1 - BT Wholesale

advertisement
BTW Planned Engineering Works
90 day overview January 2014 to March
2014
These dates are indicative dates only and not to be used for any forecasting purposes as
they are all subject to change. Please ensure that you wait for formal notifications from
IRAMS.
The information contained in this Presentation is confidential information as per your terms and conditions with British Telecommunications plc (BT).
Please treat it accordingly and do not forward, republish or permit unauthorized access.
BT reserves the right to make changes to the information in this Presentation at any time without further notice.
1
BTW 2012 Network Changes – 3 month rolling plan
•
Whilst BTW has continually worked to enhance its network, we are currently undergoing an
exceptional level of change driven by four main drivers:–
–
–
–
•
•
•
•
2
Stability – to improve the reliability of the network, BTW is targeting certain network elements with hardware
and software improvements.
Capacity – the need for additional capacity is driven by an increase in the number of broadband users on
the 21C network (through migration from 20C and growth) and also by the ever-increasing bandwidth
demands of those users.
Resilience –to improve the resilience of the network , BTW is actively removing single points of failure from
the network
New Functionality – to meet the needs of the market BTW needs to enhance its network to deliver the
services its customers require.
This presentation outlines the key upgrade programmes, their drivers, customer impact and
the number of upgrades per programme per week.
BTW is keen to deliver all the required improvements as quickly as possible whilst actively
managing the risk to customers. For this reason a range of run-rates against each
programme has been outlined. The actual run-rates achieved will be determined by this
ongoing live analysis of risk.
Customer outage times for the PEWs start between 00:01 and 02:00 with the aim of
completing customer impacting work by 06:00. This allows 2 hours for roll-back should the
PEW be unsuccessful.
Business as usual capacity upgrades and upgrades to resilient structures have not been
listed here.
21C Upgrades
Prog No:
Affected
Products
Av. End user Upgrade
outage
s per
(Mins)
week
Av 800
Min 0
Max 1000
9
WBC
35
Up to 75
Av 3000
1
HE, WBC,
WBMC
10
80
22
High
Throughput
BEA-VS
Capacity
17/20
Av 300K
1
WBC /
WCC
45 mins
1
BEA-VS
Software
Upgrade
Stability
0/20
Av 300K
1
WBC /
WBMC /
WCC
Sub-second
1
Aug 14
79/2500
45
Features (Ipv6),
Vendor Support
Ongoing
Ongoing
7750 R10
Upgrade
Apr-14
50
Progress
Nov
6
Upgrades
per PEW
Planned End
Capacity,
Stability
EUs per
upgrade
Feb
SVLAN
moves
Upgrades
Complete /
Total
Jan
Key Drivers
Dec
Upgrade
Apr-14
Upgrades
per PEW
Affected
Products
Av. End user Upgrade
outage
s per
(Mins)
week
Progress
Av 11000
Min 3000
Max 18000
2
IPSC
20
8
473/4620
700
15
IPSC
10
60
Apr 14
79/225
Planned End
EoL
EUs per
upgrade
Feb
ERX BRAS
12.3
Upgrades
Complete /
Total
Jan
Key Drivers
Dec
44
Upgrade
Nov
Prog No:
Ongoing 20C Upgrades Cont’d
46
4
Sep 14
DSLAM SDH MSIP Platform
Closure
Bypass
(MSIP
Closure)
Completed 20C Upgrades
1
14
2
36 10k BRAS SB11
5
Stability
122/122
Av 11000
Min 3000
Max 18000
6
IPSC
Up to 18
Apr 13
Completed 21C Upgrades
Upgrades
Complete
/ Total
BB EUs
and/or
Ethernet
Circuits per
upgrade
Upgrades
per PEW
Affected
Products
BRAS software
Upgrade
Stability
193/193
Av 17000
Max 32000
1
WBC /
WBMC/
WCC
45 mins
Up to 50
Jul 12
Stability /
Capacity
5844/5844
Average
700
120
WBC /
WBMC
30 mins
480
May
12
2nd vendor
MSAN
Upgrade
Stability
702/702
Average
700
40-50
WBC /
WBMC/
WCC
40 mins
200 - 250
Jul
12
2nd Vendor
Stability
51/51
Av 20k
1
WBC /
WCC /
Ethernet
30 secs –
2 mins
2
Jan
13
Non Service
Impacting
0
None
0
4
Dec
13
Progr No:
Key
Drivers
Copper MSAN
27 Software
Upgrade
30
23 MSPE
38
6
2nd Vendor
MSPE
Software
Upgrades
Functionalit
y
(LAG
Support)
67/67
Av. End
user
outage
(Mins)
Upgrades
per week
Date Ended
Upgrade
Broadband Services on 21CN
46
2
49
46
1
36
14
29
44
11
27
32
20
9
6
47 48
39
45
39
37
4
28
26
22 35
40
34 45
50
45
45
39
23
31
38
34
11
51
Ethernet Service on 21CN
8
Descriptions
9
Management of risk
10
Download