Final BENEFIT-COST AND REGULATORY ANALYSIS CDOT Utility Accommodation Code Rulemaking Minimum Vertical Clearance Over Roadways August 17, 2009 The Colorado Department of Transportation (CDOT) Safety and Traffic Engineering Branch staff has prepared this cost benefit and regulatory analysis to provide additional information to the Transportation Commission (Commission), parties, and public, in accordance with requirements of the Administrative Procedure Act (APA). As contemplated by the APA, this analysis addresses the proposed rules regarding minimum utility clearance requirements over state highways only, and provides information on its purpose, its anticipated benefits and costs, the persons affected, and certain alternatives. Because of the importance of, and interest in this rulemaking, CDOT staff prepared this analysis. CDOT staff requested cost information from all twenty-three (23) Rural Electric Associations (REAs) operating in Colorado through the CREA (Colorado Rural Electric Association), as all other electric utilities already have standard minimum vertical clearance requirements which exceed CDOT’s proposed ones. That cost information was to include all projects completed in the last five years and costs associated with projects planned in the next five years. Since not all the needed information was provided, CDOT staff proceeded with the analysis using the best available information and judgment at this time. In accordance with the APA, the staff will make this report available to the public five days before the rulemaking hearing commences. Statutory Requirements The APA serves as the legal authority for this rule-making process, setting forth requirements for both benefit-cost and regulatory analyses. Under the APA, the Department of Regulatory Agencies (DORA) may direct an agency engaged in a rulemaking to conduct a benefit-cost analysis. Any such request must occur at least twenty days prior to the hearing on the rules, and the benefit-cost analysis must be submitted to DORA and made available to the public at least five days prior to the hearing. The benefit-cost analysis must include a good faith description of the reason for the rule, the anticipated economic benefits and costs, any adverse effects on certain economic sectors and factors, and the costs and benefits of at least two alternatives. Also under the APA, any person may request an agency engaged in a rule-making to prepare a benefit-cost/regulatory analysis. Any such request must occur at least fifteen days prior to the hearing on the rules, and the benefit-cost/regulatory analysis must be made available to the public at least five days prior to the hearing. The regulatory analysis must include a good faith discussion of the classes of persons who will be affected, the probable quantitative and qualitative impacts on such classes, the Page 1 of 6 Final probable costs to the agency for implementation and enforcement, a comparison of the probable costs and benefits of the proposed rule to those of inaction, whether there are less costly or intrusive alternatives, and any alternatives. The analysis must also include quantification of the data to the extent practicable and take account of both short-term and long-term consequences. Preparation of Analysis Recognizing the importance of and public interest in this rule-making, CDOT staff began preparing both a cost benefit and a regulatory analysis of the proposed rules shortly after the initial April 2009 rulemaking hearing was recessed. In an effort to consolidate possibly redundant information, the staff has combined both analyses into a common format that addresses: the purpose of the proposed rule; the resulting benefits and costs and the parties receiving or bearing those benefits and costs; any adverse effects on certain economic or geographic sectors; and a comparison of the costs and benefits for alternatives considered and an explanation why those alternatives were rejected. At the outset of this process, CDOT staff sought cost and benefit information from the regulated community and other stakeholders. The staff also corresponded with CREA via telephone and e-mail on numerous occasions to develop acceptable rules and ascertain needed information from their members regarding these minimum vertical clearance requirements. Ultimately CDOT staff relied upon internal expertise regarding potential benefits associated with the rules, and regarding the benefit-cost analysis. CDOT staff also consulted with staff at DORA regarding the APA benefit-cost requirements as well as the scope and content of similar analyses prepared by other state agencies. Cost Benefit Analysis Requirements: A benefit-cost analysis shall include the following: (I) The reason for the rule or amendment; To improve worker safety by establishing higher minimum clearances for transverse aerial utility crossings of State Highways. On average, CDOT issued 51 permits for overhead Rural Electric Association (REA) utility line highway crossings in each of the last five years. Since two CDOT employees died as a direct result of electrocution after coming into contact with overhead electrical utility lines in the past twenty-six years with one such fatality in the last two years; CDOT is requesting that the vertical clearance for transverse utility line crossings over CDOT roadways be increased from the current minimum of 20.5 feet to 24.0 feet to improve worker safety. Page 2 of 6 Final The L150 Volvo, a five cubic yard front-end loader, and various models of twelve cubic yard dump trucks are the most common pieces of equipment currently used within CDOT right-of-way during normal maintenance operations. During a normal loading operation, the L150 Volvo loader bucket can reach heights of up to 23 feet 9 inches, and during normal dumping operations, the dump trucks can reach heights of 22 feet 6 inches. Therefore, minimum vertical utility line roadway clearances have been recommended to be raised to 24 feet to eliminate direct contact with electric utility lines. There has been no change from the current vertical clearance minimum of 20 feet for longitudinal installations since they are required to be as close to the edge of the right-of-way as possible. Section 9-2.5-102(1), Colorado Revised Statutes (CRS), requires all electric utility lines with less than ten feet of overhead vertical clearance between operated equipment and those lines to be effectively shielded. A tractor with lowboy trailer simply hauling the L150 loader to, from or on the jobsite require effective shielding of every overhead electric utility line whose overhead vertical clearance is less than 24 feet. (II) The anticipated economic benefits of the rule or amendment, which shall include economic growth, the creation of new jobs, and increased economic competitiveness; While it is impossible to quantify the value of a human life, the insurance industry experts estimate the value to exceed $1.2 million in 2009 dollars. One CDOT worker died in the last five years as a result of maintenance activities when a maintenance vehicle contacted an overhead power line. The 51 annual highway crossings that have occurred in each of the last five years would cost an estimated average cost of $800 per crossing. That would increase costs for each of the 23 REAs by less than $1,775 per year in 2009 dollars. If one life is saved every thirteen years, the net overall benefit will result in an average savings of $2.26 for each dollar spent in 2009 dollars. This equates to a benefit-cost ratio of 2.26:1. (III) The anticipated costs of the rule or amendment, which shall include the direct costs to the government to administer the rule or amendment and the direct and indirect costs to business and other entities required to comply with the rule or amendment; Increasing the current minimum vertical clearance standard of 20 feet 6 inches over roadways to 24 feet will require longer utility poles. This rule will increase the cost of each typical new overhead utility line roadway crossing by less than $800.00 (in 2009 dollars). This will increase annual operating costs for each REA by $1,775 in 2009 dollars. All other electric utilities operating within the State have minimum vertical clearance requirements that exceed the proposed minimums included in this rule. Page 3 of 6 Final No other electric utility has communicated any concern over increased costs. Over the last five years, on average 51 transverse overhead utility line crossings of CDOT roadways have been constructed at an average annual cost to each REA of $1,775. It is not anticipated that CDOT costs will change because the State Highway Utility Accommodation Code has been used as a guide for more than three years and formalizing it into a rule does not create any additional program costs. (IV) Any adverse effects on the economy, consumers, private markets, small businesses, job creation, and economic competitiveness; and Whereas this change only affects new utility line crossing State highway right-of-way, the overall impact will be negligible. Variance procedures are built into the State Highway Utility Accommodation Code for those utility companies experiencing financial difficulties to comply with the increased vertical clearance requirement. (V) At least two alternatives to the proposed rule or amendment that can be identified by the submitting agency or a member of the public, including the costs and benefits of pursuing each of the alternatives identified. (1) The alternative of taking no action, wherein CDOT makes no change to the minimum vertical clearance requirement of 20 feet 6 inches over roadways, would cost CDOT and CREA nothing. However, this approach fails to improve worker safety. (2) Establish the minimum vertical clearance at 25 feet based on the minimum standard used by Xcel Energy as well as the equipment in (I) above. This will have no net effect on CDOT costs, but will also increase REA costs by approximately $800 per crossing. No specific projects have been identified that will cross State highways in the next five years. This rule applies only to new installations, so existing facilities are not required to be upgraded to the proposed vertical clearance requirements. Regulatory Analysis Requirements: (4.5) (a) Upon request of any person, at least fifteen days prior to the hearing, the agency shall issue a regulatory analysis of a proposed rule. The regulatory analysis shall contain: (I) A description of the classes of persons who will be affected by the proposed rule, including classes that will bear the costs of the proposed rule and classes that will benefit from the proposed rule; All persons served by any REA or other similar electric utility whose facilities must cross a State highway in the future will be affected, albeit Page 4 of 6 Final minimally. The $800.00 cost increase per crossing would likely be passed on to existing customers utilizing the service. There have been no specific projects identified to be constructed in the next five years that this change will affect. All persons entering and working within the State Highway right-of-way will be positively impacted by this proposed rule. The proposed rule will have the effect of increasing their safety while working within the right-of-way in the vicinity of overhead electric facilities. All citizens of Colorado will be positively affected by this proposed rule. The increased safety of those working within the right-of-way may have the effect of lowering workers compensation, health and insurance rates (II) To the extent practicable, a description of the probable quantitative and qualitative impact of the proposed rule, economic or otherwise, upon affected classes of persons; There were 659,927 customers served by Colorado REAs in 2007. Fifty one crossings that cost an average of $800.00 per crossing amount to an annual total expense of $40,800.00. The cost of this rule would amount to an average monthly cost increase of $0.005 for each REA customer in Colorado. (III) The probable costs to the agency and to any other agency of the implementation and enforcement of the proposed rule and any anticipated effect on state revenues; None are anticipated as the State Highway Utility Accommodation Code has been utilized as a guide by CDOT for more than three years to date. (IV) A comparison of the probable costs and benefits of the proposed rule to the probable costs and benefits of inaction; These costs are unknown. Intuitively, increasing electrical line clearances over roadways may save lives. (V) A determination of whether there are less costly methods or less intrusive methods for achieving the purpose of the proposed rule; and The department has undertaken an active campaign to train and remind maintenance workers about operating heavy equipment under overhead lines. There are approximately 1,440 maintenance workers who have been trained over the past 12 months as part of an ongoing, existing safety program. Every Transportation Maintenance worker in CDOT attends annual training at the Maintenance Training Academy located at Camp Page 5 of 6 Final George West in Golden. Safety training is included in this annual training. Costs of the training associated with overhead lines were absorbed within the budget of the Maintenance Training Academy’s operating costs of $595,405 per year. (a) A description of any alternative methods for achieving the purpose of the proposed rule that were seriously considered by the agency and the reasons why they were rejected in favor of the proposed rule. As stated above, maintenance worker safety measures are already in place to supplement this proposal, but other active measures are not costeffective. One such measure would be to require all crossings to be made underground at a significantly increased cost above this proposed alternative. (b) Each regulatory analysis shall include quantification of the data to the extent practicable and shall take account of both short-term and long-term consequences. Very little data is available on the subject matter; however, based on the limited data discussed above, the short-term and long-term consequence of this regulation is improvement of roadway worker safety. (c) The regulatory analysis shall be available to the public at least five days prior to the rule-making hearing. (d) If the agency has made a good faith effort to comply with the requirements of paragraphs (a) to (c) of this subsection (4.5), the rule shall not be invalidated on the ground that the contents of the regulatory analysis are insufficient or inaccurate. Page 6 of 6