THIRD QUARTER PERFORMANCE EVALUATION REPORT OF THE WORCESTER BULK WATER SUPPLY PROJECT WCR005 BREEDE VALLEY LOCAL MUNICIPALITY WESTERN CAPE CHIEF DIRECTORATE: BULK INFRASTRUCTURE PROGRAMME PERIOD: 1 OCTOBER 2014 – 31 DECEMBER 2014 i REGIONAL BULK INFRASTRUCTURE GRANT PROGRAMME 31 DECEMBER 2014 TABLE OF CONTENTS 1 2 INTRODUCTION ............................................................................................................. 1 BACKGROUND TO THE PROJECT .............................................................................. 1 2.1 Project description .................................................................................................... 1 2.2 Project History .......................................................................................................... 2 2.3 Project concept, design and plan .............................................................................. 2 2.4 Start date duration of the programme........................................................................ 3 2.5 Funds previously allocated to the project .................................................................. 4 3 PROGRESS TO DATE ................................................................................................... 4 3.1 Milestones ................................................................................................................ 5 3.2 Implementation of the approved business plan ......................................................... 5 3.3 Schedule of work and phasing of the activities .......................................................... 5 3.4 Capacities dedicated to the programme .................................................................... 7 3.5 Key challenges within the project and not management ............................................ 7 4 PROJECT RESULTS AND BENEFICIARIES ................................................................. 8 4.1 Outcomes and outputs .............................................................................................. 8 4.2 Beneficiaries and project results ............................................................................... 8 4.3 Jobs created ............................................................................................................. 8 5 CONCLUSIONS/ LESSONS LEARNED ......................................................................... 8 5.1 Main successes and failures of the project to date .................................................... 8 5.2 Ownership and sustainability of infrastructure works ................................................. 9 6 RECOMMENDATIONS ................................................................................................... 9 ANNEXURE B: LIST OF VILLAGES EXPECTED TO BENEFIT ......................................... 11 ANNEXURE C: DETAILS OF CONTRACT .......................................................................... 12 ANNEXURE D: PROJECT SCHEDULE .............................................................................. 13 ANNEXURE E: DETAILS OF JOB OPPORTUNITIES ......................................................... 14 1 REGIONAL BULK INFRASTRUCTURE GRANT 1 31 DECEMBER 2014 INTRODUCTION In terms of Section 10(7)(b) of the Division of Revenue Act No 10 of 2014 (DORA) as promulgated in Government Gazette No 37595 dated 26 April 2014, the transferring national officer must submit an annual performance report for Schedule 6 within 45 days after the end of each quarter. The Regional Bulk Infrastructure Grant (RBIG) is a Schedule 6 indirect conditional grant for the benefit in kind of municipalities. The objective of this Report is to provide a performance evaluation report covering the 3rd quarter of RBIG funded projects, in compliance with the DORA. The objective of this evaluation was to determine whether the progress on the project is commensurate with the expenditure to date as well as to determine whether the project is still on course in terms of the original planning. This performance evaluation report, covering quarter 3 of the 2014/15 fiscal year is for the Worcester Bulk Water Supply, one of the Regional Bulk Infrastructure Grant projects currently being implemented by the Breede Valley Municipality in the Western Cape Province, with Department of Water and Sanitation (DWS) as funder, and Breede Valley Municipality as co-funder. 2 BACKGROUND TO THE PROJECT 2.1 Project description The primary focus is to augment current bulk water supply within the Breede Valley Local Municipality, located in the Cape Winelands District Municipality in the Western Cape. The Breede Valley Municipality provides services to an area of approximately 3 833 square km. Besides the town (urban, commercial and industrial) the land in the municipal area is predominately used for agriculture and also includes 23% mountainous topography. The main town is Worcester and other small towns are De Doorns, Touws River and Rawsonville. 2 REGIONAL BULK INFRASTRUCTURE GRANT 31 DECEMBER 2014 The GPS co-ordinates of the project are 33˚ 43’ 29.24”S/ 19˚ 20’ 51.34”E. The project is situated in the Breede water management area. 2.2 Project History The Breede Valley Municipality in March 2006 appointed Ninham Shand to investigate the Bulk Water Supply to towns of Worcester, Rawsonville, De Doorn and Touws River. The investigation was completed in April 2007. Aurecon Group (formerly Ninham Shand) was subsequently appointed to summarise and expand on the findings in regard to Worcester and Rawsonville. 2.3 Project concept, design and plan Worcester is the commercial and administrative centre for the Breede Valley Municipal area. The bulk water for the town is obtained from the Stettynskloof supply scheme which is located 30 km south west of Worcester on the Hosloot River. The capacity of the Stettynskloof scheme is 5 000 Ml/day and a lime CO2 stabilisation at the same site. A 32 km steel pipeline of 580/660/813 mm OD was provided to deliver stabilised water to the town. Due to growing demands, the Stettynskloof Dam was raised in 1981 to increase capacity to 15 000 Ml/day. During 1989/1990, approximately the first 6 km of the delivery pipeline was duplicated, a bypass was provided around the Pakkraal Hill and a booster pump station was provided on the north eastern side of the Breede River to increase the peak delivery rate from 39 to 52 Ml/day. Various other improvements were also carried out at this time, including improvements to the treatment works and installation of the telemetry system. Fairy Glen Dam is located about 8 km from the town, in the BranDWStch Mountains. It was built in 1983 and has a storage capacity of 516 Ml. Although the capacity is limited, this dam is able to supplement peak supply to Worcester to a limited extent when the Stettynskloof pipeline is unable to meet the peak demands. It also supplies water to higher lying consumers and is available as an emergency backup to the Stettynskloof system. The area of supply will be the Rawsonville and Worcester. Upgrading of the bulk water supply from Stettynskloof Dam to Worcester. 3 REGIONAL BULK INFRASTRUCTURE GRANT 31 DECEMBER 2014 The components of the project comprise: a) b) c) 2.4 Phase 1: Duplication of the bulk water supply pipeline from Stettynskloof Dam. The pipeline starts from a take-off after the Stettynskloof Dam and is approximately 5,5 km steel pipeline; Phase 2: This Contract provides for a new 250 mm diameter ductile iron gravity pipeline, approximately 6 000 m long connecting the existing Rawsonville reticulation network to a proposed 2 Ml reservoir. The contract further provides for a connection from the existing Stettynskloof pipeline to the new 2 Ml reservoir, valve chamber structures, road and bridge crossings and an access road to the reservoir, and Phase 3: Augmentation of the Stettynskloof Supply Pipeline – Booster Pump station: Additional pump set (Mechanical & Electrical Works). Start date duration of the programme The contract details are mentioned below: Contractor (Phase 1) : Augmentation of the Stettynskloof Supply Phase 1 Contract start date : 11 May 2012 Time for completion : 10 Months Contract completion date : 05 April 2013 Time extension granted : 161 working days Completion extension : 22 November 2013 The Municipality notes that due to the extension of time for the completion of the works the budget implication amounts to R1,137,017.70. Contractor (Phase 2a) : Contract start date Time for completion Contract completion date Time extension granted Revised completion date Completion date : : : : : : Rawsonville water Supply Pipeline and 2 Mℓ Reservoir 01 March 2013 8 Months 09 November 2013 Nil N/A 10 February 2014 Contractor (Phase 2b) Contract start date Time for completion Due completion date Time extension granted Completion date : : : : : : Augmentation of the Stettynskloof Supply Phase 2 02 May 2013 12 Months 2 May 2014 5 days (working days) 31 October 2014 Contractor (Phase 3) Contract start date Time for completion Due completion date Time extension granted Revised completion date Anticipated completion date : : : : : Augmentation of Booster Pump Station 8 July 2014 60 weeks 8 September 2015 None 8 September 2015 8 September 2015 : : 4 REGIONAL BULK INFRASTRUCTURE GRANT 2.5 Contractor (Phase 4) : Contract start date Time for completion Due completion date Time extension granted Revised completion date Anticipated completion date : : : : 31 DECEMBER 2014 Augmentation of Stettynskloof Water Treatment Works 21 January 2015 (to be finalised) 30 weeks 21 August 2015 9to be finalised) None 21 August 2015 21 August 2015 : : Funds previously allocated to the project The total project cost is R190,585,200 and the planned completion date of the project is at the end of 31 May 2016. Table 1 indicates the RBIG funding that was made available to the project during the past financial years. Table 1: Funding to date Approved budget amount 2010/11 2011/12 2012/13 2013/14 2014/15 Total R800,000 (Feasibility Study) R300,000 R19,034,784 R 33,385,496 R 10,078,000 R63,598,280 The project is funded as follows: Local Municipality (MIG) Regional Bulk Infrastructure Grant Other funding TOTAL PROJECT BUDGET 3 : R 27,670,000.00 : R 66,700,000.00 : R 96,488,200.00 : R190,585,200.00 PROGRESS TO DATE The people mentioned below attended the site meeting and conducted the performance evaluation on 16 January 2015: P Sihlali L Guqa J Steyn DWS Regional DWS Regional Breede Valley Municipality 5 REGIONAL BULK INFRASTRUCTURE GRANT 3.1 31 DECEMBER 2014 Milestones Name of Organization compiling/ developing Planned date for completion FS/IRS/Design/EIA Date FS/IRS/Design /EIA approved Feasibility Study Aurecon Group Completed Completed Implementation Readiness Study Aurecon Group Completed Completed Preliminary Design Aurecon Group Completed Completed KHULA Environmental Completed Completed Financial Funding Plan Aurecon Group Completed Completed Design Aurecon Group Completed Completed Product EIA WUL Operation and Maintenance Plan 3.2 Implementation of the approved business plan The Breede Valley Municipality has appointed Aurecon Consulting engineers to provide professional services and manage the implementation of the project. The Breede Valley Municipality has also appointed WK Construction, JVZ and Viking Pony Africa Pumps t/a Tricom Africa as contractors for the construction of phase 1, phase 2a and b and phase 3, respectively. The details of the contracts are contained in Annexure C. 3.3 Schedule of work and phasing of the activities The overall progress is: Phase 1: Phase 2a: Phase 2b: Phase 3: Phase 4 100% 100% 100% 35% 5% Progress on Phase 1 (Augmentation of the Stettynskloof Supply Line) This Contract provides for the Construction of a new 700 mm diameter pipeline and a new 800 mm diameter pipeline, approximately 2,5 and 3,0 km long respectively, including associated valve chambers and repairs to the existing Stettynskloof pipeline. Both sections of the pipeline will be laid parallel to existing 580 mm and 600 mm diameter pipe lines. The contract further provides for access road re-alignment and slope stabilization. Site clearance Pipe pedestals Install AG pipe Pipe installation below ground Pipe work in Chambers Construct Chambers 100% 100% 100% 100% 100% 100% 6 REGIONAL BULK INFRASTRUCTURE GRANT 31 DECEMBER 2014 Misc. Concrete Repairs to existing pipeline and structures Finishing 100% 100% 100% Completion certificate has been issued to the contractor with snag list to be finalised. Progress on Phase 2a (Rawsonville Water Supply Pipeline and 2 Ml Reservoir) This Contract provides for a new 250 mm diameter ductile iron gravity pipeline, approximately 6 000 m long connecting the existing Rawsonville reticulation network to a proposed 2 Ml reservoir. Site establishment Site clearance Pipe installation below ground Pipe work in Chambers Construct Chambers Misc. Concrete Reservoir construction Finishing 100% 100% 100% 100% 100% 100% 100% 100% Progress on Phase 2b (Augmentation of the Stettynskloof Supply Line) This Contract provides for the Construction of a new 800 mm diameter pipeline, approximately 6,2 km long, including associated valve chambers and repairs to the existing Stettynskloof pipeline. The pipeline will be laid parallel to existing 660 mm diameter pipeline. The Contract further provides for the replacement of the existing emergency line form the Holsloot River. Progress in the reporting period is as follows: Site clearance Pipe pedestals Install AG pipe Pipe installation below ground Pipe work in Chambers Construct Chambers Miscellaneous Finishing 100% 100% 100% 100% 100% 100% 100% 100% Progress on Phase 3 (Augmentation of the Stettynskloof Booster Pump Station) This Contract provides for the electrical and mechanical upgrading of the existing booster pump station. This contract was awarded on 8 July 2014. Contract period is 60 weeks. The anticipalted due completion date is 8 September 2015. Finalization of delivery of imported material may have an impact on the anticipated due completion date. Progress on Phase 4 (Augmentation of the Stettynskloof Water Treatment Works) This Contract provides for the electrical and mechanical upgrading of the existing water treatment works at Stettynskloof Dam. The work shall include the following; a) The addition of a rotary drum screen with a screw conveyor and connecting 7 REGIONAL BULK INFRASTRUCTURE GRANT b) c) d) e) f) g) h) i) j) k) l) m) 31 DECEMBER 2014 pipework Pipeline from the drum screen sump to the stabilization plant Replacement of two lime dosing systems Compressed air supply system Reverse jet filtration system New LV Motor Control Centre (MCC) Small power and lighting refurbishments, including new DB New programmable logic controller (PLC), including housing in a new PLC panel, I/O, HMI, UPS and programming of PLC. Modifications of the existing SCADA software and WTP mimics at the Municipal SCADA station. Minor building works to the water treatment building As-built drawings Operation and Maintenance Manual. Signage, testing, commissioning and training. This contract was awarded on 10 December 2014. Contract period is 30 weeks. The anticipalted due completion date is 21 August 2015. Finalization of delivery of imported material may have an impact on the anticipated due completion date. 3.4 Capacities dedicated to the programme The project is managed by the Department of Water and Sanitation, jointly through the Regional Bulk Infrastructure Programme and coordinated by the DWS Regional Office in Region. The capacities dedicated to the project are as follows: 3.5 Funder: Department of Water and Sanitation and Breede Valley Municipality Implementing agent: Breede Valley Municipality Operation & Maintenance: Breede Valley Municipality Consulting Engineer: Aurecon Contractor (current): WK Construction Contractor (current): JVZ Construction Joint Venture Viking Pony Africa Pumps t/a Tricom Africa Key challenges within the project and not management a) b) c) d) e) Importing of materials (i.e. pipes, pumps, electrical equipment, etc.): The suppliers that met the specifications for the supply of the materials were not locally available and the materials had to be ordered overseas. Stakeholder consents: Dealing with stakeholders as the pipeline passes through their properties and the haulage of the material to the site passes through their premises and storage. Some of the pipeline will be passing through the informal settlement and the councillor will have to negotiate with the informal settlement dwellers. Access to site to lay pipes: The provision of a road for the bringing in the pipes where they will be installed as the topography was mountainous where the contractor was installing the pipeline. External approval processes: The Record of Decision was obtained on time for the project but there was a change in the position of the reservoir which required amendment to the Environmental Impact Assessment to Environmental Affairs. National labour strikes during September 2013 and August / September 2014. 8 REGIONAL BULK INFRASTRUCTURE GRANT 4 PROJECT RESULTS AND BENEFICIARIES 4.1 Outcomes and outputs 31 DECEMBER 2014 Currently the expected outcomes and outputs are on track for the phases under construction. Planning phase has been completed. Phases 1, 2A and 2b are completed. Phases 3 and 4 are where the focus of activities is at this stage. 4.2 Beneficiaries and project results The bulk pipeline project is aimed at eradicating all water backlogs at the towns of Worcester and Rawsonville. When completed, the project will provide water services to over 146,050 people within the service area. The completion of the project will also ensure the delivery of sustainable basic water services, the enhancement of economic development towards achieving the national services target by 2014, the objectives of water for growth and development, employment and redistribution. The communities and households expected to benefit are captured in Annexure B. 4.3 Jobs created Phase 2 will be employing more labourers from the local community as the pipeline will be laid in a very confined space in which machinery might be difficult to manoeuvre. Table for the employment attached as Annexure E. In this reporting period October – December 2014, no new jobs were created. For the entire project period since inception 53 jobs have been created. 5 CONCLUSIONS/ LESSONS LEARNED 5.1 Main successes and failures of the project to date a) b) c) d) e) The municipality is eagerly awaiting the completion of the project as it will resolve the long standing issues on the demand for the towns. Phase 1 of the project could not maximise labour intensive as the majority of the pipeline was above the ground and huge pipes that could not be lifted by hand which resulted in maximum use of the machinery. There were good relations with some of the farm owners as some of the material that was excavated was used to fill the farmer’s quarry which turned out to be much cheaper to the municipality. The materials that were used during the construction was stockpiled in one of the farmer’s property and rented by the contractor. The Record of Decision was received on time for the amendment to the EIA submitted to DEADP. The location of the suppliers led to the late delivery of the pipes for the Phase 1 of the project. The pipes for the Phase 2 of the project were ordered on the 15 May 2013 and the contractor anticipates delivery after 2 months as they are ordered overseas. In the meantime the contractor has commenced with the construction of the reservoir whilst waiting for the delivery of the pipes. 9 REGIONAL BULK INFRASTRUCTURE GRANT 5.2 31 DECEMBER 2014 Ownership and sustainability of infrastructure works The Breede Valley Local Municipality is the Implementing Agent and is the owner of the infrastructure. The municipality is currently operating the existing Bulk Water Supply and will continue to so with the upgraded pipeline and reservoir. Breede Valley Municipality has a good record in maintaining the existing treatment works and DWS is satisfied that they will be able to maintain the upgraded Bulk Water Supply. Breede River Valley will budget for O&M appropriately. No new risks have been identified. 6 RECOMMENDATIONS It is recommended that: The project continues to be implemented as it will ensure water security to the municipality. 10 REGIONAL BULK INFRASTRUCTURE GRANT ANNEXURE A: PROJECT IMPLEMENTATION PHOTOS 31 DECEMBER 2014 11 REGIONAL BULK INFRASTRUCTURE GRANT 31 DECEMBER 2014 ANNEXURE B: LIST OF VILLAGES EXPECTED TO BENEFIT The bulk pipeline project is aimed at eradicating water backlogs of at the towns of Worcester and Rawsonville. When completed, the project will provide water services to over 146,050 people within the service area. Area Community/ Village Breede Valley Municipality Worcester (Wards 6 to 18 and 21) Breede Valley Municipality Rawsonville (Wards 19, 20) No. of households (social component) 41 486 (17 424) 959 (402) 12 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 ANNEXURE C: DETAILS OF CONTRACT CONTRACT AWARD / START DATE PLANNED COMPLETION DATE ACTUAL COMPLETION DATE EXPENDITURE AS AT DECEMBER 2014 % COMPLETION CONTRACT NO. AND NAME CONTRACTOR CONTRACT VALUE (incl. VAT) BV 187 Augmentation of the Stettynskloof Supply Pipeline WK Construction (Pty) Ltd R 35,220,000 11 May 2012 28 July 2013 22 November 2013 R42,357,164 100% BV 232 Rawsonville Water Supply Pipeline and 2Ml Reservoir (Phase 2A) JVZ Construction R 17 600 829 01 March 2013 Nov 2013 10 February 2014 R19,063,028 100% BV 250 Augmentation of the Stettynskloof Supply Pipeline (Phase 2B) JVZ Construction R44 698 551 02 May 2013 30 October 2014 N/A R 41,634,556 100% BV 322 Augmentation of Stettynskloof Booster Pump Station Viking Pony Africa Pumps t/a Tricom Africa R 8 673 378 8 July 2014 8 September 2015 N/A R 2,209,739 35% BV 363 Augmentation of Stettynskloof Supply Pipeline- Water Treatment Works Upgrade M.A.N. Engineering Services R 11,296,964 21 January 2015 21 August 2015 N/A R0 0% NOTE: Retention monies withheld have been included as expenditure. All figures include 14% VAT. 13 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 ANNEXURE D: PROJECT SCHEDULE 14 REGIONAL BULK INFRASTRUCTURE GRANT SEPTEMBER 2014 ANNEXURE E: DETAILS OF JOB OPPORTUNITIES Stettynskloof Phase 2 Summary of Decent Job Opportunities Decent job opportunities for people employed at various occupational levels: Decent = Full time for at least 5 months or more Decent job opportunities for the financial year 2014/15 Adult Men Perso Actual cost n on job Days opportuniti es No Adult Women Person Actual Days cost on job opportun ities No Youth Men Perso Actual n cost on Days job opportun ities No No Youth Women Perso Actual n cost on job Days opportuniti es Disabled Pers Actual on cost on Day job s opportun ities No TOTAL Perso Actual n cost on Days job opportunit ies No Clerical Ongoing 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 Clerical New 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 22 1802 R 267 445 0 0 R0 0 0 R0 0 0 R0 0 0 R0 22 1802 R 267 445 Labourers New 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 Managerial Ongoing 0 0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 Managerial New 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 Semi-Skilled Ongoing 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 Semi-Skilled New 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 Skilled Ongoing 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 Skilled New 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 Supervisor Ongoing 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 Supervisor New 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 Other Ongoing 0 0 R0 0 0 R0 1 70 R0 0 0 R0 0 0 R0 0 0 R0 Other New 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 0 0 R0 22 1802 R 267 445 0 0 R0 0 0 R0 0 0 R0 0 0 R0 22 1802 R 267 445 0 0 0 0 0 0 0 0 0 0 R0 0 0 R0 0 0 R0 Labourers Ongoing TOTAL Ongoing TOTAL New