CableLabs Engineering Change Request

advertisement
CableLabsīƒ’ī€ Specification Engineering Change (EC) Form
Project
EC TRACKING INFORMATION (Blue fields to be completed by CableLabs only)
DOCSIS
N Identifier PHYv3.0-N-14.1207-2
Status
Affected Specification
ECR Date
ECO Date
ECN Date
ECN Effective Date
CM-SP-PHYV3.0-I11-130808
10/22/2014
Comment Period End Date 11/12/2014
SEVERITY
11/12/2014
Comment Period End Date 12/10/2014
Non-Critical
12/10/2014
114
Critical
Cert Wave No
Overall Type of Change (Tech/Edit/Both) Both
Version
2
CHANGE TYPE
Minor
Major
TO OBTAIN LATEST ISSUED SPECIFICATION WORD VERSION, CLICK HERE :
https://www.cablelabs.com/doczone/docsis/requirements/specs/current/issued/
TO SUBMIT EC, EMAIL COMPLETED FORM TO: docsis_ec@cablelabs.com
SPECIFICATION DOCUMENT DETAILS
Document EC is written against: CM-SP-PHYv3.0 Issued Version # I11
AUTHOR INFORMATION
Primary Author
Email
Company
Additional Contributors
First Richard Last Prodan
rprodan@broadcom.com
Broadcom Corporation
Kirk Erichsen
Title of EC
Date sent to CableLabs
PHY US Frequency Clarifications
10/14/2014
Date of revised EC
Brief description of revision
10/21/2014
Added REQ Changes Details
Country
Phone
USA
949-926-6417
ENGINEERING CHANGE DOCUMENT DETAILS
EC REVISION HISTORY
DETAILED PROPOSED CHANGES
Sections Affected
REQs Affected
3; 5.2.2; 6.2.17.1; 6.2.22; 6.2.22.1.2; 6.2.24
Yes
Test Plans Affected
Unknown
OTHER RELATED ENGINEERING CHANGES (LIST ALL THE APPLY)
The following EC(s) are recommended to be processed in conjunction with this document:
EC#
Title of EC
Affected Document
MULPI US Frequency Clarifications
CM-SP-MULPIv3.0
NOTE! IMPORTANT EC AUTHOR INSTRUCTIONS:
For an ECR to advance to ECO status:
- Requirements Affected section of the embedded DOCSIS-SpecDetailChange.docx must be completed.
- If applicable, the embedded TestPlanDetailChanges.docx must be completed.
For an ECO to advance to ECN status:
- If applicable, compiled MIB files and final Schema docs must be attached before requested changes can
move to ECN status and noted as attachments in the table directly below.
DOCSIS_Spec-TestPlan_EC-Form_9-2014.docx
1 of 2
In submitting the Engineering Change Request ("ECR"), the Author(s) [primary author, additional authors, and contributors], individually and as
an authorized representative of the Company, agrees that if CableLabs incorporates this ECR in whole or in part into the relevant Specification,
all intellectual property in the ECR shall be licensed royalty free, and without confidentiality, under the terms of the "Data Over Cable Service
Interface Specifications License Agreement" ("Contribution Agreement"). CableLabs may disclose the content of this ECR to CableLabs'
members and such others as is necessary for the development of CableLabs' specifications. Questions about the Authors' licensing of
intellectual property in this ECR submission may be directed to legal@cablelabs.com.
This Engineering Change has the following file(s) attached.
Type of Attachment(s) (Visio, Word, txt,
.yang, etc.)
File Name of Attachment(s)
DETAILED DESCRIPTION OF PROBLEM:
Cable operators are actively engaged in upgrades to extend the frequency range of the upstream plant to 85 MHz.
DOCSIS 3.0 specification text permits this frequency extension, but ONLY if the cable modem incorporates a
physical layer switched output bandwidth to support operation in plants with either legacy or extended upstream
frequency plans. There is no allowance for certification of a cable modem that supports only the extended
frequency plan, thus forcing cable operators to incur significant extra costs associated with switchable bandwidth
upstream operation. In anticipation of the fact that operators will eventually complete upstream frequency
extension, this EC allows for certification of cable modems that are compliant with the extended frequency
operation only, thus reducing the cost of equipment for those operators who do not require dynamic upstream
bandwidth selection.
CHANGE DETAILS FOR THE SPECIFICATION:
Complete Engineering Change details for the specification is contained in the following embedded file:
EChangePHY3.0-14.
1207-2.docx
CHANGE DETAILS FOR THE TEST PLAN (ATP):
Complete Engineering Change details for the test plan is contained in the following embedded file:
DOCSIS-TestPlanDet
ailChanges.docx
End of Request
Additional Instructions to EC Author
Embed_Doc_TrkChg_
Instr.docx
DOCSIS_Spec-TestPlan_EC-Form_9-2014.docx
2 of 2
In submitting the Engineering Change Request ("ECR"), the Author(s) [primary author, additional authors, and contributors], individually and as
an authorized representative of the Company, agrees that if CableLabs incorporates this ECR in whole or in part into the relevant Specification,
all intellectual property in the ECR shall be licensed royalty free, and without confidentiality, under the terms of the "Data Over Cable Service
Interface Specifications License Agreement" ("Contribution Agreement"). CableLabs may disclose the content of this ECR to CableLabs'
members and such others as is necessary for the development of CableLabs' specifications. Questions about the Authors' licensing of
intellectual property in this ECR submission may be directed to legal@cablelabs.com.