CONSOLIDATED RESULTS FOR THE YEAR ENDED 28 FEBRUARY 2014 2 STORY LINE Lowlights Loss making contracts in Civils Trading environment Highlights Geotechnical sale Developments established Pipelines maintained growth Financial position Gearing Order book Going concern 3 AGENDA • Salient features • Financial overview • Operational overview • Strategy • Prospects and order book • Conclusion 4 SALIENT FEATURES 5 SALIENT FEATURES (CONTINUED OPERATIONS) Revenue Order book Gearing R1,593bn R2,6bn 27,0% ▲ 3,6% ▲ 18,6% ▼ 16,4% R1,538bn R2,2bn 32,3% Net cash Health & Safety HEPS R20,9 million LTIFR 0,86 (11,3) cents ▼ ▲ ▼ 155,1% R33,6 million LTIFR 0,59 20,5 cents Non-recurring items in financial year 2014 Reduced to 0,43 at April 2014 • Sale of Geotechnical business • Impairment of goodwill A year of many highs and lows 6 SALIENT FEATURES CONTINUED Sale of Geotechnical business • Approval at GM - 18 November 2013 • Disposal valued at R592 million including fair value of contingent consideration of R65 million • Cash received to date R497 million • Outstanding Issues › Registration of off-shore properties › Rationalisation of legacy legal structures • Sale proceeds utilised as follows: R’mil › Settle HYB 210 › Dividend of 38 cents/share 150 › Working capital investment 70 › Geotech borrowings settled 45 7 FINANCIAL REVIEW 8 FINANCIAL RESULTS IN CONTEXT Lowlights • Finalisation of loss making contracts › N4 impacted by Marikana unrest, bridge design error and consequential late completion › Kriel Civils and Boxhole contracts impacted by changes in construction methodology, subject to claims (not traded) › Hwelereng road contract for RAL subject to numerous delays and consequential late completion • Labour unrest impacted productivity on most sites • Civil’s conservative view on estimated final completion margin on Kusile contracts Major drainage at N4 Highlights • Increase in revenue and profitability maintained in Pipelines • Established Developments business • Gearing down to 27% • Order book increase to R2,6 billion • B-BBEE certified as Level 3 at 78,96 from level 4 On the back of weak markets with margins remaining under pressure 9 SUMMARY STATEMENT OF COMPREHENSIVE INCOME Segmental summary of Earnings Geotechnical Civils Pipelines Developments 2014 R’000 2013 R’000 50 178 62 203 (142 546) 39 380 29 319 21 543 962 - Corporate and eliminations (104 074) (35 416) Consolidated earnings (166 161) 87 710 Adjusted Loss/impairment of assets 84 934 Loss on disposal of discontinued operations 38 190 Headline earnings (43 043) (10 683) 77 027 10 STATEMENT OF COMPREHENSIVE INCOME Continuing operations Revenue 2014 R’000 2013 R’000 % Change 1 592 835 1 538 101 3,6 EBITDA (135 342) 163 454 (182,8) PBIT (281 761) 74 890 (476,2) - Operating (loss)/profit before non-recurring items (158 639) 64 207 (347,1) - Non-recurring items (123 122) 10 683 n/a (37 440) (31 652) 18,9 (319 201) 43 238 n/a 102 862 (18 136) n/a (216 339) 25 102 n/a 2 168 485 18,6 Net Finance expense PBT Taxation (Loss)/profit from continuing operations Order book 2 607 718 11 STATEMENT OF COMPREHENSIVE INCOME 2014 R’000 2013 R’000 Revenue 724 052 787 857 EBITDA 96 361 106 217 Attributable earnings 50 178 62 608 Discontinued operations Sale consideration 592 485 NAV of discontinued operation 624 458 Loss on disposal (31 973) Net profit from discontinued operations 50 178 Taxation effect 36 349 Surplus on disposal 54 554 12 STATEMENT OF COMPREHENSIVE INCOME Earnings per share (Loss)/profit after tax 2014 R’000 2013 R’000 (166 161) 87 710 Adjustment 123 122 10 683 Headline earnings (43 039) 77 027 (Loss)/earnings per share (cents) (43,5) 23,5 Headline (loss)/earnings per share (cents) (11,3) 20,5 13 STATEMENT OF FINANCIAL POSITION 2014 R’000 2013 R’000 Property, plant and equipment 320 135 822 678 Intangibles and goodwill 185 062 392 051 64 923 3 11 457 22 729 32 083 27 726 Trade debtors and contracts in progress 659 928 826 713 Inventories and land for development 221 345 69 721 Taxation 13 455 14 513 Cash and cash equivalents 40 423 67 647 1 548 811 2 243 781 Financial overview Financial asset at fair value Deferred tax Long-term receivables Total assets NTAV/share 168,6 cents 45 days in trade receivable 2014 Current ratio 1,65 NAV/share 203,5 cents 14 STATEMENT OF FINANCIAL POSITION 2014 R’000 2013 R’000 Share capital and reserves 777 219 1 053 262 Secured borrowings 237 393 447 988 Deferred tax liability 21 335 148 906 Bank overdraft 19 583 34 059 Preference shares 23 424 21 000 Taxation 19 131 4 508 437 013 493 816 13 713 40 242 1 548 811 2 243 781 26,5% 32,3% Financial overview Trade and other payables Provisions Total equity and liabilities Debt/equity 64 days in trade payables 15 Thousands CASH FLOW 600 500 400 300 200 100 0 Cash balance March 2013 EBITDA cash items Disposal of Geotech division Dividends Repaypaid ment of HYB Disposal of fixed assets Other Acquisition Acquisition secured of developof fixed borrowings ment assets properties Working capital Shares issued Tax paid Other investing activities Interest Cash balance February 2014 16 OPERATIONAL REVIEW 17 THE YEAR GENERAL General market • General tough contracting conditions - tight margins and fierce competition • Risk transfer to contractor • Focus on contract completion • Finalising commercial compensation claims • Still awaiting budgeted public sector expenditure • Tender activity increased but seems to be budgetary • Infrequent and delayed awards Reaction • Rebuilding order book - focus on skills • Cautious approach to Africa • Right-sizing Action • Look to consolidate construction operations in year ahead • Office established in Zimbabwe 18 PIPELINES Pipelines 2014 R’000 2013 R’000 Revenue 579 285 323 552 39 892 30 583 254 857 191 552 1 163 763 79% 42% 9% 10% Order book 654 205 518 822 Pending awards 351 700 32 000 1 380 000 1 630 000 -% -% 100% 100% PBIT Segment assets Number of employees Revenue growth Operating margins Prospects Non-government Government 19 PIPELINES CONTINUED • Focused on contract completion and commercial compensation (BG3 and Mopani) • Infrequent and delayed awards impacting 2014/15 • Start-up of major contracts - Northern and Western Aqueduct • Competition from new entrants (perceived low barrier of entry) • Impact of level 3 B-BBEE rating • Cross-border focus - Namibia, Zambia and Zimbabwe › Time and cost • Sanitation project for eThekwini progressing well BG3 100ton crane Focus on project delivery pipe lift • Plant expansion of R10 million on back of awarded work Office established in Zimbabwe 20 CIVILS 2014 R’000 2013 R’000 961 599 1 214 549 (183 881) 76 525 788 590 963 994 1 969 2 701 Revenue growth (20,8)% 47% Operating margins (13,9)% 6% 1 228 500 1 269 039 Pending awards 552 000 1 235 000 Prospects 723 000 2 940 000 Non-government 35% 45% Government 65% 55% Civils Revenue PBIT Segment assets Number of employees Order book 21 CIVILS CONTINUED • Loss making contracts (N4, Kriel and RAL) • Generally tough contracting conditions • Focus on contract completion and commercial compensation • Rebuilding order book at acceptable margins and risk • Still awaiting budgeted public sector expenditure • Delayed awards • Fierce competition at tight margins • Contracts at Kusile › Crushing nearing completion (no claims) N4 Temporary staging to portal structure Look to continue consolidating construction operations in year ahead › General services piping 62% complete (no claims) › Bulk earthworks - original contract nearing completion with minor claims › Underground facilities 51% complete with substantial scope changes and claims submitted • Plant optimisation nearing completion Reinvigorated business 22 CIVILS LOSS MAKING CONTRACTS N4 Bakwena • Contract award 4 May 2011 • Value at award R370 million • Duration originally 30 months What happened Placing selected fill at N4 • Tendered at time of economic crisis at break even • Anticipated/historical productivity never achieved resulting in R62 million loss on allowable › Steel and fuel strikes in 2012/13 › Marikana killings in March 2013 › Platinum strike 2014 • Consequential effects: › Plant utilisation achieved 60% and R60 million loss › Late completion of project forecasted to be August 2014 with impact on P&G What now • • • • Agreed programme with client - completion August 2014 Reduced resources to activity levels Negotiating contractual entitlements and claims Design errors - variation agreed with costs 23 CIVILS LOSS MAKING CONTRACTS Kriel Civils and Boxhole Civils Boxhole • Contract award 11 April 2012 • Value at award R109 million • Duration 12 months • Contract award 11 April 2012 • Value at award R35 million • Duration 8 months What happened • • • • • Earthworks at Kriel Tendered at time of low work on hand at break even Scope changed materially - subject to claim Client imposed restrictions on methodology and access Availability of client supplied materials Consequential effects: › Productivity and utilisation never achieved, R32 million loss on labour and plant › Late completion of project – Civils in May 2014 – Boxhole in July 2014 What now • • • • Civil contract complete - snags being finalised Agreed Boxhole programme with client - completion July 2014 Reduced resources to activity levels Continued with commercial claims process 24 CIVILS LOSS MAKING CONTRACTS | CONTINUED RAL road contract - Hwelereng • Contract award 10 March 2011 • Value at award R80 million • Duration 18 months What happened • Tendered at time of economic crisis at break even • Re-work impacting completion • Availability of crushed materials • Never achieved tendered production rates • Consequential effects: Road upgrade at Hwelereng for RAL › Productivity and utilisation never achieved, R27 million loss on labour and plant › Late completion of project with associated costs What now • Contract complete - handover finalised • Awarded associated works contract of R30 million, mainly subcontractors 25 CIVILS TURNAROUND STARTED NOVEMBER 2012 Actions and timeline • Loss making contracts • Productivity • Utilisation • Tender and estimating • Commercial • Civils Recovery Strategy 2014.ppt Building bridges at Diepsloot 26 DEVELOPMENTS 2014 R’000 2013 R’000 63 356 - 1 401 (1 668) 264 454 57 123 3 1 N/A N/A 2,2% N/A Order book 724 632 410 900 Pending awards 895 876 1 000 000 4 000 000 2 000 000 Non-government 51% N/A Government 49% N/A Developments Revenue PBIT Segment assets Number of employees Revenue growth Operating margins Prospects 27 DEVELOPMENTS CONTINUED Established division during the year • Orchards R30 million sales in 2014 › Project potential to be realised exceeds R240 million • Broke ground at Diepsloot East, north of Johannesburg › Project potential to be realised exceeds R2 billion, with commercial element • Uitvlugt is an integrated residential development in Three Rivers East with land transferred to Esor › Project potential excluding top structures to be realised exceeds R600 million • Soshanguve is a residential development in Tshwane with Esor acquiring development rights Orchards Completed houses Strategically important division due to secondary work potential for group › Project potential to be realised exceeds R150 million • Division may expand into top structure development • Potential in social and gap housing expected to increase over the next few years • Demand for affordable housing exceeds supply, but may be impacted by rising interest rates and unemployment 28 STRATEGY 29 STRATEGY Strategic themes • Consolidate and rationalise • Streamline support functions • Build on strong brand • Leadership • Commercial astuteness • Cash flow • Positive about SADC Strategic alignment to improve combined strength Keep it simple 30 PROSPECTS AND ORDER BOOK 31 LOOKING AHEAD Prospects • SANRAL - budget of R10 billion pa • Transnet - various rail and port projects in the pipeline • Eskom - ongoing work at Kusile and Medupi power stations with potential for Coal 3 • Major water projects planned for SA, Lesotho and Zambia • Schools - R5 billion worth of tenders submitted and still to be awarded Order book • Order book increased by 18,6% to R2,6 billion • One-year and total order book both at satisfactory levels against FY2014 revenue • Work on hand heavily weighted in favour of Government and Parastatal work 32 ORDER BOOK Order book R’mil Secured revenue FY 2015 R’mil Secured revenue FY 2015 + R’mil 1 228 500 828 500 400 000 Developments 724 632 157 000 567 632 Pipelines 654 586 357 498 297 088 2 607 718 1 342 998 1 264 720 Non-government 13% 11% 15% Government 87% 89% 85% Civils 552 000 257 000 295 000 Developments 895 876 41 053 854 823 Pipelines 351 700 235 700 116 000 1 799 576 533 753 1 265 823 2 year secured order book Civils Total secured Pending awards Total pending 33 ORDER BOOK LEGACY LOSS MAKING CONTRACTS IN WOH Impact of loss making contracts on 2015 order book Old work still to be completed • Civils order book - R1,2 billion R203,8m • Included FY15 order book is R25,4 million re legacy loss making contracts • Order book includes R203,8 million work secured prior to FY14 R25,4m • New work secured represents 81% of order book R998,3m Old work still to be completed Old loss making work to be completed 2015 New secured work 34 CAPEX 35 CAPEX 2015 R’mil 2014 R’mil 2013 R’mil - 26 313 132 406 Pipelines 20 300 9 596 17 083 Corporate 6 960 2 117 1 626 Total spend/approved 27 260 38 026 151 115 Depreciation 48 124 61 780 79 807 0,57 0,62 1,89 CAPEX Civils Depreciation cover 36 CONCLUSION 37 IN SUMMARY • Tough year across industry • Maintained growth in Pipelines • Established Developments Actions taken • Gearing improved • Controlled growth mainly in RSA with prospects in select African countries • Rebuilding Civils › Implemented and tracking progress › Complete loss making contracts › Improve commercial acumen 38 DISCLAIMER Forward-looking statements This presentation contains forward-looking statements that, unless otherwise indicated, reflect the company’s expectations as at 28 February 2014. Actual results may differ materially from the company’s expectations if known and unknown risks or uncertainties affect its business or if estimates or assumptions prove inaccurate. The company cannot guarantee that any forward-looking statement will materialise and, accordingly, readers are cautioned not to place undue reliance on these forward-looking statements. The company disclaims any intention and assumes no obligation to update or revise any forward-looking statement even if new information becomes available as a result of future events or for any other reason save as required by statute or regulation. 39 CONTACT US Esor Limited 30 Activia Road, Activia Park, Germiston 1401 PO Box 6478, Dunswart, 1508, South Africa Bernie Krone | CEO + 27 83 259 5984 +27 11 776 8700 +27 11 822 1158 Bernie.krone@esor.co.za Wessel van Zyl | CFO + 27 82 498 3518 +27 11 776 8700 +27 11 822 1158 Wessel.vanzyl@esor.co.za 40