Developing a Decommissioning Acquisition Strategy for 2014-26 Paul Foster, Decommissioning Director Rob Harries-Harris Contract Officer, Commercial Directorate Date: March 2013 2 Agenda • Background • Principles Underpinning the Future Model • Enablers 3 Orientation - Where are we now? • The Sellafield Plan – an accurate and realistic picture of the state the site is in – sets out what we are doing to reduce hazard, with milestones and governance in place to enable the NDA to monitor our progress and hold us to account – risks to the plan remain but we are currently on target to deliver decommissioning milestones 4 Key Deliverables 2014/15 to 2025/26 • • • First generation magnox storage pond – sludge retrievals begin in 2014/15, export of fuel and skips in 2015/16 – bulk desludging complete by 2018/19 Pile fuel storage pond – bulk desludging and metal fuel export complete in 2014/15 – local sludge treatment plant export complete 2017/18 Pile fuel cladding silo – • • retrievals begin in 2017/18 Magnox swarf storage silo – retrievals targeted to start 2016/17* – residuals removal to begin no later than 2023/24* Site remediation and decommissioning – Ongoing hazard reduction and decommissioning across SRDP portfolio throughout contract term Source: Sellafield Plan Aug 2011 * subject to confirmation 5 Areas for Improvement • Public Accounts Committee Concerns: • • • • Planning and schedule adherence Programme and project management capabilities Collaborative working to package resources Robust performance management • Other bodies, including NDA: – Identify SL’s historical contracting model as a priority development area • some weakness in capacity and capability of supply chain • SL does not always strategically think through and establish a model for core and non core capability • SL does not always adopt a strategy for best value and performance (including schedule assurance) maximising available supply chain capability and capacity 6 Our Challenge: Clear focus on outcomes From … • • • • • • • • • Short term contracts Price driven Control vs quality Mini-competitions Short term plans Itinerant workforce Inefficient Ineffective Adversarial ... To • • • • • • • Longer contracts Focus on benefits Built in quality Benchmarked costs Long term vision Develop resources Collaborative OUTCOME • Accelerated hazard reduction • Fit for purpose assets • Access to resources • Economic operations Engagement to Develop and Implement the Strategy • 18-24 Month Engagement Process begins today • Next 6 months will be vital • SL commitment to engage constructively with Supply Chain at all levels • Your contributions are invited • Early contractor involvement in programme and project cycles 8 Strategic Context NDA OJEU, etc. UK & Local Government Commercial SLCs 22 & 35 Over-Arching Acquisition Strategy Supply Chain Special Arrangements Technical R&D and Strategy Decommissioning Acquisition Strategy FGMS P DFA Major Projects Innovation ISA PFSP MSSS Benefits Production Operations PFSS W’scal e SR&D P Learning From Experience MDSW DSA Infrastructure 9 Simplified Engagement Structure Decommissioning Programme Management FGMSP PFSP MSSS PFSS W’scale SR&DP Make v Buy Decomm Delivery 4P/Major Projects Current Arrangements DSA ISA MDSW/Other 10 Effective Planning at All Stages Reactive Work Planned Work 11 Collaboration/Sharing Enablers • Share Information • Share Risks not Responsibilities • Share Benefits – Keep savings on at risk elements – Share savings on variable cost elements – Innovations benefit client and innovators • Align objectives through strong incentives 12 Supply Chain Assurance • SL is Tier 1 contractor and must manage the performance of its supply chain – This requires visibility, oversight and governance of Tiers 2/3/4 performance: • Safety, Health and Environmental • Time, Cost, Quality • Wider government agenda, SME and Socio-Economic issues – Desired Outcomes • • • • Accelerated hazard reduction Fit for purpose assets Access to resources Economic operations 13 The Opportunity • Longevity – A programme of work lasting up to 10 years • Scale – up to £700m of work between 2014/15 and 2025/26 14