Takaki

advertisement
Physics of Fukushima Damaged Reactors and its Preliminary Lessons
Naoyuki Takaki
Department of Nuclear Engineering, Tokai University
1. The trigger of Fukushima accident
The Pacific coast area of eastern Japan was struck by the Tohoku district - off the Pacific Ocean
earthquake at 14:46 on March 11, 2011. The magnitude of this earthquake was 9.0. It was the largest one
in Japan’s recorded history. This earthquake occurred offshore Miyagi prefecture at a depth of 23.7km
where the Pacific plate sinks beneath the North American plate. The size of the source area is 400km
north to south x 200km east to west and the seismic intensity is registered more than 6 on the Japanese
seismic scale over a wide area (Fig.1).
Epicenter
Fukushima nuclear
power stations
Seismic Intensity
Fig.1
7
4
6+
3
62
5+
1
5-
Location of epicenter and seismic intensity
Afterwards, tsunamis struck the Pacific coast in a series of seven waves, resulting in the inundation of
an area as large as 561km2 and approximately 25,000 people are reported dead or missing.
Two nuclear power stations of Tokyo Electric Power Co. (TEPCO) located in this coast area as
lustrated in Fig.2 were also struck by the huge tumani waves. At the Fukushima Dai-ichi sites, south one
of them, the coming of tsunami with the height of 14 to 15m consequently caused a great deal of damages
for three units under operation and for 1 unit which had been shut down for planned maintenance, with
the nuclear fuel having been transferred to the spent fuel pool.
1
Fig.2
Nuclear power stations along Pacific coast area of eastern Japan
2. Accident progression
2.1
Station blackout after normal shutdown
Table 1 summarizes 3-mode acceleration observed at each plant. Reactor No.2 (built on solid
bedrock) suffered the largest horizontal ground acceleration of 550 gals, which is 26 percent
stronger than the reactor's design limit, however, three units from 1 to 3 at the Fukushima Dai-ichi
sites which were under operation automatically shut down at 14:46 on March 11.
Table 1
How large is the ground motion at the Fukushima Dai-ichi plants ?
2
All six external power supply sources were lost because of intense ground motion. This caused
the emergency diesel power generators to start up, as expected response according to its design.
However, seawater pumps, emergency diesel generators and distribution boards were submerged
by the tsunami strike, and all emergency diesel power generators stopped except for one generator in
Unit 6 that is an air-cooled type. Thus all AC power supplies were lost except at Unit 6.
Since the seawater pumps were submerged, residual heat removal systems to release the residual
heat inside the reactor to the seawater and the auxiliary cooling systems to release the heat of various
equipments to the seawater lost their functions (Fig.3).
Fig.3
2.2
Major root cause of the accident
Emergency cooling of the core
Therefore core cooling functions not utilizing AC power were put into operation, or, alternately,
attempts were made to put them into operation. These were operation of the emergency isolation
condenser (IC) in Unit 1, the operation of the reactor core isolation cooling system (RCIC) in Unit 2
and the operation of the RCIC and the high pressure injection system (HPCI) in Unit 3.
Here the IC in Unit 1 has a function to cool down the water vapor in the reactor pressure vessel
(RPV) during isolation event. The water vapor send to heat exchanger is condensed into water then
returned into RPV (Fig.4). Two ICs can remove heat load of 6% of rated power that is almost
enough for decay heat removal. The IC pool capacity is designed for 10 hours operation without AC
power to makeup water vapor into IC tank. The IC of Unit 1 automatically started up at 14:52 on
March 11 and started cooling the reactor, however, it was manually stopped functioning at 15:03 on
the same day (before tsunami hit) to keep the cooling speed less than 55 degrees Celsius/hour by
following operation manual.
3
•IC Tank capacity is
for 10 hours
•Operation of valves
requires DC power
Fig.4
Isolation condenser (IC)
The RCIC in Unit 2 and 3 is a system that cools the reactor cores when reactors are isolated from
feed water and condenser systems. The water vapor in the RPV sent to RCIC turbine drives pump
that injects water either from the condensate storage tank or the pressure suppression pool into RPV
(Fig.5). Condensed reactor steam (drained water from RCIC turbine) is discharged to suppression
pool. All valves and governor in the turbine pump can be operated by DC power and this RCIC can
be operable only for 8 hours. As for Unit 2 and 3, TEPCO manually started up this RCIC just after
the earthquake. But the RCIC automatically stopped very soon because of the high water level in the
reactors. The RCIC did not work continuously, however they tried to restart RCIC several times
after the first trial and finally DC power was lost.
•Requires DC power
for operation of
valves and governor.
Fig.5
Reactor core isolation cooling system (RCIC)
The HPCI is one of the emergency core cooling system that injects water, with the pump driven
by providing the water vapor generated by the decay heat to the turbine. The HPCI in Unit 3
4
automatically started due to the reactor low water level at 12:35 on March 12 and the HPCI stopped
at 2:42 on March 13. The reason for this appears to have been a drop in pressure in the reactor.
Another probable cause could be water vapor outflow from the HPCI system. HPCI was not
activated for Unit 1 and 2 and the reason is not clear at this moment.
These core cooling systems that do not utilize AC power supplies stopped functioning thereafter,
and were switched to alternative injections of freshwater or sea water by fire extinguishing lines,
using fire engine pumps.
2.3
Hydrogen generation
Concerning Units 1 to 3 of the Fukushima Dai-ichi NPS, as the situation where water injection to
each RPV was impossible to continue for a certain period of time, the nuclear fuel in each reactor
core was not covered by water but was exposed, leading to hydrogen generation. Once the rods
reach more than 1200 degrees Celsius, the zirconium of the fuel cladding tubes will interact with the
water vapor and split the hydrogen from the water by the following chemical reaction.
Zr + 2 H2O → ZrO2 + 2 H2
In addition, the fuel cladding tubes were damaged and radioactive materials therein were
discharged into the RPV which keeps radioactive materials inside the reactor. Further, these
hydrogen and radioactive materials were discharged into the primary containment vessel (PCV)
during the depressurization process of the RPV. If the hydrogen released from the reactor core and
containment vessel accumulates in sufficient concentrations of 4% or more with 5% of oxygen gas
in the air, it can explode.
With damaging cladding tube, the core melt was made progress. Part of the melted fuel stayed at
the bottom of the RPV. This will be discussed later in more details.
2.4
Venting to save containment vessel
Injected water vaporizes after absorbing heat from the nuclear fuel in the RPV. Accordingly, the
inner pressure rose in the RPVs which had lost their core cooling functions, and this water vapor
leaked through the safety valves into the PCV. Due to this, the inner pressure within the PCVs in
Units 1 to 3 rose gradually.
TEPCO built new vent pipes extending from the suppression pool and dry well (D/W) to the
stacks from 1999 to 2001 as PCV vent facilities during severe accidents as shown in Fig.6. These
facilities were installed to bypass the standby gas treatment system (hereinafter referred to as SGTS)
so that they can vent the PCV when the pressure is high. The facilities are also provided with a
rupture disk in order to prevent malfunction.
5
Fig.6
Venting Facility
The PCV vent from the suppression pool is referred to as “wet vent” and vent from dry well is
referred to as “dry vent”. By conducting these vent operation, the gases including radioactive
isotopes and hydrogen in the PCVs are released into the atmosphere through the ventilation stack.
The former wet vent is cleaner and given higher priority. The procedures for operation in severe
accidents specify that the chief of emergency response headquarters shall determine whether PCV
vent operation should be conducted after core damage.
The wet vent shall be conducted when the PCV pressure reaches the maximum operating pressure
before core damage or when the pressure is expected to reach about twice as high as the maximum
operating pressure after core damage, if residual heat removal system (RHR) is not expected to be
recovered. The wet vent shall be conducted if the vent line of the suppression pool is submerged.
Because of the total loss of the AC power supply, motor driven valves had to be opened manually
for the PCV venting operations. For operation of pneumatically-actuated valves, the pressurized air
required for operating such valves could not be assured, and thus a temporary air compressor had to
be mounted to assure the pressurized air. For such reasons, the facilities could not be operated in
accordance with the documented operation procedures for severe accidents, which caused the PCV
venting operation to be delayed.
Reducing pressure was necessary to protect the PCV therefore vent operations of PCV wet well
was carried out a number of times. Consequently such operations were too late to prevent hydrogen
explosion then huge amount of radioactive materials were released into environment.
6
2.5
Hydrogen explosion
After the wet well venting of the PCVs, explosions caused by hydrogen which had presumably
leaked from the PCV occurred in the upper area of the reactor buildings, ruining the operation floor
in the reactor buildings of Units 1 and 3. As a result of these incidents, a lot of radioactive materials
were discharged to the atmosphere.
The hydrogen gas produced in Unit 1 is estimated to be about 270kg and the concentration of 15%.
In the Unit 3, the amount and the concentration of hydrogen seems to be almost double then caused
harder explosion (detonation) than that occurred at Unit 1 as shown in Fig.7.
Unit 1
Fig.7
Unit 3
Hydrogen explosion at Unit 1 (at 15:36 JST on 12 March)
and Unit 3 (at 11:15 JST on 14 March)
Following the ruination of the Unit 3 building, an explosion probably caused by hydrogen
occurred in the reactor building of Unit 4, ruining its upper area. In Unit 4, all core fuels had been
transferred to the spent fuel pool for planned maintenance before the earthquake. Thus damaged
fuels stored in the spent fuel pool at Unit 4 were suspected as a source of hydrogen generation.
Unit 4
Common
Stack
From Unit 3
Fig.8
Plausible hydrogen path from Unit 3 to Unit 4
7
The spent fuel pool has about 2 MW heat load that is relatively high because of existence of new
fuels but water level is maintained by filling up water from outside. Pool water sample were taken
and it has been confirmed that there should be no severe fuel damage. Accordingly, it is considered
that hydrogen gas caused explosion at Unit 4 might come from vent line merged with adjacent unit
(unit 3).
As for Unit 2, it seems that a hydrogen explosion occurred and caused damage at a point
presumed to be near the suppression pool.
2.6
Core meltdown
The core conditions of Unit 1, 2 and 3 were analyzed by using current limited information with
necessary assumption such as diameter of leak hole of PCV to determine a leak rate of water vapor,
working condition of cooling system without AC power supply, etc.
The results shows that the reactor core of Unit 1 has been significantly damaged after the IC
stopped, then the fuels were relocated below or slumped to the lower plenum from the fixed position
of the loading, however, most of it is being stably cooled down around there (Fig.9 and Fig.10).
Fig.9
Water level of Unit 1 reactor core
As for the core of Unit 2, if we assume that the water level could be maintained above the active
fuel zone by sufficient water supply with fire pump, there partially exists a molten core pool, but a
large part of fuels remains in original range and does not lead to breach of RPV. The reason is that
the water injection by RCIC at the early stage was implemented continuously and the period of
RCIC suspension was shorter than in the case of Unit 1. Assuming lower water level and larger parts
of exposed fuel due to smaller water injection, the damage of the core of Unit 2 could be more
serious and breach of RPV is unavoidable.
8
4.7 hours after SCRAM
14.3 hours after SCRAM
5.3 hours after SCRAM
Fig.10
15 hours after SCRAM
Progression of core melt of Unit 1
The core of Unit 3, there partially exists a molten core pool, but a large part of fuels remains in
original range and does not lead to breach of RPV because water injection by RCIC and HPCI at the
early stage was implemented continuously and time period of HPCI suspension is shorter than in
Unit 1. Assuming lower water level, the damage of the core of Unit 3 could be more serious and
breach of RPV is unavoidable.
These analyses were performed based on data containing many uncertainties and should be
confirmed by detailed investigation after cold shutdown in near future.
2.7 Cooling of spent fuel pool
The most urgent task just after the accident at the site, along with recovery of the power supply
and the continuation of water injection to reactor vessels, was water injection to the spent fuel pools.
In the spent fuel pool in each unit, the water level continued to drop on account of the evaporation of
water caused by the heat of the spent fuel in the absence of the pool water cooling system, due to the
loss of power supply. Water injection to the spent fuel pool was carried out by the Self-Defense
Forces, the Fire and Disaster Management Agency and the National Police Agency, using
helicopters and water cannon trucks. Concrete pump trucks were ultimately secured, which led to
stable water injection using freshwater from nearby reservoirs after the initial seawater injection.
3. Particularities, lessons and challenges
3.1 Particularities and seriousness of Fukushima accident
The clear and essential difference between Fukushima and the past nuclear disasters happened at
Chernobyl and TMI is the cause of accident. There is no doubt that the first trigger of Fukushima is
9
a tremendous natural disaster nothing like that Japan has ever experienced in the recorded history.
Furthermore the decisive factor is not earthquake itself but tsunami that struck the site about 40
minutes later and destroyed necessary equipments and power supply to cool the reactors and spent
fuel pools.
Namely this Fukushima accident has the following particularities. It was triggered by a natural
disaster; it led to a severe accident accompanied by hydrogen explosion, damages to fuels in cores
and spent fuel pools, core melts, damages to RPV and PCV in multiple units, resulting in release of
radioactive materials into atmosphere (770 PBq) and the ocean (5 PBq).
The rating of INES (International Nuclear and Radiological Event Scale) officially announced on
March 11th by NISA (the Nuclear and Industrial Safety Agency) of Japan was only level 3. But it
was successively revised to level 4 on March 12th, to level 5 on March 18th and finally to level 7 on
April 12th by reflecting amount of released radioactivity and seriousness of accidents relating
multiple facilities.
To stabilize damaged reactors, bringing the temperature at the base of each reactor vessel to
below 100 degree centigrade is a key. The conditions for achieving “cold shutdown” is temporary
extended by including leakage termination of radioactive substances from the plant to environment
in addition to the original definition in terms of the reactor temperature. TEPCO had planned the
milestone of shutdown is no later than January 2012 but it will be slightly moved up owing to
improved smooth operation of radioactive water processing facilities.
It will take decades to complete the decommissioning plants after removal of melted fuels.
• Cooling
– Operate the closed circulation system of cores and SF pools
to remove the decay heat and cleanup the coolant.
• Minimizing residual risks
– Nitrogen gas injection
– Support SF pool from the bottom of (Unit 4)
– Reliability of power supply
– Reactor building cover
• Cold shutdown
• Remove fuels
• Decontamination
• Decomissioning
• Waste disposal
Fig. 11
Several
months
By January 2012
Several
decades
On-going, near-term and future actions
3.2 Lessons learned
However it is only natural the power of natural disaster is far beyond human understanding,
TEPCO and the Japanese government are solemnly responsible to ensure the safety of nuclear power
10
palns and to avoid any risk impending to the public.
The Fukushima accident revealed some weakness and imperfectness in technological design of
nuclear plant and the authorization process. All electric power companies that own nuclear plants
had already taken prompt actions to enhance resistance to tsunami disaster by deploying
power-supply vehicles, cables, spare pumps etc. according to directions by a minister of METI.
These are just temporary actions and more complete measures should be adopted based on lessons
learned from this accident. The nuclear emergency response headquarters organized by Japanese
government presented 28 lessons which are classified into 5 categories in a report submitted to the
IAEA ministerial conference on June 2011.
The categories include 1) sufficiency of preventive measures against a severe accident, 2)
adequacy of the responses to this severe accident, 3) adequacy of the emergency responses to the
nuclear disaster in this accident, 4) robustness of the safety infrastructure established at nuclear
power stations and 5) thoroughness in safety culture while summing up all the lessons. Table 2 lists
the identified lessons.
Table 2
Lessons learned from Fukushima accident
(identified by the nuclear emergency response headquarters)
11
3.3 Challenges in front
About three-fourth of Japan’s 54 reactors have been shut down by the middle of September 2011
because of planned maintenance, leading to power shortages that could compel nation to save power
and result in hurting Japan’s economy. Assuming no reactor can be restarted, Japan may have no
nuclear reactors running by May 2012.
To prevent this situation, the government decided to conduct stress test consisting of two steps.
The first step targets reactors which have already completed planned maintenance and are ready for
restart. This will assess resistance to severe earthquakes and other events more extreme than those
for which they were designed. If reactors pass the first stage of the two-step, they would be able to
restart, while all units would be subjected to more comprehensive tests in a second stage.
Under Japan's previous energy plan, prior to the Fukushima disaster, nuclear power had been set
to meet more than half of electricity demand by 2030, up from current share of about one-third.
Needless to say, obtaining public acceptance is key to restart nuclear reactors but public opinion is
generally united in reducing nuclear plants, instead of increasing them. Just after the earthquake,
social response seemed to be relatively comprehensive or patient to the nuclear accident, then
recently, public increases distrust to nuclear industry, utility company and government while
enduring their unrest life brought by the accident.
Fig.12
Social response to nuclear industry after Fukushima accident
As of August 2011, tens of thousands of residents left the Fukushima prefecture as they feared the
health effects of radiation. Most of them intend to avoid their children being exposed to radiation
even if the additional radiation dose is generally comparable to the background dose.
Although this may be an extreme instance, major part of public equally has more negative
impression to nuclear energy than before. Some of them affirm that they are ready to tolerate
12
decelerated economy and worse quality of life with higher energy cost so as to abandon national
nuclear energy policy.
Generally speaking, top two grounds why public oppose to nuclear energy have been “safety”
and ”radioactive waste” regardless of countries. Long lasting radioactivity of nuclear waste as
illustrated in Fig.13 is hardly acceptable to public because they consider that it may harm their
descendant and imposing problems arising from current generation to future innocent generation is
not ethically allowed.
The Fukushima accident realistically gives fears of radioactivity, so that Japanese public enhanced
their concerns more about potential risk and existence of radioactive material being close area to
their life. They noticed that nuclear reactor in operation (and attached spent fuel pool) contains huge
amount of radioactivity that is continuously generated therein (Fig.13) and citizens have been forced
to live in the vicinity of it. They also learned that the multi-barrier to confine radioactivity in the
system can be broken.
Fig.13
Radioactivity existed above the ground and buried long term radioactivity
“Risk-free world” never exists. Any kinds of modern life involve many kinds of risk to a certain
extent ascribed from technologies. Principally, choice of energy source must be made by the balance
between risk and benefit. The energy policy should be politically judged based on both scientific
data and social factors. Before restarting current nuclear plants and to develop future nuclear system,
these concepts must be reexamined.
4. Concluding remarks
13
The Fukushima accident has still been imposing various types of difficulties on daily life of citizens,
foods, energy supply, industries, economy etc. of Japan and it simultaneously posing messages to nuclear
engineers as partly shown in the last chapter.
Through examining the accident with limited determinations of the cause and the current status of the
plant, it can be said that the following points should be reviewed and reflected to the design of future
nuclear reactors;
 proper definition of design based event (DBE) to limit the probability of large scale release of
radioactive materials by revising the external event to be considered (less probable but high risk
events such as huge tsunami, volcanic eruptions, intentional attack by terrorism etc.),
 more independent and redundant safety system to ensure power supply and cooling functions (ex.
distributed arrangement of diesel generators and electrical distribution boards, preparation of
various heat sink, coolant injection system driven by gravity etc.),
 optimized combination of passive safety system with active system that are functional for
removing the decay heat even in case of station blackout to secure extended time period enough
for necessary accident management.
In general, failure is a stepping stone to success, it is however said that it may not be the case for
nuclear technology due to the seriousness, hugeness and irreparability of its impact. The Fukushima
accident certainly imposed immeasurable hardship and damages on people especially living in east coast
of Japan. It is urgently needed to implement radical review for national nuclear energy policy, validity of
authorization procedure and related laws and the nature of utilities.
If an opportunity to revive was given to nuclear utilization, nuclear plants would become more robust
energy source with strengthened safety for natural disaster and other external event. The emerged nuclear
power will contribute to power the sustainable world for centuries without emission of greenhouse gas.
To realize this, opened and fair discussions on the various energy sources and their realistic deployment
strategy should be made again and again.
Reference:
 Report of the Japanese Government to the IAEA Ministerial Conference on Nuclear Safety - The
Accident at TEPCO’s Fukushima Nuclear Power Stations -, Nuclear Emergency Response
Headquarters, Government of Japan June 2011
 Akira Omoto, Fukushima Accident : An overview, Presentation at prenaly session of ICAPP2011, Nice
14
Download