MICROSOFT: PROJECT
ALLUVION
PROJECT ALLUVION
Incentives & Infrastructure
Estimated incentives and Infrastructure
cost: $87,000,000
We will have a Development Agreement
with Microsoft that will also have a
minimum assessment agreement
requiring a minimum property valuation
of $255,000,000 at the end of Phase IV
Project Description
Four phase data center
Area: 154 acres
Total investment: $1,126,218,000
Total building size: 1,165,364 square feet
Total employment: 84
Potential Infrastructure Improvements
South 8th Street (old Army Post Rd to County Line Rd)
Pine Avenue to new Army Post Road
Potential Infrastructure Improvements
Continued
Pine Avenue upgrades (eastern Corporate Limits to
South 8th Street)
Maffitt Road/County Line Road
connection (South Veterans’ Parkway to County Line
Road)
County Line Road
connector to Maffitt
Road extension
Water & Sewer
Water line distribution/storage upgrades
Sanitary sewer line upgrades
Services
Relocation of MidAmerican power line
Fiber optic conduit/fiber line installation
Public Safety Facility (to be
constructed/equipped as part of TIF
District at a date to be determined)
Schedule
Review plans (Phase I only)
Grading
Construction of Phase 1
Open Phase 1
Future Phases