 53% 5. Mawa Approach Road January 2014 July 2017 6. Service Area-2 January 2014 July 2017 7. Construction Supervision Consultant-1 (CSC-1) for Approach Roads & Service Area-2 Land Acquisition October 2013 October 2018 Approach Road = 10.579 km. Work is going on. Construction work of Toll Plaza, Police Station and Fire Service Station is going on. Approach Road = 1.67 km. Work is going on. Construction work of Toll Plaza, Police Station and Fire Service Station is going on. It has been handed over 12 nos. duplex building, 20 nos. motel mess. Rest of work is going on. Supervision of work is going on. August 2006 June 2015 4. 8. Munshigonj: Proposed land = 400.75 hectre; Acquisition land = 330.89 hectre; Possession taken by PMBP = 261.72 hectre. Madaripur: Proposed land = 571.13 hectre; Acquisition land = 386.53 hectre; Possession taken by PMBP = 386.15 hectre Shariatpur: Proposed land = 710.18 hectre; Acquisition land = 514.36 hectre; Possession taken by PMBP = 467.57 hectre # Total proposed land for three districts =1682.06 hectre; # Total acquisition land for three districts =1231.78 hectre; # Total Possession of land taken by PMBP in 3 districts =1515.44 hectre. It will be required additional Tk. 200.00 crore approximately for land acquisition to install platform for 400 KVA power 59.87% 67% 46% 9. 10. Resettlement June 2009 activities(Compen sation and plot handed over) June 2020 Environment June 2020 June 2009 line in the river. a) Tk.550.74 crore additional grant has been handed over to the PAP up to November/2015. b) 1370 Nos. plots has been handed over out of 1416 Nos. to the PAP which is recommended by the “Project Level Plot Allocation Committee” up to November/2015. Among, It has been handed over 367 Nos. Landless families without any cost. a) Tree plantation has been started from 2012 and 67,550 Nos. of tree plantation has been completed up to November/2015 in resettlement area and service area on both side of the river. b)Consulting firm Agriconsulting S.P.A & SODEV Consult International Ltd. has been started their work which is going on for “Biodiversity Baseline Survey and Preparing Monitoring Plan, Identifying Location of the protected Sanctuary and Developing a Sanctuary Plan of PMBP” c) MoU has been signed with Geological Department of Dhaka University to stablished a Museum in the project area and signing of contract agreement is under process. d) RFP work is going on from selected short listed firms for “Consultancy Services for Preparing a Comprehensive Documentation of Padma Multipurpose Bridge Project”.