Planning is a legal Obligation • PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be approved by the Head of the Procuring Entity (HOPE) or by the officer empowered by the HOPE BAU:June 16, 2011 PP for SPM 1 Four Key Words Item Lot Package Contract A single article or unit in a list. With an identified quantity ….. 1,2,3 etc A number of items grouped together Any number of items can form a lot A group of lots forming a contract No package can have more than 5 lots The agreement between the PE and Supplier/Contractor/Consultant and enforceable by law Through which the package is purchased Package & Procurement Methods PE decides Splitting /Assembling packages Applicability of the Procurement methods considering the nature & size of the procurement , by carefully reviewing the proposed procurement activities & issues BAU:June 16, 2011 PP for SPM 3 Combination of Lot • Items of same nature & generally supplied by a particular group of supplier and normally available in a single shop or in a market. (Computer and Air Cooler should not be in the same lot while scanner, printer and computer should be in a single lot) • Suppliers availability and ability also to be considered BAU:June 16, 2011 PP for SPM 4 Packages Few or More?? Large or Small ?? Arguments in favour of Groupings into Few Large Procurement Packages ►Benefits from economics of scale-achievement of economy & efficiency ►Management aspects ( PE’s capacity to manage the whole project) ►Risk aspect (where failure of a sub-supplier may unduly affect critical path) ►Benefits from participation of large International Tenderers ►Administrative costs of tendering BAU:June 16, 2011 PP for SPM 5 Packages Few or More?? Large or Small ?? Arguments in favour of Splitting into more small Packages ►Time element (procurement items are needed at different times) ►Business structure( some good or services are not available from a single source) BAU:June 16, 2011 PP for SPM 6 Three Initial Steps 1. Categorize procurement into: Goods Works Services 2. Consider time scale and combine into contract packages….. assign a unique Code Number 3. Make packages as large as practicable for improved participation and competition. BAU:June 16, 2011 PP for SPM 7 Packages Splitting of Packages for avoiding particular method or sanction from Higher authority have been prohibited in the Act/Rules But HOPE or AO may approve splitting to smaller packages & lots on justifiable grounds BAU:June 16, 2011 PP for SPM 8 Splitting of Packages PE shall not generally split a Project components with the intention of avoiding either method or the approval of a higher authority ►PE shall not usually split a package into more than five ( 5) lots for keeping cross –discounts application simple ► BAU:June 16, 2011 PP for SPM 9 Splitting of Packages (Contd.) ►PE shall take into account the following aspects for splitting single object of Procurement the capacity of the local & international markets in submitting responsive Tenders the convenience of implementation with due regard to geographical location of sites for potential Works contracts. BAU:June 16, 2011 PP for SPM 10 Packages Classified by category such as Goods, Works and Services Separate for Development Project and Revenue Budget Revenue Budget is not needed for SPM BAU:June 16, 2011 PP for SPM 11 Key Issues ► PE shall arrange to publish the Procurement Plans on their notice boards, and where applicable in their websites & in the websites of the concerned Department or Directorate or organizations, bulletins and reports (PPR- 16.9) ►PE shall, for its own purposes, update the Procurement Plan on a quarterly basis to accommodate delays, re-tendering & other unforeseen changes or constraints (PPR-6.10). BAU:June 16, 2011 PP for SPM 12 Key Issues (contd.) Publication in CPTU website Procurement Plans, above the threshold, specified in Schedule II shall be published in CPTU website on a regular basis (PPR- 16.11). BAU:June 16, 2011 PP for SPM 13 Procurement Scheduling Process Seven Key Steps in preparing the Procurement Plan 1. List objects to be acquired under the Project or Programme, categorizing procurement into: ►Goods (Section 2.16) ( raw materials, products, equipment and objects in solid, liquid or gaseous form, electricity & related services) (readily useable) ► Works (section 2. 6) ( construction, reconstruction, site preparation, demolition, repair, maintenance or renovation railways,roads, highways or building etc. as well as physical services) ► Services (section 2. 24 ) (intellectual & professional services) BAU:June 16, 2011 PP for SPM 14 Procurement Scheduling Process ( cont’d) 2. Consider time scale and determine target dates when each goods or works or services should be ready for use, within the overall project implementation framework 3. Identify Interrelationship between the processing of these procurement objects 4. Decide on the content of Individual Procurement Packages. BAU:June 16, 2011 PP for SPM 15 Procurement Scheduling Process (contd.) 5. Determine the procurement lead times for each package & schedule the target date for each event in the procurement process 6. Prepare Implementation Schedule – Table, Bar Chart or list identifying key dates of each package ( Gantt Chart) 7. Develop a Monitoring System to ensure timely procurement decisions & Implementation follow-up actions. BAU:June 16, 2011 PP for SPM 16 Procurement Plan Formats Procurement Plan has been made an integral part of DPP by the Government. Procurement Plans for the both the Dev and Revenue Project are to be prepared in the Formats prescribed by the Government from time to time. (For SPM World Bank Format as supplied) BAU:June 16, 2011 PP for SPM 17 Total Procurement Plan for Development Project • Identifies: The packages for goods, works and services that are required under the development project. Each procurement package, giving it a unique code and considers the expected cost of the package (as per the PP/TAPP), and The anticipated dates when the procurement package will be supplied BAU:June 16, 2011 PP for SPM 18 Annual Procurement Plan for Development & Revenue Budgets • Time bound PP assists a Procuring Entity to effectively plan its procurement requirements and is an important and useful tool used to monitor the progress of procurement BAU:June 16, 2011 PP for SPM A. to ensure that it does not go astray; B. to ensure that early problems with slippage can be dealt with promptly; and C. can form a useful Annual Plan for procurement. 19 Procurement Methods •PPA section: 31-34 •PPR: 61-62, 69,74,83, & 103-104 BAU:June 16, 2011 PP for SPM 20 Frequently used Proc Methods for Goods & Works • OTM (Open Tendering Method) (PPR-61) (WB term it National Competitive Bidding ) • ICB (International Competitive Bidding) (International Tender) (PPR-83) • RFQ (request for Quotation) (PPR- 69) • Direct Contacting (Direct Cash Purchase and Others methods) (PPR- 75) NCB BAU:June 16, 2011 PP for SPM 21 Proc Methods for services frequently used by SPM • CQ (Consultant Qualification) (normally firm) (PPR-108) • IC (Individual Consultant) (PPR-112 ) • FBS (fixed Budget Selection) (PPR- 106) • LCS (Least Cost Selection) (PPR-107) • QCBS (Quality Cost Based Selection) (PPR- 105) BAU:June 16, 2011 PP for SPM 22 Procurement Plan Format Column 4: Unit (unit of measurement) Goods: Numbers, Pieces, Liter, meter, Lot etc Works: Cubic Meter, Square meter, Lump sum etc Service: Staff Months, Days, Hours , lump sum etc BAU:June 16, 2011 PP for SPM 23 Procurement Plan Format Column 10: Planned Date of Bid opening (Actual Date of Bid Opening) • We are to follow the provision PPR-61(4), 64(5) 71(4) and 83 (1) (ka) • Time from publication of invitation to bid opening depends on threshold and proc methods BAU:June 16, 2011 PP for SPM 24 Procurement Plan Format Column 11: Planned Date of Contract Signing (Actual Date of signing) • Signing of Contact depends not only on PE but also on the Supplier/ contractor/ Consultant. • Period of Evaluation, approval by the proper authority, issuance of NOA, Suppliers acceptance, Submission of performance security, are the factors to be considered BAU:June 16, 2011 PP for SPM 25 Procurement Plan Format Column 12: Planned Date of Completion (Actual date of completion) • It depend on the Size/ Quantity/ Volume/ market situation/suppliers ability/ urgency/ weather/transport facilities/availability of funds and so many things. We are to consider all these. BAU:June 16, 2011 PP for SPM 26 World Bank Format for PP Sl Contact No Package No 1 2 1 G-1 Contact Description 2 G-2 Printing of Lab Operation Manual 3 G-10 Printing Quarterly Newsletter BAU:June 16, 2011 3 Supply of a microbus World Bank Format for PP Sl. No Contact Description 1 Contact Package No. 2 W1 2 W2 3 W3 Construction of two latrin for female students Repair of laboratory room of Physic dept 1 BAU:June 16, 2011 3 Sand filling to play ground World Bank Format for PP Sl. Contract No package No. 1 2 1 S1 Contract description 2 S2 Selection of local partnership for network design and implementation 3 S3 Selection of Digital Library specialist BAU:June 16, 2011 3 Website dev and maintenance for BUD World Bank Format for PP Unit Quantity/ Estimated numbers cost (Actual Contract Price) Procure ment Method Procure ment Guidelin e (PPA/BG) 4 Unit of measu rement 5 1,5,3 etc 6 US$ BDT. 7 8 OTM/ICB/ PPA/ RFQ/CQ/ IC etc BG BAU:June 16, 2011 World Bank Format for PP Prior Planned Date Review of Bid (yes/no) opening/ Proposal Submission (Actual date of Bid opening/ ) 9 BAU:June 16, 2011 10 Planned Date of contract signing (actual Date of contract signing) Planned Date of Delivery/ completion (actual date of delivery/ completion 11 12 Miscellaneous • Basic principle is not to be adopt any ill tactics • Keep budget provision for honurium • Training and foreign visit not to be included in planning • Lump Sum Contract: A contract for the performance of a specified amount of work by a specified date for a sum established in advance BAU:June 16, 2011 PP for SPM 32 Queries ?? • If you have any query please do not hesitate to contact HEQEP procurement unit Procurement specialists and procurement officers are always ready to response your queries. BAU:June 16, 2011 Thanks. Md. Alamgir Hossain Procurement Officer HEQEP Phone: 01819567424 Email:alamgir4158@yahoo.com BAU:June 16, 2011 PP for SPM 34