Project Plan

advertisement
Spring 2009
Cocktail Stuffers – Project
[Type text]
Cocktail Stuffers - Project Plan
Recipe Database Information System
In an attempt to estimate the size and the amount of effort and time to work on this project,
Richard Meyer, Mark Hammond, and Andrei Zhuchenko have used several steps to help
determine the completion of each phase of this project.
Project Size Estimation
To develop this project, the RAD (Rapid Application Development) phased development
methodology was chosen and the completion date should occur before the new fiscal year. The
function point approach was used to determine the number of lines of code that can be
converted to find the effort required to develop the system, which that information would be
converted to find the estimated schedule time.

Estimating project size:
System Components: Estimate the Total Unadjusted Function Points (TUFP)
Complexity
Description
Total
Number
Low
Medium
High
Total
Inputs
5
1x3
3x4
1x6
18
Outputs
7
2x4
4x5
1x7
35
Queries
11
4x3
5x4
2x6
44
Files
10
3x7`
6x10
1x15
96
Program Interfaces
2
0x5
1x7
1x10
17
Total Unadjusted Function Points (TUFP):
210
Overall System: Estimate the Total Processing Complexity (PC)
Data Communication
2
Heavy use configuration
0
Page 1
Spring 2009
Cocktail Stuffers – Project
Transaction rate
1
End-user efficiency
3
Complex processing
1
Installation ease
0
Multiple sites
0
Performance
0
Distributed functions
0
Online data entry
2
Online update
0
Reusability
0
Operational ease
2
Extensibility
0
Total Processing Complexity (PC):
11
[Type text]
(0=no effect on processing complexity; 3=great effect on processing complexity)
Adjusted Project Complexity (APC): .90 + (0.01 x 11) = 1 .01 Total adjusted Function Points
(TAFP) = .1.01 (APC) x 210 (TAFP): 212.1
The development of this system will use the following:
60% Java, 30%XML, 8% SQL, 1% JavaScript, and 1% HTML
Total Lines of code:
[(.60x 212.1 x55) + (.30 x 212.1 x 15) + (.08 x 212.1 x 15) + (.01 x 212.1 x 15) +
(.01 x 212.1 x 15)] = 8240.1

Estimating the effort:
Page 2
Spring 2009
Cocktail Stuffers – Project
[Type text]
The next step is to covert the lines of code using the COCOMO model which will determine the
estimation of effort to complete this project in person-months.
Effort (in person-month) = 1.4 X (8240.1/1000) = 11.536 person-months

Estimating the time required:
The total time that may be required to complete this project is determined by:
Schedule time (months) = 3.0 x 11.5361/3 = 6.78 months

Estimating the number of staff:
For this project, the number of staff members are determined by:
Number of staff = 11.536 / 6.78 = 1.70 ~ 2 staff members.
Work Breakdown Structure
Task
Number
Duration
(In Days)
Task Name
Dependency
Status
1
Project Initiation
2
2
Identify Problems
1
1
Complete
3
System Request
2
2
Complete
4
Feasibility Analysis
3
4.1
Technical Feasibility
1
3
Complete
4.2
Economic Feasibility
1
4.1
Complete
4.3
Organizational Feasibility
1
4.2
Complete
Project Plan
6
5
Page 3
Complete
Spring 2009
Cocktail Stuffers – Project
[Type text]
5.1
Size Estimation
1
4
5.2
Work Breakdown Structure
1
5.1
5.3
Work Plan
1
5.2
5.4
Staffing Plan
1
5.3
Complete
5.5
Standards List
1
6.4
Complete
5.6
Risk Assessment
1
6.5
Complete
6
Requirement Gathering
5
5
7
Data Flow Diagram
1
6
8
Data Dictionary
5
7
9
Database Design (E-R Diagram)
1
7
10
Document/Design Input Screens
2
9
11
Document/Design Output Report
2
9
12
Document/Design Menu System
3
9
13
Program Design
5
14
Program Test Design
5
15
System Architecture
15
16
Database Development
15
15
17
Program Codes
60
16
18
User Interface
30
17
19
Program Testing Results
30
18
Work Plan
Insert Work Plan Diagram Here
Page 4
13
Complete
Spring 2009
Cocktail Stuffers – Project
Staffing Plan
Mohammad Rob, Project Manager
[Type text]
Creates the work plan, staffs the project, and
applies techniques to control and direct the
project through the SDLC.
Richard Meyer, System Analyst
Analyzes and design the infrastructure and
business process model while focusing on
interfaces for the system and to ensure proper
performance.
, Business Analyst
Analyzes the business process and documents
the data flows
, Programmer
Codes System
Richard Meyer, Implementation
Install, maintain, and perform postimplementation audits.
Standards
To better organize the activities of this project, certain standards were created to promote
efficiency and accountability among the project members and to avoid ambiguous
documentation.
Coding Standards

All modules should include headers that identifies the
programmer, last update information, and description of
the code

W3C web standards compliance

Use Coding standards

Use SQL standards

Ensure cross platform compatibility (Windows, Mac,
Unix) with different web browsers (Internet Explorer,
Firefox/Nestsape, Safari, etc..)
Page 5
Spring 2009
Cocktail Stuffers – Project
Documentation Standards

All margins should be set to 1 inch.

All deliverables should be added to the project binder
and recorded in its table of contents, keeping the
chronology in order.

Project name and date should appear as a header on all
documentation.

Record task progress in the work plan every Friday,
10am.

Mandatory meeting attendance for every Monday
morning, 10am. E-mail notifications will be sent for
canceled meetings.

Any changes to the requirements must be submitted as a
written format request and to be approved by the
project manager.

Name of program to be created

Description of the program’s purpose

Identify special calculations

Apply business rules that should be incorporated into
the Pseudo-code

Include due date
Procedural Standards
Specifications Requirement
Standards
Page 6
[Type text]
Spring 2009
Cocktail Stuffers – Project
[Type text]
User Interface Design
Standards

Labels will appear in boldface text, left justified.

Company Logo/Name must appear on top left of entry
screen

The tab order of the screen will move from top left to
bottom right.
Risk Assessment
Potential risks that could be associated with this project are:

Poor design---Medium Risk
o
Implemented system does not work on current infrastructure


Scope creep—Medium Risk
o
Will delay entire process and will offset the project


Solution: Analysis and requirements gathering should be thorough.
Solution: Avoid changes if possible. Include the modifications to system
after the completion of the project.
Inadequate personnel—Low Risk
o
May extend time to complete project

Solution: Include additional personnel

Solution: Provide training
Page 7
Spring 2009

Cocktail Stuffers – Project
[Type text]
Over estimating the project plans—Low Risk
o
Will require additional resources (size, effort, time) if the project cannot
complete as schedule

Solution: Use standard estimation for this specific industry
Page 8
Download