Lau Gatignon 21 June 2011 MINUTES OF CEDAR FLAMMABLE GAS SFETY MEETING Present: Agenda: J.Gulley / DGS-SEE, A.Sharma / PH-CMX (FGSO), V.Falaleev / PH-UFT (GLIMOS-NA62), J.Fry, C.Lazzeroni / NA62-UK, R.Guida, S.Haider / PH-DT, L.Gatignon / EN-MEF 1. Introduction 2. Gas System presentation 3. HAZOP 4. Zoning 1. Introduction V.Falaleev presented the CEDAR counter and its environment in the experimental cavern TCC8 with an emphasis on the gas system and potential leak sources, see slides. The CEDAR has a length of approximately 6 m and contains a gas volume of 1.1 m 3. The existing counter will be modified to have a shorter ‘nose’ and the light readout system (8 PMTs) will be replaced by a more performing and complex system with many more PMTs. The old control electronics will be removed from the upstream foot to a location further away. The downstream foot contains only two motors for adjustment of the horizontal and vertical orientation of the counter. The Cedar used is of Cedar-West type, normally used with Nitrogen gas, but for NA62 it will be operated with Hydrogen at an absolute pressure of up to 4 bars. On each end the counter is separated from the beam vacuum by a hydro-formed Aluminium window of 150 m thickness upstream (serves as fuse!) and 200 m downstream. Tests with such windows will demonstrate that they withstand the gas pressure (maximum 5 bars in operation) with the appropriate safety factors (tests to be defined with the help of P.Miguel Santos Silva, HSE unit). If so required following the results of the tests, the windows will have to be made thicker (the present windows are rated for 15 bars nominal working pressure and are 400 m thick). In case of rupture, the Hydrogen gas will escape directly into the beam vacuum and thus will not form a flammable mixture with air, although the shock wave may do very serious damage to the NA62 detectors (Gigatracker and Straws in particular). A large (~5 m3) vacuum volume will be connected to the beam vacuum to serve as buffer volume. The gas enters and leaves the detector from below on the upstream side. These are potential leak sources. Other leak sources were listed: the entrance and exit windows towards the beam vacuum, the quartz windows, the big O-rings above the two feet, the top vacuum and safety valves, the diaphragm motor and its feed-through and the gas pipe for the pressure gauge. Electrical equipment includes the diaphragm end-switches (inside the H2), the diaphragm motor and potentiometer, the four PT100 temperature probes and the horizontal and vertical motors for alignment with their switches and potentiometers. A number of CEDAR safety discussions have taken place in the past, in particular one on 24 November 2008. The present discussions were building on these previous ones. The PMT’s and their local electronics as well as the nose and the quartz windows will be housed in a Nitrogen enclose. The diaphragm motor will be outside this inert volume and will be replaced by a ATEX rated one. The same applies to the diaphragm end switches, which are inside the pure H2 volume that could be contaminated with air in case of a wrong manipulation. Finally it was pointed out that flammable/combustible materials shall be avoided in the vicinity of potential Hydrogen leaks. This concerns in particular the insulating material, which should be chosen mainly according to this criterion rather than solely optimum insulating performance. It was noted that the temperature in TCC8 should be quite stable anyway. Of the neighbouring beam equipment, only the FISCs were considered to merit further discussion in terms of zoning. 2. The gas system Roberto Guida explained the gas system in detail. Most of the system is installed in the surface buildings (gas building and a mixing zone in B918), but the vacuum and N2 flushing related parts are installed in the underground TCC8 area, not too far (~6 m) from the Cedar counter. The operating principle is that the detector is emptied as well as reasonably possible (to 0.1 mbar or better) before filling it to the required pressure with pure Hydrogen from bottles located in the gas building. All gas extracted (or escaping via the safety valve) from the detector is evacuated to the outside via a 22 mm diameter H2-rated exhaust line. An auxiliary system allows to flush the detector as well as the inlet and exhaust lines with inert gas, Nitrogen, e.g. in case of interventions on the counter or the gas system. The vacuum pump must be reasonably close, as it requires a large diameter vacuum tube (~25 mm diameter) to the detector with minimal impedance. For the filling two methods are available: a fast one for initial filling and a slow one for topping up (miniscule) leaks. Apart from computer controlled valves there are necessarily a number of manual valves. This has potential risks of bad manipulation, the consequences of which must be mitigated. In both methods the filling stops automatically when the required pressure has been reached, as measured by a pressure gauge. Emptying the counter is ‘just’ pumping out any gas present in the counter. Basically there are 4 procedures (“nodes” in the HAZOP language) to be analysed in depth: 1. Purging the counter and gas lines with Nitrogen gas, by computerized system, or – if necessary – manually, 2. Filling with Hydrogen – this requires manual intervention - and the automatic procedure to top up leaks 3. The pressure scan, where the pressure is lowered in small steps, alternated with efficiency measurements, 4. The emptying of the counter. These four nodes have been discussed in depth in the framework of a HAZOP risk analysis, see the next section. Manual interventions with potential safety implications must be logged by computer. This concerns e,g, manual valve or switch manipulations. Expert operators have the freedom to bypass certain parts of procedures. Such actions must be password-protected and logged. 3. The HAZOP HAZOP stands for HAZard and OPerability analysis. It is a systematic approach to each of the “nodes” analysed according to pre-defined keywords and parameters. Consequences and required actions are defined as a result. In our case we have defined four nodes. The detailed outcome of the HAZOP analysis is reported in the attached HAZOP sheets. Below we summarise some additional remarks that came up in the discussions for each node. 1. Purging the lines and detector, including the exhaust line The aim is to have a Nitrogen purity of at least 99%, as a contamination below 1% is considered harmless whatever the nature of the contaminant. It was pointed out that this is a possible action although not necessarily one that is used routinely for normal operation. It is mainly useful before interventions on the system or detector. The 1% is not measured but derived from the time of flushing. It was pointed out that for this node, like for the other ones, the proper function of the Cedar safety valve is the principle safety against overpressure in the Cedar volume. It was also pointed out that certain problems can occur in case the computer blocks. In that case a watchdog will diagnose this and stop all inlet and outlet processes. The gas will be left in the system as it is. Any alternative action could imply risks that are potentially worse than leaving the limited amount (< 200 mg) of Hydrogen in place. 2. Emptying the counter This is a rather simple procedure where all valves are closed, except the one between the counter and the vacuum pump. The beam must be evacuated to avoid rupture of the Cedar windows. 3. Hydrogen filling This is rather similar to the first node, except the fact that this time the Hydrogen inlet valve is opened instead of the Nitrogen one. 4. Pressure scan It is considered better to scan from high to lower pressure, as the opposite process could have a larger impact on the temperature in the detector and thus on the refractive index and detector performance. In view of the limited quantity of Hydrogen in the system, it was agreed that no “emergency dump” procedure for H2 evacuation is required. But this implies also that some zoning is necessary. 4. Zoning We discussed in detailed the need for some declared ATEX zones. As a result of our discussions and analyses eight zones were defined and they are described in Table 1. All other regions are not considered part of the zoning system: The diaphragm motor and feed-through would fall in a Zone 2 (declared around feed-through and safety valve in vicinity of motor), and therefore will have to be replaced by an ATEX rated motor. ATEX end switches (inside H2 volume, declared as a Zone 2) will also be required. The safety valve must be connected to the exhaust line, the vent of which wil also be a declared Zone 2. All ATEX Zoning referred to in Table 1 (apart from the gas storage building) to be recorded by FGSO for PH (A.Sharma) using standard forms. The alignment motors below the downstream end of the CEDAR will be outside the declared zone. These motors and switches need therefore not be ATEX rated. For the same reason the FISCS are considered to be outside the zone. It was discussed to avoid zone #7 by having fixed welded connections between detector and gas rack, but this was finally considered too impractical. 5. Final remarks The slides and some additional information is available from the Indico agenda of the meeting at http://indico.cern.ch/conferenceDisplay.py?confId=144135. The (ambitious) plan is to operate the modified Cedar with Hydrogen gas in TCC8 in the NA62 technical run in September or October 2012. TABLE (2 pages) Zone Description Comments 1 The gas storage building 2 The mixing zone inside B918 3 The underground gas system 4 Quartz windows This is where the Hydrogen bottles are stored. It is an existing gas building, but the detection equipment must be suitable for Hydrogen (light gas that goes upward, sensitivity to be calibrated for H2, etc). Needs to be /installed F.Schmitt (GS/ASE). As FGSO for the gas building he must also perform and record the Hazardous Area Classification (ATEX Zoning) using the standard form. In a narrow (~2 m wide) corridor behind the control rooms. This zone is relative well equipped, but the state of the roof must be verified and it must be emptied of temporary storage (cupboards, combustible materials, etc). For the Hydrogen rack which will be under Local exhaust ventilation: - if the rack is closed the zone (Zone 2) can be confined to the dimensions of the rack, - if not closed the zone may extend beyond the dimensions of the rack (e.g. 0.5 to 1 m). For the Hydrogen rack which will be under Local exhaust ventilation: - if the rack is closed the zone (Zone 2) can be confined to the dimensions of the rack, if not closed the zone may extend beyond the dimensions of the rack (e.g. 0.5 to 1 m). In practice this implies that the electronics rack of the gas system can be rather close (0.5 to 1 m distance from the gas rack). The gas lines from the rack to the Cedar may run over the floor, provided they are properly protected and separated from electrical cables. Only the central part of the Nitrogen enclosure that encapsulates the quartz windows are considered “Zone 2 NE, of Negligible Extent” due to the tightness of the seal. The outer part of the N2 enclosure that houses the PMTs and local electronics can be considered the safety area around this zone. A H2 detector must be installed in the top part of this outer part of the N2 enclosure. The N2 flow must be interlocked with the power to the electronics. Zone 5. 6. 7. 8. Description Comments Feedthroughs and safety relief The diaphragm motor would fall in a Zone 2 valve (declared around feedthrough and safety valve in vivinity of motor), and therefore it will have to be replace by an ATEX rated motor. Inside H2 volume ATEX end switches Iinside H2 volume, which will be declared as a Zone 2) will also be required. The gas connections The gas connections below the upstream part of the Cedar form a Zone 2 with dimension ±0.5 m. Its presence and boundaries must be clearly indicated and ignition sources are forbidden in this zone. Exhaust from vent lines An ATEX Zone (1 or 2) will be declared around the exhaust from the vent line (at a safe place outside), Table 1: The definition of the zoning