Chapter 13, Solutions Cornett, Adair, and Nofsinger CHAPTER 13 - WEIGHING NET PRESENT VALUE AND OTHER CAPITAL BUDGETING CRITERIA Questions LG1 1. Is the set of cash flows depicted below normal or non-normal? Explain. 0 1 2 3 4 5 Time Cash Flow -$100 -$50 $80 $0 $100 $100 They’re normal: there is only one change in cash flows from negative to positive. LG1 2. Derive an accept/reject rule for IRR similar to 13-8 that would make the correct decision on cash flows that are non-normal, but which always have one large positive cash flow at time zero followed by a series of negative cash flows: 0 1 2 3 4 5 Time Cash Flow Sign + - - - - With one positive at the beginning and all future cash flows negative, this type of project would be worth more if rates were higher, implying that the NPV profile would be upward-sloping. So the appropriate accept/reject decision rule would look like Accept Project if IRR ≤ Cost of Capital Reject Project if IRR > Cost of Capital LG1 3. Is it possible for a company to initiate two products that target the same market and are not mutually exclusive? Sure, as long as the market has room for both products. LG2 4. Suppose that your company used “APV”, or “All-the-Present Value-Except-CF0”, to analyze capital budgeting projects. What would this rule’s benchmark value be? Accept Project if APV ≥ -CF0 Reject Project if APV < -CF0 LG3 5. Under what circumstances could Payback and Discounted Payback be equal? They would be equal if i = 0. LG5 6. Could a project’s MIRR ever exceed its IRR? 13-1 Chapter 13, Solutions Cornett, Adair, and Nofsinger MIRR would be greater than IRR if a project with normal cash flows had a negative NPV. LG6 7. If you had two mutually exclusive, normal-cash-flow projects whose NPV profiles crossed at all points, for which range of interest rates would IRR give the right accept/reject answer? At all rates, because we would be indifferent between the two projects at any rate. LG7 8. Suppose a company wanted to double their firm’s value with the next round of capital budgeting project decisions. To what would they set the PI benchmark to make this goal? They would set it equal to 1. LG5 9. Suppose a company faced different borrowing and lending rates: How would this range change the way that you would compute the MIRR statistic? We would want to use the borrowing rate to move the negative cash flows to time 0, and the lending rate to move the positive cash flows to the end of the project. Problems Basic Problems LG2 13-1 Compute the NPV for Project M and accept or reject the project with the cash flows shown below if the appropriate cost of capital is 8 percent. Project M 0 1 2 3 4 5 Time Cash Flow -$1,000 $350 $480 $520 $300 $100 Using equation 13-2: NPV $1,000 $350 1.08 1 $480 1.08 2 $520 1.08 $436.96 The project should be accepted. 13-2 3 $300 1.08 4 $100 1.08 5 Chapter 13, Solutions LG2 13-2 Cornett, Adair, and Nofsinger Compute the NPV statistic for Project Y and tell whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 12 percent. Project Y 0 1 2 3 4 Time Cash Flow -$11,000 $3,350 $4,180 $1,520 $2,000 Using equation 13-2: NPV $11,000 $3,350 1.12 1 $4,180 1.12 2 $1,520 1.12 3 $2,000 1.12 4 $2,323.72 The project should be rejected. LG2 13-3 Compute the NPV statistic for Project U and recommend whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent. Project U 0 1 2 3 4 5 Time Cash Flow -$1,000 $350 $1,480 -$520 $300 -$100 Using equation 13-2: NPV $1, 000 $350 1.10 1 $1, 480 1.10 2 $520 1.10 3 $300 1.10 4 $100 1.10 5 $293.45 The project should be accepted. LG3 13-4 Compute the Payback statistic for Project A and recommend whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 8 percent and the maximum allowable payback is 4 years. Project A 0 1 2 3 4 5 Time Cash Flow -$1,000 $350 $480 $520 $300 $100 13-3 Chapter 13, Solutions Cornett, Adair, and Nofsinger Solving equation 13-3 for N, cumulative cash flow will switch from negative and positive between years 2 and 3: LG3 13-5 Year Cash Flow Cumulative Cash Flow 0 -$1,000 1 $350 2 $480 3 $520 4 $300 5 $100 -$1,000 -$650 -$170 $350 Specifically, PB 2 $170 2.3269 years so this project should be accepted. $520 Compute the Payback statistic for Project B and decide whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 12 percent and the maximum allowable payback is 3 years. Project B 0 1 2 3 4 5 Time Cash Flow -$11,000 $3,350 $4,180 $1,520 $0 $1,000 Solving equation 13-3 for N: Year Cash Flow Cumulative Cash Flow 0 -$11,000 -$11,000 1 $3,350 -$7,650 2 $4,180 -$3,470 3 $1,520 -$1,950 4 $0 -$1,950 5 $1,000 -$950 This project will never achieve payback, and should be rejected. LG3 13-6 Compute the Discounted Payback statistic for Project C and recommend whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 8 percent and the maximum allowable discounted payback is 3 years. Project C 0 1 2 3 4 5 Time Cash Flow -$1,000 $350 $480 $520 $300 $100 Solving equation 13-5 for N, cumulative PV of cash flow will switch from negative and positive between years 2 and 3: 13-4 Chapter 13, Solutions Cornett, Adair, and Nofsinger Year Cash Flow 0 -$1,000 Cash Flow PV -$1,000 1.08 1.08 Cum. Cash Flow PV -$1,000 $324.07 -$675.93 $411.52 -$264.41 Specifically, DPB 2 LG3 13-7 1 $350 $350 2 $480 $480 1 3 $520 $520 1.08 2 4 $300 5 $100 3 $412.79 $148.38 $264.41 2.64 years and this project should be accepted. $412.79 Compute the Discounted Payback statistic for Project D and recommend whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 12 percent and the maximum allowable discounted payback is 4 years. Project D 0 1 2 3 4 5 Time Cash Flow -$11,000 $3,350 $4,180 $1,520 $0 $1,000 The NPV for this project is negative, so discounted payback never occurs. LG5 13-8 Compute the IRR statistic for Project E and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 8 percent. Project E 0 1 2 3 4 5 Time Cash Flow -$1,000 $350 $480 $520 $300 $100 The IRR for this project will be the solution to equation 13-7: 0 $1,000 1 IRR 0 $350 1 IRR 1 $480 1 IRR 2 $520 1 IRR IRR .2549, or 25.49% Since IRR > i, this project should be accepted. 13-5 3 $300 1 IRR 4 $100 1 IRR 5 Chapter 13, Solutions LG5 13-9 Cornett, Adair, and Nofsinger Compute the IRR statistic for project F and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 12 percent. Project F 0 1 2 3 4 Time Cash Flow -$11,000 $3,350 $4,180 $1,520 $2,000 The IRR for this project will be the solution to equation 13-7: 0 $11,000 1 IRR 0 $3,350 1 IRR 1 $4,180 1 IRR 2 $1,520 1 IRR 3 $2,000 1 IRR 4 IRR .2068, or 20.68% Since IRR > i, this project should be accepted. LG5 13-10 Compute the IRR statistic for Project G and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent. Project G 0 1 2 3 4 5 Time Cash Flow -$1,000 $350 $1,480 -$520 $300 -$100 IRR for this project will be the solution to equation 13-7: 0 $1,000 1 IRR 0 $350 1 IRR 1 $1, 480 1 IRR 2 $520 1 IRR 3 $300 1 IRR 4 $100 1 IRR 5 However, since cash flows are not normal, there may be multiple solutions to this problem, and IRR should not be used. LG5 13-11 Compute the MIRR statistic for Project H and note whether to accept or reject the project with the cash flows shown below if the appropriate cost of capital is 8 percent. Project H 0 1 2 3 4 5 Time Cash Flow -$1,000 $350 $480 $520 $300 $100 13-6 Chapter 13, Solutions Cornett, Adair, and Nofsinger Cash flows will be moved as shown below: 0 -$1,000 Year Cash Flow 1 $350 2 $480 3 $520 4 $300 5 $100 $350 1.08 $480 1.08 $520 1.08 $300 1.08 4 Future Value (If Positive) $476.17 3 $604.66 2 1 $100 $324 $606.53 $2,111.36 Sum of FV Modified CFs -$1,000 $2,111.36 With this new set of modified cash flows, the MIRR is: 0 $1,000 1 IRR 0 $2,111.36 1 IRR 5 IRR .1612, or 16.12% Since our MIRR decision statistic exceeds the 8 percent cost of capital, we would accept the project under the MIRR method. . LG5 13-12 Compute the MIRR statistic for Project I and tell whether to accept or reject the project with the cash flows shown below if the appropriate cost of capital is 12 percent. Project I 0 1 2 3 4 Time Cash Flow -$11,000 $3,350 $4,180 $1,520 $2,000 Cash flows will be moved as shown below: Year Cash Flow 0 -$11,000 2 $4,180 $3,350 1.12 $4,180 1.12 3 Future Value (If Positive) Sum of FV Modified CFs 1 $3,350 $4,706.51 $5, 243.39 3 $1,520 2 4 $2,000 $1,520 1.12 1 $1,702.40 $2,000 $13,652.30 -$11,000 $13,652.30 13-7 Chapter 13, Solutions Cornett, Adair, and Nofsinger With this new set of modified cash flows, the MIRR is: 0 $11,000 1 IRR 0 $13,652.30 1 IRR 4 IRR .0555, or 5.55% Since our MIRR decision statistic is less than the 12 percent cost of capital, we would reject the project under the MIRR method. LG5 13-13 Compute the MIRR statistic for Project J and advise whether to accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent. Project J 0 1 2 3 4 5 Time Cash Flow -$1,000 $350 $1,480 -$520 $300 -$100 Cash flows will be moved as shown below: Year Cash Flow 0 -$1,000 Present Value (If Negative) -$1,000 1 $350 2 $1,480 3 -$520 $520 1.10 4 $300 5 -$100 $100 1.10 3 $390.68 Sum of PV -$1,452.78 Future Value (If Positive) Sum of FV Modified -$1,452.78 CFs $350 1.10 $1,480 1.10 4 3 $1,969.88 $512.44 $300 1.10 1 $330 $2,812.32 $1, 452.78 1 IRR $62.09 $2,812.32 With this new set of modified cash flows, the MIRR is: 0 5 0 $2,812.32 1 IRR 5 IRR .1412, or 14.12% 13-8 Chapter 13, Solutions Cornett, Adair, and Nofsinger Since our MIRR decision statistic is greater than the 10 percent cost of capital, we would accept the project under the MIRR method. LG5 13-14 Compute the PI statistic for Project Z for and advise the firm whether to accept or reject the project with the cash flows shown below if the appropriate cost of capital is 8 percent. Project Z 0 1 2 3 4 5 Time Cash Flow -$1,000 $350 $480 $520 $300 $100 Using equation 13-9: NPV $1, 000 $350 1.08 1 $480 1.08 2 $520 1.08 3 $300 1.08 4 $100 1.08 5 $436.96 $436.96 PI .4370, or 43.7% $1, 000 Since PI > 0, the project should be accepted. LG5 13-15 Compute the PI statistic for Project Q and tell whether you would accept or reject the project with the cash flows shown below if the appropriate cost of capital is 12 percent. Project Q 0 1 2 3 4 Time Cash Flow -$11,000 $3,350 $4,180 $1,520 $2,000 Using equation 13-9: NPV $11, 000 $3, 350 1.12 1 $4,180 1.12 2 $1, 520 1.12 $2, 323.72 $2, 323.72 PI .2112, or -21.12% $11, 000 Since PI < 0, the project should be rejected. 13-9 3 $2, 000 1.12 4 Chapter 13, Solutions LG5 Cornett, Adair, and Nofsinger 13-16 Compute the PI statistic for Project LL and decide whether to accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent. Project LL 0 1 2 3 4 5 Time Cash Flow -$1,000 $350 $1,480 -$520 $300 -$100 Using equation 13-9: NPV $1, 000 $350 1.10 1 $1, 480 1.10 2 $520 1.10 3 $300 1.10 4 $100 1.10 5 $293.45 $293.45 PI .2935, or 29.35% $1, 000 Since PI > 0, the project should be accepted. LG1 13-17 How many possible IRRs could you find for the following set of cash flows? 0 1 2 3 4 Time Cash Flow -$11,000 $3,350 $4,180 $1,520 $2,000 Since there’s only 1 change in sign, there can only be 1 IRR. LG1 13-18 How many possible IRRs could you find for the following set of cash flows? 0 1 2 3 4 Time Cash Flow -$211,000 -$39,350 $440,180 $217,520 -$2,000 Since there are 2 changes in sign, there could potentially be as many as 2 IRRs. Intermediate Problems ***Use this information to answer the next 6 questions. If a particular decision method should not be used, indicate why.*** Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 8 percent, and 13-10 Chapter 13, Solutions Cornett, Adair, and Nofsinger that the maximum allowable payback and discounted payback statistics for the project are 3.5 and 4.5 years, respectively. Time Cash Flow LG3 0 1 2 3 4 5 6 -$5,000 $1,200 $1,400 $1,600 $1,600 $1,400 $1,200 13-19 Use the payback decision rule to evaluate this project; should it be accepted or rejected? Cumulative cash flow will switch from negative and positive between years 3 and 4: 0 1 2 3 4 5 6 Year $1,200 $1,400 $1,600 $1,600 $1,400 $1,200 Cash Flow -$5,000 -3,800 -2,400 -800 800 Cumulative Cash -$5,000 Flow $800 Specifically, PB 3 3.5 years , which is equal to the maximum $1, 600 allowable payback, so this project should be accepted. LG3 13-20 Use the discounted payback decision rule to evaluate this project; should it be accepted or rejected? Cumulative PV of cash flow will switch from negative and positive between years 4 and 5: Year Cash Flow Cash Flow PV Cum. Cash Flow PV 0 -$5,000 -$5,000 -$5,000 1 $1,200 $1,111 -$3,889 2 $1,400 $1,200 -$2,689 3 $1,600 $1,270 -$1,418 4 5 6 $1,600 $1,400 $1,200 $1,176 $953 $756 -$242 $710 $242 4.25 years , which is less than the maximum $953 allowable payback of 4.5 years, so this project should be accepted. Specifically, DPB 4 LG5 13-21 Use the IRR decision rule to evaluate this project; should it be accepted or rejected? The IRR for this project will be the solution to: 0 $5, 000 1 IRR 0 $1, 200 1 IRR 1 $1, 400 1 IRR 2 IRR .1706, or 17.06% Since IRR > i, this project should be accepted. 13-11 $1, 600 1 IRR 3 $1, 600 1 IRR 4 $1, 400 1 IRR 5 $1, 200 1 IRR 6 Chapter 13, Solutions LG5 Cornett, Adair, and Nofsinger 13-22 Use the MIRR decision rule to evaluate this project; should it be accepted or rejected? Cash flows will be moved as shown below: Year Cash Flow Future Value (If Positive) Sum of FV Modified CFs 0 1 2 3 4 5 6 -$5,000 $1,200 $1,400 $1,600 $1,600 $1,400 $1,200 $1, 200 1.08 $1, 400 1.08 $1, 763.19 $1, 904.68 5 $1, 600 1.08 4 $2, 015.54 3 $1, 600 1.08 $1,866.24 2 $1, 400 1.08 1 $1,512 $1, 200 $10,261.66 -$5,000 $10,261.66 With this new set of modified cash flows, the MIRR is: 0 $5, 000 1 IRR 0 $10, 261.66 1 IRR 6 IRR .1273, or 12.73% Since our MIRR decision statistic is greater than the 8 percent cost of capital, we would accept the project under the MIRR method. LG2 13-23 Use the NPV decision rule to evaluate this project; should it be accepted or rejected? NPV $5, 000 $1, 200 1.08 1 $1, 400 1.08 2 $1, 600 1.08 3 $1, 600 1.08 4 $1, 400 1.08 5 $1, 200 1.08 6 $1, 466.58 The project should be accepted. LG7 13-24 Use the PI decision rule to evaluate this project; should it be accepted or rejected? NPV $5, 000 $1, 200 1.08 1 $1, 400 1.08 2 $1, 600 1.08 $1, 466.58 $1, 466.58 PI .2933, or 29.33% $5, 000 Since PI > 0, the project should be accepted. 13-12 3 $1, 600 1.08 4 $1, 400 1.08 5 $1, 200 1.08 6 Chapter 13, Solutions Cornett, Adair, and Nofsinger ***Use this information to answer the next 6 questions. If you should not use a particular decision technique, indicate why.*** Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 11 percent, and that the maximum allowable payback and discounted payback statistics for your company are 3 and 3.5 years, respectively. 0 1 2 3 4 5 Time Cash Flow -$235,000 $65,800 $84,000 $141,000 $122,000 $81,200 LG3 13-25 Use the payback decision rule to evaluate this project; should it be accepted or rejected? Cumulative cash flow will switch from negative and positive between years 2 and 3: Year Cash Flow Cumulative Cash Flow 0 -$235,000 -$235,000 Specifically, PB 2 LG3 1 $65,800 -$169,200 2 3 $84,000 $141,000 -$85,200 $55,800 4 $122,000 $177,800 5 $81,200 $259,000 $85, 200 2.6043 years so this project should be accepted. $141, 000 13-26 Use the discounted payback decision rule to evaluate this project; should it be accepted or rejected? Cumulative PV of cash flow will switch from negative and positive between years 3 and 4: Year Cash Flow 0 -$235,000 Cash Flow PV -$235,000 Cum. Cash Flow PV -$235,000 1 $65,800 2 $84,000 3 $141,000 4 5 $122,000 $81,200 $65,800 $84, 000 $141, 000 $122, 000 1.11 1.11 1.11 1.11 1 2 3 4 $59, 279.28 $68,176.28 $103, 097.98 $80, 365.18 -$175,721 -$107,544 -$4,446 $75,919 $4, 446 3.05 years , which is less than the maximum $80, 365.18 allowable discounted payback, so project should be accepted. Specifically, DPB 3 13-13 Chapter 13, Solutions LG5 Cornett, Adair, and Nofsinger 13-27 Use the IRR decision rule to evaluate this project; should it be accepted or rejected? The IRR for this project will be the solution to: 0 $235, 000 1 IRR 0 $65,800 1 IRR 1 $84, 000 1 IRR 2 $141, 000 1 IRR 3 $122, 000 1 IRR 4 $81, 200 1 IRR 5 IRR .2879, or 28.79% Since IRR > i, this project should be accepted. LG5 13-28 Use the MIRR decision rule to evaluate this project; should it be accepted or rejected? Cash flows will be moved as shown below: 0 Year Cash -$235,000 Flow Future Value (If Positive) Sum of FV Modified -$235,000 CFs 1 2 3 4 5 $65,800 $84,000 $141,000 $122,000 $81,200 $65,800 1.11 4 $99,889.03 $84, 000 1.11 3 $141, 000 1.11 $122, 000 1.11 2 1 $173, 726.10 $114,881 $81, 200 $135, 420 $605,116.14 $605,116.14 With this new set of modified cash flows, the MIRR is: 0 $235, 000 1 IRR 0 $605,116.14 1 IRR 5 IRR .2082, or 20.82% Since our MIRR decision statistic is greater than the 11 percent cost of capital, we would accept the project under the MIRR method. LG2 13-29 Use the NPV decision rule to evaluate this project; should it be accepted or rejected? NPV $235, 000 $65,800 1.11 1 $84, 000 1.11 2 $141, 000 1.11 $124,106.98 Since NPV > 0, the project should be accepted. 13-14 3 $122, 000 1.11 4 $81, 200 1.11 5 Chapter 13, Solutions LG7 Cornett, Adair, and Nofsinger 13-30 Use the PI decision rule to evaluate this project; should it be accepted or rejected? NPV $235, 000 $65,800 1.11 1 $84, 000 1.11 2 $141, 000 1.11 3 $122, 000 $124,106.98 $124,106.98 PI .5281, or 52.81% $235, 000 Since PI > 0, the project should be accepted. Advanced Problems ***Use the project cash flows for the two mutually exclusive projects shown to the right to answer the following 4 questions.*** LG6 13-31 Graph the NPV profiles for both projects on a common chart, making sure that you identify all of the “crucial” points. Since the two NPV profiles shown below do not cross in the first quadrant, the only crucial points are the two projects’ IRRs: IRRA = 13% and IRRB = 14.29% 13-15 1.11 4 $81, 200 1.11 5 Chapter 13, Solutions Cornett, Adair, and Nofsinger NPV Profiles $600.00 $500.00 $400.00 NPV $300.00 $200.00 $100.00 20.00% 19.00% 18.00% 17.00% 16.00% 15.00% 14.00% 13.00% 12.00% 11.00% -$200.00 10.00% 9.00% 8.00% 7.00% 6.00% 5.00% 4.00% 3.00% 2.00% 1.00% -$100.00 0.00% $- r A LG6 B 13-32 For what range of possible interest rates would you want to use IRR to choose between these two projects? For what range of rates would you NOT want to use IRR? Since the two projects’ NPV profiles do not cross in the first quadrant, IRR would work for ALL possible rages of rates. LG6 13-33 Assume that the expected cash flows for these two projects have been revised as shown to the right. Reconstruct the NPV profiles. Now the two NPV profiles will cross in the first quadrant, so we will need to compute the crossover rate as well as the two projects’ IRRs. 13-16 Chapter 13, Solutions Cornett, Adair, and Nofsinger NPV Profiles $500.00 $400.00 $300.00 NPV $200.00 $100.00 -$300.00 r A B As shown below, project A’s IRR will still be 13%, project B’s IRR will be 11.08%, and the two profiles will cross at 6.03%. LG6 13-34 With the new expected cash flows shown to the right, is there still a range of possible interest rates where the 3-step decision process for choosing between mutually exclusive projects using IRR will accept the wrong project? Explain your answer. Yes. If i < 6.03%, we should NOT use the IRR decision rule, as it will always want to choose project A at step two of the runoff, even if project B is better (as measured by a higher NPV at those lower interest rates). 13-17 20.00% 19.00% 18.00% 17.00% 16.00% 15.00% 14.00% 13.00% 12.00% 11.00% 9.00% 8.00% 10.00% -$200.00 7.00% 6.00% 5.00% 4.00% 3.00% 2.00% 1.00% -$100.00 0.00% $- Chapter 13, Solutions LG6 Cornett, Adair, and Nofsinger 13-35 Construct an NPV profile and determine EXACTLY how many nonnegative IRRs you can find for the following set of cash flows: As shown below, there appear to be only two. NPV Profiles $100.00 $80.00 $60.00 $40.00 2100.00% 2000.00% 1900.00% 1800.00% 1700.00% 1600.00% 1500.00% 1400.00% 1300.00% 1200.00% 1100.00% 900.00% 800.00% 700.00% 600.00% 500.00% 400.00% 1000.00% -$60.00 300.00% -$40.00 200.00% $-$20.00 100.00% NPV $20.00 -$80.00 -$100.00 r LG6 13-36 Construct an NPV profile and determine EXACTLY how many nonnegative IRRs you can find for the following set of cash flows: As shown below, there appears to be only one in the first quadrant. 13-18 Chapter 13, Solutions Cornett, Adair, and Nofsinger NPV Profiles $160.00 $140.00 $120.00 $100.00 NPV $80.00 $60.00 $40.00 $20.00 2100.00% 2000.00% 1900.00% 1800.00% 1700.00% 1600.00% 1500.00% 1400.00% 1300.00% 1200.00% 1100.00% 900.00% 1000.00% 800.00% 700.00% 600.00% 500.00% 400.00% -$60.00 300.00% -$40.00 200.00% -$20.00 100.00% $- r Research It! Business Valuation The capital budgeting decision techniques that we’ve discussed all have strengths and weaknesses, but they do comprise the most popular rules for valuing projects. Valuing entire businesses, on the other hand, requires that some adjustments be made to various pieces of these methodologies. For example, one alternative to NPV used quite frequently for valuing firms is called Adjusted Present Value (APV). To explore these alternative decision rules, do a web search for APV and answer the following questions: 1. What is APV, and how does it differ from NPV? 13-19 Chapter 13, Solutions Cornett, Adair, and Nofsinger 2. What other business valuation models seem to be popular? Solution: The two main approaches to valuation used by practitioners are those involving discounted cash flows, which we’ve discussed here, and those involving the “multiples” method, which involves using a sample of ratios from comparable peer groups to estimate an appropriate price for a firm. Integrated Minicase Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 11 percent, and that the maximum allowable payback and discounted payback statistics for your company are 3 and 3.5 years, respectively. Time Cash Flow 0 -$175,000 1 -$65,800 2 $94,000 3 $41,000 4 $122,000 5 $81,200 Using every one of the capital budgeting decision methods discussed in this chapter, evaluate this project, indicating whether each decision rule would call for acceptance or rejection of the project. Solution: The decision statistics and the appropriate accept/reject decisions are shown below: 13-20 Chapter 13, Solutions Cornett, Adair, and Nofsinger 13-21