1 - BT Wholesale

advertisement
BTW Planned Engineering Works
90 day overview
May to July 2012
The information contained in this Presentation is confidential information as per your terms and conditions with British Telecommunications plc (BT).
Please treat it accordingly and do not forward, republish or permit unauthorized access.
BT reserves the right to make changes to the information in this Presentation at any time without further notice.
1
BTW 2012 Network Changes – 3 month rolling plan
•
Whilst BTW has continually worked to enhance its network, we are currently undergoing an
exceptional level of change driven by four main drivers:–
–
–
–
•
•
•
•
2
Stability – to improve the reliability of the network, BTW is targeting certain network elements with hardware
and software improvements.
Capacity – the need for additional capacity is driven by an increase in the number of broadband users on
the 21C network (through migration from 20C and growth) and also by the ever-increasing bandwidth
demands of those users.
Resilience –to improve the resilience of the network , BTW is actively removing single points of failure from
the network
New Functionality – to meet the needs of the market BTW needs to enhance its network to deliver the
services its customers require.
This presentation outlines the key upgrade programmes, their drivers, customer impact and
the number of upgrades per programme per week.
BTW is keen to deliver all the required improvements as quickly as possible whilst actively
managing the risk to customers. For this reason a range of run-rates against each
programme has been outlined. The actual run-rates achieved will be determined by this
ongoing live analysis of risk.
Customer outage times for the PEWs start between 00:01 and 02:00 with the aim of
completing customer impacting work by 04:00. This allows 2 hours for roll-back should the
PEW be unsuccessful.
Business as usual capacity upgrades and upgrades to resilient structures have not been
listed here.
Network
change
Status
Programme
Summary
22
Introduce High throughput BEA-VS into the 21c platform
BTID Network Change
Number – Major Project Summaries
HT BEA-VS
Status –
Introduction Deployment
ongoing
• 3rd migration at Glasgow completed on 17th May.
• Next site will be Colindale on 7th June.
• Pre-Olympic scope of this project is 5 sites to be completed by 5 th July.
Network
change
Status
MSPE
software
upgrade.
Status – 3
Core
upgrades
remain to be
completed
Programme
Number
11
Summary
Code upgrade (3.9.1 + SMU patches) is required on the Cisco MSPE to
improve platform stability.
• Two upgrades complete since last report – Edinburgh and Preston.
• Completion is targeted for 13th June.
3
BTID Network Change – Major Project Summaries
Network
change
Status
2nd
Vendor
MSPE
Status –
Deployment
Ongoing
Programme
Number
23
Summary
Introduce 2nd vendor MSPE for WCC and WBMC shared
resilience.
• Upgrade of 17th site for WCC resilience complete on 30th May. 6 more remain to be completed for WCC
• Upgrade of 12th device complete for WBMC resilience on 30th May. 1 remain to complete for WBMC shared.
20
4
BTID Network Change – Major Project Summaries
Network
change
Status
21c BRAS
Software
Upgrade
Status –
Deployment
Ongoing (37%
complete)
Programme
Number
26
Summary
Upgrade software on 21c BRAS to fix known defects.
• Defects in the software which will require resolution.
• BAU deployment is now proceeding, 74 now upgraded.
• Upgrade plan is agreed, current plan for software is to complete by 6th July.
Network
change
Status
2nd vendor
MSAN Software
Upgrade
Status –
Deployment
Pending
Programme
Number
• Resolves software defects.
• 183 out of 688 upgrades complete.
• Deployment completion due19th June.
5
30
Summary
Upgrade software on 2nd vendor MSAN to fix known defects.
Non
customer
impacting
Affected
Products
Av. End
user
outage
(Mins)
Upgrades
per week
1
None
0
1
Progress
May 12
2/2
Upgrades
per PEW
Planned End
Capacity
EUs per
upgrade
Aug
Edinburgh
LPA
Upgrades
Complete /
Total
July
6
Key
Drivers
June
29
Upgrade
May
Prog No:
20C Upgrades
Edin
20c
requ
21C Upgrades
Upgrades
per PEW
Affected
Products
Av. End user Upgrade
outage
s per
(Mins)
week
Progress
Capacity
20
MSE
Upgrades
2/70
Av 2500
Min 0
Max 8000
1
WBC
1
8 - 12
Av 20000
Min 0
Max 100000
1
WBMC
Phase 1 –
No Outage
Phase 2180
(240 Max)
1-4
Various
1
5-8 minutes
TBA
(will not
start
until
2012)
WBC
MEAS
ETHERNET
Sept 12
Phase 1
83/83 (No
Customer
impact)
Phase 2
23/26
Up to 75
Jun 12
Code
Update
11
MPLS Core
Router
Upgrades
35
Dec 12
460/520
WBC
Ongoing
Resilience
9
Access
MCLAG
1–5
Aug
Stability
6
Av 800
Min 0
Max 1000
July
Ongoing
June
SVLAN moves Capacity,
7
EUs per
upgrade
May
Prog No:
Key Drivers Upgrades
Complete /
Total
Planned End
Upgrade
SVL
offl
Bro
to a
alle
Acc
poi
(mo
agg
and
ove
MP
req
soo
Pha
imp
com
MS
fun
add
by u
Edg
21C Upgrades
3/5
2nd Vendor
23 MSPE
Stability
2nd vendor
30 MSAN
Upgrade
Stability
183/688
5
Av 120K
1
WBC /
WCC
45 mins
1
WBC /
WCC /
Ethernet
30 secs –
10 mins
2
WBC /
WBMC/
WCC
45 mins
Up to 50
WBC /
WBMC
30 mins
WBC /
WBMC/
WCC
40 mins
Av 20k
1
Av 17000
Max
32000
1
Average
700
120
Average
700
40-50
EEA – EES
This chan
scalability
Additiona
and this i
introduci
To increa
2nd vendo
introduce
21c BRAS
increase
480
200 - 250
June 12
5642/5844
0
May 12
Stability /
Capacity
None
July 12
Copper MSAN
Software
27
Upgrade
8
74/200
40
June 12
Capacity
Stability
Non
Customer
impacting
Progress
June 12
High
22 Throughput
BEA-VS
Upgrades
per week
Jan13
285/1060
Av. End
user
outage
(Mins)
Planned End
Capacity
BRAS
software
Upgrade
Affected
Products
Aug
EEA – EES
24 Backhaul
Uplift
29/51
Upgrades
per PEW
July
BB EUs
and/or
Ethernet
Circuits
per
upgrade
June
Upgrades
Complete /
Total
May
Key
Drivers
Progr No:
Upgrade
Software
new line
stability b
energy ef
Completed 20C Upgrades
1
14
2
9
Completed 21C Upgrades
3
5
8
10
12
10
Completed 21C Upgrades
7
13
19
18
21
11
Completed 21C Upgrades
Upgrades
Complete
/ Total
BB EUs
and/or
Ethernet
Circuits per
upgrade
Upgrades
per PEW
Affected
Products
Copper MSAN
Functional
ity
5594/5594
NonCustomer
Impacting
Up to 120
None
0
Up to 480
Dec
11
EAD Chassis
Stability
6950/6950
Up to 15
Ethernet
Circuits
Up to 200
Ethernet,
Mobile
Ethernet
<1
Up to 1000
Feb
12
Non
Customer
Impacting
Up to 12
WBC
0
16-30
Feb 12
Progr No:
Key
Drivers
15 Upgrade
16 Code Upgrade
3
12
21C BRAS
Core
Migration
Capacity
151/151
Av. End
user
outage
(Mins)
Upgrades
per wee
Date Ended
Upgrade
BEA VS Card
17 Upgrade
Capacity
20/20 –
Complete
NonCustomer
Impacting
1
None
0
Up to 4
Mar
12
DDR
28 Hardware
replacement
Stability
200/200
Non
Customer
impacting
10
None
0
50
May
12
Broadband Services on 21CN
29
9
27
22
30
20
28 26
6
24
13
23
11
Ethernet Service on 21CN
14
Descriptions
15
Management of risk
16
Download