Sellafield Commercial Opportunities 2014 Presented by David Magrath and Rob Harries-Harris 12 June 2014 Agenda Introduction Sellafield Strategy Procurement Plan Overview Key Procurements – – – – – Decommissioning Major Projects Operations Collaborative SME Opportunities Wrap and Summary Questions 08 April 2015 2 Sellafield Strategy Overview of the Plan Safety and Quality Excellent Relationships – Collaboration/Partnering Early Market Engagement SME & Socioeconomics Category Management Logistics Development of Capability and Capacity 08 April 2015 4 Forecast Supply Chain Spend PP14 08 April 2015 Demand and Supply Constraints Source: NIA Supply Chain Capability Report Dec 2012 08 April 2015 Decommissioning at the Sellafield Site Legacy Ponds & Silos Pile Fuel Cladding Silo Pile Fuel Storage Pond Magnox Swarf Storage Silo Remediation Portfolio First Generation Magnox Storage Pond Sellafield Site Decommissioning Strategy • Decommissioning Strategy being developed to support these activities: – – – – Aligned with Sellafield Limited strategy Considers and drives integration more strongly Develops a “decommissioning mindset” Sustainable, balanced portfolio of work • Decommissioning Mindset – “What would we do differently if we knew our hazardous facilities were certain to fail tomorrow?” – transition in working culture to become empowered to deliver bold, but simple solutions to specific issues and work in partnership to significantly accelerate high hazard reduction. Decommissioning Delivery Partnership (DDP) • Update – Internal preparations of PQQ well advanced – Waiting on approval from ND – Estimated 30th June 2014. Webinar: 1st July 2014 • • Lot structure: Lot 1 – SR&DP, PFSP, PFCS & other sitewide demanders – 3 - 5 awards – Collaborative Framework • Lot 2 – FGMSP – 1 award – Delivery Partner • Lot 3 – MSSS – 1 award – Delivery Partner Transition Plan & Initial Mobilisation PQQ Assessed NDA Approval IRP Expiration of MDSW ITT Contract Award PQQ Full Transition to DDP We are here April-14 June-14 June-14 Sep-14 Nov-14 Jul-15 Jul-15 Mar-17 08 April 2015 Mar-17 9 Decommissioning - Sellafield Box Procurement Project (SBBP) • Early engagement work – manufacturer visits, industry days • Pre Qualification Questionnaire (PQQ) high number of responses received – short listed in line with Contract Notice range • ITT issued 31st Jan 14, responses received 22nd April 14 • Initial tender assessment complete, clarifications underway • Practical assessment of tenderers capability commenced June 14 (Weld Test) • Tender assessment to be concluded by the beginning of Aug 14 • Contract placement on programme for Dec 14. 08 April 2015 10 Major Projects Box Encapsulation Plant (BEP) Scope EPC (Engineering, Procurement, Construction of a Box Encapsulation plant Duration and Value £200 – 250m Key Dates Plan Award March 2015 – working to an accelerated programme Current Position ITT due for return in July 2014 Major Projects SIXEP Contingency Plant • Site Ion Exchange Effluent Plan (SIXEP) – – – – • • • • High volume, low-medium beta active effluent abatement service Nearing end of design life SIXEP Contingency Plant – mitigate risk of failure Required to be operational by 2024 Early stage of project life ITT August 2016 (Current forecast) Contract Award March 2017 – EPC scope (Current forecast) Estimated £100M – £250M Operations Fellside Combined Heat and Power Plant Scope Fellside CHP Operations and Maintenance Duration and Value £75 -100m Key Dates Contract Award Nov 2015 Current Position Acquisition Strategy being finalised 08 April 2015 13 Operations SSEP – Police Firing Range Scope Design and Build of a replacement police firing range Duration and Value £25-50m Key Dates Contract Award November 2016 Current Position Acquisition Strategy being finalised 08 April 2015 14 Operations/Projects Supply Agreement – Overhead Cranes Scope Design, Supply Install and Commission Overhead Cranes Duration and Value Five years +£100m + Key Dates Contract Award September 2015 – trying to accelerate Current Position Business Case approval in July 2014 - ITT 08 April 2015 15 Support/Collaborative Commercial and Project Controls Strategic Partner Scope Provision of Commercial/QS and Programme Controls Services Duration and Value Ten years ~ £200-250m Key Dates Contract Award June 2015 Current Position ITT in preparation 08 April 2015 16 Support/Collaborative Agency Supplied Workers Scope Provision of Agency Supplied Workers (ASWs) across the NDA - skill range Admin to Technical Duration and Value Five Years Up to £700m Key Dates Contract Award October 2015 Current Position Early Market Engagement 19 June 2014 08 April 2015 17 Support/Collaborative Personal Protective Equipment Scope Supply and delivery of Radiological and conventional PPE – NDA Estate Wide Duration and Value Four Years ~ £10 -25m Key Dates Contract Award August 2015 Current Position Strategy to supply through UKSBS Agreement 08 April 2015 18 SME Target Opportunities 08 April 2015 19 Summary & Questions? 08 April 2015 20