SAIMM Technical Presentation 15 July 2010 Index • Vision and Positioning • APMOT Production Module at a glance – – – – Standard level and block Geology Scheduling Levelling – Team Sharing • Costing Module – Approach – Rules • Case Studies MRM What is APMOT? • Anglo Platinum Mining Optimisation Tool – APMOT was developed for Anglo Platinum and is a nongraphical rules based production scheduling solution that allows a full production schedule to be done very quickly. – In this way many different mine design and production assumptions can be tested and the impact compared. • The APMOT solution also includes a financial module that calculates activity based costs and labour as well as valuations for the given schedule. MRM APMOT Vision A solution that allows rapid generation of a reliable production schedule and associated economics so that multiple options/scenarios can be considered and thereby determine the ‘optimal’ deterministic schedule. This required a solution that had: • Enough flexibility and speed to study multiple options • Evaluation of grade at an acceptable level of confidence • Linking Labour and other costs to the production schedule to allow true activity based costing • Incorporating costs and capital to allow NPV optimisation • Incorporating Global Assumptions to allow trade-off’s • Allow iteration and dynamic changes without required re-work • Allow checking against constraints to ensure the production profile is realistic, these should include: – Ventilation – Men and material logistics – Scraping, tramming and hoisting constraints MRM APMOT Positioning Short term Long term Business Plan Program MES Options Top Down Goals Tons and Ounces Business Plan Budget Iteration APMOT PM Trade Offs and Options Cadsmine Project Stage Gates Desktop – L3 MRM Scoping – L2C Pre-Feasibility L2B Feasibility – L2A Execution – L1E Operations – L1 APMOT Positioning Short term Long term APMOT PM Operations Scheduling Business Plan Program Cadsmine MES Options MRM Top Down Goals EssBase Tons and Ounces Budget Group Value Optimisation Iteration Business Plan APMOT Positioning Short term Long term APMOTBudget PM Driven by and Iteration Asset Optimisation linked to Cadsmine profile Optimisation proven in APMot before incorporation in plan Cadsmine MES Options Top Down Goals Iteration APMOT Labour and Costs Business Plan Program Tons and Ounces APMOT - Projects Labour and Costs APMOT PM Trade Offs and Options Project costs feeds Opexand modelling into short long already done for term plans projects Cadsmine Projects MRM Business Plan Budget APMOT Positioning Short term Long term APMOT PM Operations Scheduling APMOT PM Asset Optimisation Group Value Optimisation APMOT Labour and Costs Cadsmine MES Options Top Down Goals EssBase Tons and Ounces Business Plan Budget APMOT - Projects Labour and Costs APMOT PM Trade Offs and Options Cadsmine Project Stage Gates Desktop – L3 MRM Scoping – L2C Pre-Feasibility L2B Feasibility – L2A Execution – L1E Operations – L1 Summary APMOT Positioning Current Ops Geological Representation Mine Design & Layout New Projects Activity Scheduling Production Plan Costing, Labour Comps & Valuation Variance Tracking Short Term Budget 5Yr & Life of Mine Plan (BUDGET CREATION) A C Asset Level Performance Management T U (BUDGET MANAGEMENT) A Multiple plans from multiple operations L S Group Valuation & Long Term Strategy MRM Industry Dynamics Simulation Portfolio Level Performance Management MRM APMOT – A Half Level as a series of Blocks of Ground A standard half level and block Half-level 1 EAST Drive to Reef •Standard Half Level - An area containing all the mining activities from the apex either east/west or north/ south on a level •Standard block - TheGeological smallest self-contained production unit encompassing development, losses ledging, equipping, stoping and sweepings, vamping and reclamation. Half-level 2 EAST Shaft MRM 1 2 Raise Line Back length Foot Wall Drive Block Width 3 4 5 APMOT - Standard Block for Scattered Breast Standard Block All Block Dimensions are on strike and dip Block Length on Dip Raise Line Foot Wall Drive Cubbies Travelling Way Dip Step over Block Width on Strike MRM Dilution Calculation – Placement of Excavations MRM Scheduling MRM Scheduling Window MRM Natural Schedule 36 000 2021 MRM Team Sharing Choose what to level Choose which excavations to include and assign priorities Choose which levels, half levels or blocks to include and assign priorities MRM Team Sharing – “Levelling” With team sharing it is possible to introduce constraints and priorities for: – Any mining activity – Limit the number of drop-raise crews • Easy to demonstrate that one crew is enough on average, but two crews are too little to meet the proposed stoping schedule – multiple drop raises may be required simultaneously. – Include different excavations, only flat development, all development, on reef only, haulages only. – Assign priorities, haulage never stops, or on-reef always takes precedence. – The above configuration can be applied to any portion off-, or the whole mine. – Areas of the mine can be prioritised • Shaft over-stoping higher priority • Big strike levels higher priority for tail management • Each half level can be levelled individually, or a global levelling can be done. MRM Levelled Schedule 17 500 2021 MRM Activity Based Costing Shaft Head OPEX Total Cost Categories Engineering Services Direct Mining Cost Activities UES MTS Stoping Sundries Stores Utilities Cost Resource Explosives Drill Steel Mechanical Spares GL Data GL Entries GL Entries GL Entries Cost Elements MRM Labour Contractors Data Modelling Detail Desktop ± 30% Concept ± 25% High-level Data High-level Data Benchmarks Previous appropriate and applicable study results Modelling High-level modelling Extrapolation Tonnage and m2 profiles only Assumed Fixed Variable Splits No Labour Modelling MRM Pre-Feasibility ± 15% Feasibility ± 10% Historical SAP GL Data Historical SAP GL Data First Principal and Zero-Based Costing First Principal and Zero-Based Costing if Team efficiencies, Salary and L&A data Team efficiencies, Salary and L&A data Team Costs and Team Efficiencies Designations and team composition Designations and team composition Variable and flat labour modelling of teams Labour modelling per designation Detailed Analysis of Cost Drivers Assumed Fixed Variable Splits Assumed Fixed Variable Splits Actual Fixed Variable Cost Splits Tonnage and m2 profiles only Detailed APMOT schedule Detailed CADSMine schedule Escalated Historical Costs Define Activities, Sub-Activities and Resources Define Activities MRM Labour Modelling - Labour Rules Rule Type Fixed Labour Labour driven by production Labour driven by infrastructure Labour driven by Labour Labour driven by Operation span Labour driven by step functions Example: Production Manager Stoper Belt Attendants Supervision Surveyors Boiler makers • Rules can be embedded “if” and conditional statements • These types of rules are derived and validated per designation, per activity, per entity • Labour in essence is derived from first principles. • For Concept and Desktop studies, Labour teams are modelled as either fixed teams for LoM or 100% variable with production. The approach can be summarised as follows: Derive team from designation list Compile cost per team Decide on Fixed or variable Process followed per activity, per entity Apply drivers to team cost and counts MRM Define Labour Structure Customized Job Grade Definitions MRM Define Labour Rules Define Rule that drives number of teams MRM Standard Reporting MRM Example Pivot Report MRM Case Study 1– Mothballed shaft Re-Evaluated • Questions/Concerns regarding 2007 planning – Production levels were too low to justify the overhead costs. – There was uncertainty regarding the ramp up period and desired level of production. – Since there were several levels with limited remaining production, it was not clear for how long any particular production level could be maintained. – There were opinion differences regarding suitable crew efficiencies. – Previous scheduling resulted in a large unprofitable tail. • The Mining Engineer was tasked to: – Determine a suitable production level. – Schedule an appropriate ramp-up period. – Evaluate the impact of using several different crew efficiencies – was there enough face length for additional crews? – Optimise the tail. MRM Case Study 1– Mothballed shaft Re-Evaluated Development completed Details of Scheduling durations for selected activity Details of delays in selected activity - Raise MRM Case Study 1– Mothballed shaft Re-Evaluated Peak of 36 000m² Levels with little mining remaining Separate Decline Long life levels Higher grade MRM Case Study 1– Mothballed shaft Re-Evaluated 18 000 m² can be maintained Second decline as replacement Once the model has been built it is easy to iteratively: •Change crew efficiencies to a consensus level and check the impact on production level and costs •Improve the grade model for more accurate ounces Higher grade up front – close of levels •Change the sequence of mining or add additional construction, equipping or capital activities. Long life levels as base MRM Case Study 2 – Improving a business case in a capital constrained environment • Two decline shafts ramping up to 3 million tons annually from 9 levels each. • It was requested to: – Reduce or postpone capital. – Reduce costs. – Reduce perceived risks due to the development and stoping rates. • This translated into the following options which would be modelled in APMOT: – Reducing the number of levels from 9 to 7, thereby reducing capital and working cost development. – Consider the effect of reduced development rates on each option – Consider the effect of reduced stoping rates on each option. MRM Case Study 2 – Improving a business case in a capital constrained environment • The following were built in APMOT – 6 options were scheduled depicting all the permutations of • high/conservative development rates • high/conservative stoping rates and • 7/9 levels 2# and 1# separate - Tons to Concentrator stockpiles 1# - Option 1 - 7 levels Conservative Dev & 360 m2 / team steady state 2# - Option 1 - 7 levels Conservative Dev & 360 m2 / team steady state 1# - Option 1 - 7 levels Dev matched to IP & 422 m2 / team steady state 2# - Option 1 - 7 levels Dev matched to IP & 422 m2 / team steady state 1# - Base Case -9 Levels Dev matched to IP & 422 m2/team steady state 2# - Base Case -9 Levels Dev matched to IP & 422 m2/team steady state 1# - Base Case -9 Levels Conservative Dev & 360 m2/team steady state 2# - Base Case -9 Levels Conservative Dev & 360 m2/team steady state 1# - Option 1 - 7 levels Dev matched to IP & 360 m2 / team steady state 2# - Option 1 - 7 levels Dev matched to IP & 360 m2 / team steady state 1# - Base Case -9 Levels Dev matched to IP & 360 m2/team steady state 2# - Base Case -9 Levels Dev matched to IP & 360 m2/team steady state MRM 2010 45,784 56,580 45,784 56,580 45,784 56,580 45,784 56,580 45,784 56,580 45,784 56,580 2011 54,409 85,867 56,553 86,281 56,553 86,281 54,409 85,867 56,553 86,281 56,553 86,281 2012 78,515 32,221 84,324 36,113 84,324 36,113 78,515 32,221 84,324 36,113 84,324 36,113 2013 227,937 192,023 300,033 248,400 312,042 253,059 219,414 179,412 255,428 215,163 245,539 198,964 2014 345,032 361,823 396,180 378,740 456,191 403,159 338,128 310,124 351,756 358,945 346,710 307,218 2015 2016 452,227 793,647 460,926 796,329 415,030 645,395 476,544 800,690 729,593 1,075,770 676,281 1,004,964 560,558 841,413 515,019 793,461 457,745 789,057 454,110 822,788 567,446 853,383 507,035 779,263 2017 1,092,409 994,215 808,475 969,468 1,392,773 1,351,056 1,106,360 1,123,555 1,090,929 1,114,130 1,112,016 1,069,460 2018 1,387,747 1,085,413 1,343,412 1,034,501 1,546,590 1,558,314 1,352,226 1,292,902 1,355,466 1,334,998 1,360,574 1,245,888 2019 1,509,831 1,370,173 1,555,900 1,272,995 1,549,921 1,603,168 1,462,678 1,477,350 1,473,196 1,521,670 1,514,583 1,395,165 2020 1,554,618 1,527,897 1,582,107 1,459,282 1,477,998 1,591,851 1,499,117 1,606,170 1,496,178 1,545,882 1,552,602 1,498,622 2021 1,481,034 1,485,513 1,445,173 1,530,394 1,493,278 1,498,428 1,537,870 1,553,778 1,451,927 1,525,431 1,599,923 1,553,505 2022 1,429,629 1,455,603 1,456,824 1,472,842 1,547,230 1,503,356 1,491,420 1,531,514 1,379,627 1,480,837 1,564,803 1,556,349 Case Study 2 – Improving a business case in a capital constrained environment Option Studies with backlength and Dev and stoping efficiencies Ramp Up section of 2# & 1# combined 3,500,000 3,000,000 Tons (TCS) 2,500,000 2,000,000 1,500,000 1,000,000 500,000 2010 MRM 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 Option 1 - 7 levels Conservative Dev & 360 m2 / team steady state Option 1 - 7 levels Dev matched to IP & 422 m2 / team steady state Base Case -9 Levels Dev matched to IP & 422 m2/team steady state Base Case -9 Levels Conservative Dev & 360 m2/team steady state Option 1 - 7 levels Dev matched to IP & 360 m2 / team steady state Base Case -9 Levels Dev matched to IP & 360 m2/team steady state 2023 Case Study 2 Conclusions • The 7 level option ramps up 1-2 years slower than the 9 level option. • Regardless of the production rates, it was possible to man to full production. • The higher development rates yielded slightly higher total annual production. • The lower stoping rates had less of a tail. This allowed an informed decision to be made regarding the postponing or reducing of capital and the impact of these decisions on the business case of the project. MRM Case Study 3 – Decline position • A decision had to be made regarding the position of a decline for the next phase of a project. Additional considerations were: – – – – – MRM Mining through a major fault Total strike length and length of conveyors Production in the tail Capital required Surface infrastructure required Case Study 3 – Decline position • 9 Different models were scheduled and costed in APMOT • The results showed that: – – – – MRM Capital estimates did not vary significantly across the options. Cost were impacted by the duration that a steady state could be maintained There were not any great variances in working cost rates. Option 1,3,5,8,9 were chosen to be optimised further at a higher total volume. Case Study 3 • Improving the production rates and volume of mining resulted in: – Significantly better tail management with the total mine maintaining the higher volume of production. – Life of mine was shortened by 5-6 years. – Significantly increased NPV. – This allowed the option with the best NPV to be put forward with confidence. – Upside and downside scenarios could be quantified through actual scheduling and the impact evaluated in the cost model. – All work was completed within a three month period. MRM Trade-Off Between Time and Level of Detail. - Level of Detail of Input Variables + - Time Axis + Low Level of Detail – - Hand Drawn Mine Design or existing design - Large single Geozones - Average Grade - Standard Block Sizes - High Level Activities i.e. Stoping, on-reef dev and off reef dev - Can replicate scheduling to all blocks - No Significant Data gathering required Feasibility Time – 2 to 3 weeks per unique option including data Pre-feas Time – 1 to 2 weeks per unique option including data Concept Study Time – 3 days to 2 Week per unique option including data Desk Top Study Time – 1 day to 1 Week per unique option including data MRM Current Operations 39 High Level of Detail– - Detailed Mine Design - Individual Geozones - Grade per horizon per geozone - Individual block sizing - Detailed Activities i.e. stoping, ledging, equiping, FWD, breakway etc - All activities scheduled - Replication of schedule to blocks in same Geozone and design - Significant data gathering required Conclusions In conclusion APMOT has achieved the following for Anglo Platinum: • Ability to produce a production schedule for a particular mine design within days to weeks depending on level of detail. • Therefore the generation of multiple production options and production schedules to determine ‘optimal’ that meets strategic objectives required. • Quick adjustment of schedule to test different ‘what-if’ scenarios (change team efficiencies, back lengths etc). • Linking of economics to the production schedule (activity costs, labour complements, revenue, profit and value). Anglo Platinum are now able to rigorously test different production strategies and optimise the mine design and schedule within the constraints defined. MRM Thank you and Questions Thank you to the SAIMM for this opportunity to do this presentation and expose to other mining houses the work that we are doing to improve our mining business. Questions? MRM