Transportation Systems Management & Operations – Capability Maturity Implementation Plan New Jersey Department of Transportation Transportation Systems Management (TSM) (Division of Traffic Operations and the Division of Mobility and Systems Engineering) » Final Implementation Plan • Selected Priority Action Items 1 Transportation Systems Management & Operations – Capability Maturity Implementation Plan Business Processes (Planning and Programming) Priority Action 1of 3 Action Description Develop The Connected Corridor (TSM&O) Plan Products: The Connected Corridor – NJDOT TSM&O Plan The NJ ITS Architecture Update and ITS Strategic Deployment Plan has been branded The Connected Corridor. It serves as the NJ statewide TSM&O Plan authorized by the NJDOT with stakeholders including non-NJDOT, Authorities, local agencies, MPOs, and other partners. Products and Desired Outcomes: Establish Vision, Objectives, and Strategies in the short and Long Term Desired Outcomes consistent with identified regional planning goal areas. Objectives and related strategies supported by performance measures establishing a performance based approach to planning and ultimately strategic capital investment. Result in system-wide, performance-based, innovative, and mode neutral investments, with operational strategies and technology solutions integrated into the planning processes, and chosen over traditional infrastructure projects in capital programming. Completion and acceptance of The Connected Corridor (NJ’s TSM&O Plan) to include the program maintenance and Implementation Plan. Also, develop business case and communications plans consistent with NJDOT’s congestion relief and problem statement development processes. Task(s) / Subtask(s) Promote private sector engagement through organizations like ITS America and ITS NJ to promote delivery to the customer. (continued on next slide) 2 Transportation Systems Management & Operations – Capability Maturity Implementation Plan Business Processes (Planning and Programming) Priority Action 1 of 3 (continued) Action Objective Develop The Connected Corridor (TSM&O) Plan Lead Solomon Caviness, NJTPA “The Complete Team” (including NJDOT TSM, Planning, Programming, MPOs, FHWA) Operating Agencies, Counties, NJ universities, ITS NJ, TRANSCOM (with strategic participation Support Staff from agencies so that the overall number of participants is limited to drive accountability and responsibility). 4 months to finalize The Connected Corridor – approximately a dozen people at about 10% Staff Level of Effort) time – approximately 100 person hours. Senior Leadership Commitment to goals, liaison with external executive stakeholders, product guidance and Support Actions promotion, assignment of staff, briefing availability, schedule prioritization and management. Incorporate input from stakeholders into The Connected Corridor. 4 Plan meetings, approx. Collaboration one per month, among key support staff identified above. Requirements: Plan is applicable Actions and across Federal, State, County, Municipal and Regional jurisdictions, including TRANSCOM. Requirements Establish The Connected Corridor partnership and implementation MOU. Technical Issues How we share information across agencies, various communications platforms, use of virtual meeting opportunities, cross agency policy consistency and conformance (standards). (continued on next slide) 3 Transportation Systems Management & Operations – Capability Maturity Implementation Plan Business Processes (Planning and Programming) Priority Action 1 of 3 (continued) Action Objective Develop The Connected Corridor (TSM&O) Plan Key staff availability, continuity of program, keeping a focused vision and long term commitment to seeing this through. Funding continuity and constraint. Finding appropriate leadership for The Key Risks Connected Corridor. Plan acceptance at executive level. Failure to meet customer demands and needs. FHWA Planning for Operations technical assistance, CMM Workshops, Example TSM&O Plans Resource from other regions and State DOTs, and Travel Assistance for identified TSM&O Peer Exchanges Requirements and SME support. FHWA Support TSM&O training opportunities for NJ Local Implementation Plan Team Resource FHWA NJ Division – Calvin Edghill and Ek Phomsavath Start Date June 1, 2014 End Date September 30, 2016 Completion and Cross Acceptance of The Connected Corridor Plan. Support for ongoing Success / Completion partnership and implementation MOU. Shared vision and momentum for next steps. Acceptance Indicator and first meeting of The Connected Corridor maintenance initiative. 4 Transportation Systems Management & Operations – Capability Maturity Implementation Plan Business Processes (Planning and Programming) Priority Action 2 of 3 Action Description Develop a Business Case Document for TSM&O Products: The Connected Corridor Business Case Desired Outcomes: Identify programs/projects for investment and deployment as per The Products and Connected Corridor strategic plan. Link project objectives with MPO and FHWA Goal Areas. Desired Outcomes Measure the results as outcomes/benefits for success stories (i.e. Statewide Traffic Management Center, TRANSCOM) to promote as tools for strategic investment. Project and program outcomes and results document easily translatable to executives, private sector, and the customer/public. Write a Business Case. Develop a Team that focuses specifically on measuring project and program outcomes and results to document success stories to support this Case. This Team would include MPO and Agency Ops staff knowledgeable in performance and operations investment. Task(s) / Subtask(s) Use CMM/AASHTO Presentation Template. Include work done by John Allen and others. (continued on next slide) 5 Transportation Systems Management & Operations – Capability Maturity Implementation Plan Business Processes (Planning and Programming) Priority Action 2 of 3 (continued) Action Objective Develop a Business Case Document for TSM&O Lead Solomon Caviness, NJTPA John Ward-DVRPC, Dave Heller-SJTPO, MPOs, John Allen-NJDOT Planning, Walter Kraft-VHB, Support Staff Steven Dilts-CH2M Hill, Tom Batz-TRANSCOM Staff Level of Effort) Assume about: 1 day per week over 3 months for 6 persons =72 person days Commitment to completion of Business Case, liaison with external executive stakeholders, Senior Leadership guidance and promotion, assignment of staff, briefing availability, schedule prioritization and Support Actions management. Shared vision, consistency across agencies, and 2 milestone meetings. Collaboration Actions and Requirements FHWA to monitor process, collaboration and input with stakeholders. Technical Issues (continued on next slide) 6 Transportation Systems Management & Operations – Capability Maturity Implementation Plan Business Processes (Planning and Programming) Priority Action 2 of 3 (continued) Action Objective Develop a Business Case Document for TSM&O Schedule, failure to make a case that translates well across different audiences, exclusion of key players, and lack of connection with public benefits. Key Risks FHWA Planning for Operations Workshops & CMM Workshops, AASHTO’s SSOM Resource Committee, ITS America and ITS NJ, Peer Exchanges, and Participation at TRB’s TSM&O Requirements Committee Meetings. FHWA Support FHWA Technical Resources (website) Resource FHWA NJ Division – Calvin Edghill and Ek Phomsavath Start Date June 1, 2014 End Date May 12, 2015 Final document that translates well across multiple audiences. 2 briefings (Executive leads). Success / Completion Business Case able to be linked with The Connected Corridor (NJ TSM&O) Plan. Indicator 7 Transportation Systems Management & Operations – Capability Maturity Implementation Plan Business Processes (Planning and Programming) Priority Action 3 of 3 Action Description Develop and implement a Communications Plan Executive and Public Document. Include an electronic brochure with a roll out program for Products and acceptance and endorsement. Desired Outcomes Write a Communications Plan that explains, justifies, and builds support for Technology enterprise. Develop a Team that focuses specifically on a communications strategy that translates well across multiple audiences that explains benefits of technology and operational strategies. Fundamental review and documentation of Best Practices in communicating operational strategies. Use CMM/AASHTO Presentation Template. Include Task(s) / work done by John Allen and others. Subtask(s) (continued on next slide) 8 Transportation Systems Management & Operations – Capability Maturity Implementation Plan Business Processes (Planning and Programming) Priority Action 3 of 3 (continued) Action Objective Develop and implement a Communications Plan Lead Branislav Dimitrijevic, NJIT Support Staff NJDOT TSM, NJDOT & MPOs Communications staffs Staff Level of Assume: 1 day per week over 8 weeks for 6 persons = 48 Person Days Effort) Endorsement and engagement of key communications personnel. Commitment to Senior Leadership completion of Communications Plan, liaison with external executive stakeholders, Support Actions guidance and promotion, assignment of staff, briefing availability, schedule prioritization and management. Collaboration 2 Meetings. Plan should be able to be presented across various platforms, including social Actions and media. Development and circulation of draft document to key communications directors Requirements and executive management. Establishment of electronic site. Shared vision, consistency across agencies, document written in “plain English” easily understand and able to connect with multiple audiences (i.e. public, freight providers, Technical Issues emergency management). (continued on next slide) 9 Transportation Systems Management & Operations – Capability Maturity Implementation Plan Business Processes (Planning and Programming) Priority Action 3 of 3 (continued) Action Objective Key Risks Develop and implement a Communications Plan Schedule, deviation from message, and continuity. FHWA Planning for Operations Workshops & CMM Workshops, AASHTO’s SSOM Resource Committee, ITS America and ITS NJ, Peer Exchanges, and Participation at TRB’s TSM&O Requirements Committee Meetings. FHWA Support FHWA NJ Division – Calvin Edghill and Ek Phomsavath Resource Start Date September 1, 2014 End Date September 30, 2016 Press Event, agency presentations to executive management, executive endorsement, plan Success / Completion for regular and consistent communications with multiple audiences – key stakeholders, Indicator decision makers. 10 Transportation Systems Management & Operations – Capability Maturity Implementation Plan Systems and Technologies Priority Action 1 of 2 Seek/study national best practices regarding State DOT IT-related procurement issues and propose improvements. Protocols/understanding established between NJDOT(NJDOT (IT and TSM) and NJOIT to streamline processes as it relates to IT/ITS procurement, security, differing agencies Products and priorities, telecommunications, personnel/staffing, etc., to improve the Desired Outcomes relationship/coordination between NJDOT/NJOIT and to strengthen the TSM Programs. Action Description 1. 2. 3. Task(s) / Subtask(s) 4. 5. 6. Research national best practices and summarize information. Have a high level meeting with DOT (IT and TSM) and OIT to discuss what is working well, what is not working well, review national best practice, outline recommendations, and designate a champion from each agency. Champions meet to detail the recommendations and meet with high levels from DOT (IT and TSM) and OIT to gain concurrence. Formal announcements of recommendations are distributed in each agency. Recommendations are implemented based on an accepted schedule. Champions review the processes every six months and make changes made for improvement. (continued on next slide) 11 Transportation Systems Management & Operations – Capability Maturity Implementation Plan Systems and Technologies Priority Action 1 of 2 (continued) Seek/study national best practices regarding State DOT IT-related procurement issues and propose improvements. Lead Walter Kraft (VHB) Action Objective Support Staff OIT and DOT(IT and TSM) organizational support plus outside support, if needed. Staff Level of Effort) Senior Leadership Support Actions One month to research national best practices (80 hrs). One week for peer to peer meeting with other successful programs (40 hrs). Three months effort for initial meetings and develop the recommendations (160 hrs). Two months to implement the recommendations (120 hrs). Approximately 400 total person hours initially. Three days every six months to review the processes and one week to implement the changes. (Maintaining Effort 64 hours every 6 months) Heads of OIT and DOT (IT and TSM) are supportive and create a positive atmosphere for cooperation. Collaboration All trust each other and work together as equals to enable a good faith effort for Actions and scheduling and problem resolution. Requirements Simplified review process; speed of the process and security needs must match. Technical Issues (continued on next slide) 12 Transportation Systems Management & Operations – Capability Maturity Implementation Plan Systems and Technologies Priority Action 1 of 2 (continued) Seek/study national best practices regarding State DOT IT-related procurement issues and Action Objective propose improvements. Key Risks Coordinating meetings, gaining concurrence, impact on DOT construction projects, OIT security issues Resource Agency resources and outside support, as needed. Requirements Any available documented best practices for streamlining the procedures. Travel FHWA Support assistance for identified IT/ITS peer exchanges. Sample IT/ITS standard operating Resource procedures (SOPs) from agencies considered national leaders. Start Date Immediately End Date On-going Processes are in place, interim milestones are met, actions items are promptly acted Success / Completion upon, and metrics (number of meetings, attendance at meetings, etc.) are in place. Indicator 13 Transportation Systems Management & Operations – Capability Maturity Implementation Plan Systems and Technologies Priority Action 2 of 2 Review/re-evaluate current agency data sharing practices and policies – such as integration of transit into 511, siloing in communication platforms, etc. Defined TSM&O data/system (i.e. OpenReach, CDU Emergency Lane Closure (EL – 15) database, Genetec Camera Control, etc.) requirements to have the capability to support Products and the exchange of information among State and local agencies to improve safety/mobility, Desired Outcomes coordinate traffic incident management, emergency transportation operations, and facilitate multi-modal traveler information. Establish a multi-agency working group which will: Action Description • • • Task(s) / Subtask(s) • • • identify all data and systems that currently support TSM&O, along with those which could potentially support TSM&O if more effectively utilized. Need to identify data for intermediate, mid-term and long term uses. identify deficiencies and gaps in data sharing that have resulted in suboptimal TSM&O. identify technical, and institutional issues that need to be resolved in order to overcome these deficiencies, including standards, interoperability, legal issues and system resiliency. identify additional agencies & organizations which would support TSM&O if these issues are resolved. review these findings with leadership group to obtain concurrence and support, including a commitment of resources. develop an implementation plan, for approval by the leadership, to ensure that these issues are resolved effectively. (continued on next slide) 14 Transportation Systems Management & Operations – Capability Maturity Implementation Plan Systems and Technologies Priority Action 2 of 2 (continued) Review/re-evaluate current agency data sharing practices and policies – such as Action Objective integration of transit into 511, siloing in communication platforms, etc. Lead Dennis Motiani (NJDOT) and TRANSCOM (Matt Edelman) Operations and IT staff from all agencies. ITS New Jersey Forum on Technology chaired by Support Staff Rizwan Baig (PANY&NJ) Two weeks per month of effort by one person for coordination between agencies. Staff Level of Formalized plan would require approximately 4 months for 10-15 hours per week 160-200 Effort) person hours in total. Senior Leadership Leadership of NJDOT and Senior Officials from key transportation and public safety Support Actions agencies An understanding among the agencies in the working group of: the value of what has Collaboration Actions and already been accomplished; openness to recognizing the gaps & deficiencies; & an Requirements understanding that certain support procedures may have to change. Technical Issues Standards, interoperability, legal/institutional concerns over data sharing, and quality control over shared data. (continued on next slide) 15 Transportation Systems Management & Operations – Capability Maturity Implementation Plan Systems and Technologies Priority Action 2 of 2 (continued) Review/re-evaluate current agency data sharing practices and policies – such as Action Objective integration of transit into 511, siloing in communication platforms, etc. Key Risks Operational and technical changes, which will need to be supported by the administrative structure of the agencies Resource Maintenance of resources, unrestricted sharing of data, and knowledge of validity of data. Requirements Need success in Action 2 of 4 in Systems and Technology for this Action to succeed. NCHRP Synthesis Report: Project 20-05/Topic 44-13, Current Practices of Sharing FHWA Support Operations Data Among Agencies Resource Start Date Immediately End Date March 31, 2015 Success / Completion Indicator Overcoming barriers, integration further enhanced, and Implementation plan completed 16 Transportation Systems Management & Operations – Capability Maturity Implementation Plan Performance Measurement Priority Action 1 of 2 Action Description Establish Performance Management Policy/Plan TSM&O Performance Measurement document defining TSMO terminology, internal and external performance measures to be used, address analytical techniques and decision Products and support systems, address a common statewide approach to outcome measures, Desired Outcomes incorporation of SW approach to MAP 21 performance measures and requirements, establish a statewide strategy for utilization of performance measures. 1. By August 1, 2014, establish a project manager and project team and target date for completion. Charter the project and project manager. Identify critical stakeholders. Identify a multi-agency steering committee to ensure communication and success of the project. 2. By November 1, 2014, project team defines policy/plan purpose and need, objectives and how it relates to other transportation planning documents and processes. Get buy-in from steering committee. a) Review MAP-21 Act and System Performance Measures proposed rule to ensure work is in line Task(s) / Subtask(s) with federal requirements. b) Canvass experience/activities of peer agencies related to desired outcomes. (continued on next slide) 17 Transportation Systems Management & Operations – Capability Maturity Implementation Plan Performance Measurement Priority Action 1 of 2 Action Description Establish performance management policy/plan 3. By November 1, 2014, project team establishes plan framework/outline of elements and gets buy-in from steering committee. A suggested framework/outline may include: a) Plan purpose and need. b) Summary of MAP-21 requirements. c) Definitions of terminology. d) Performance Measures considered and selected, both external statewide and internal for management purposes. e) Description of current conditions. f) Selection of Initial Performance Targets, potentially based on alternate scenarios, including discussion of factors considered in selection and potential additional targets moving forward. g) Strategies to reach selected performance targets citing interim deliverables/objectives. Work Task(s) / Subtask(s) includes data collection, analysis and reporting. a) Work with Law Enforcement to utilize CAD data to backfill DOT incident timeline data. h) Development of Risk Management Plan to eliminate or mitigate risk in achieving performance targets. i) Establish process for progress reporting, evaluation and reassessment of the plan. 4. By November 1, 2014, identify leads and team members/subject matter experts to complete each of the various elements of the plan. 5. By April 1, 2015, complete first draft plan. 6. By June 1, 2015, solicit feedback from steering committee and other stakeholders as required. 7. By July 1, 2015, revise and finalize the plan. (continued on next slide) 18 Transportation Systems Management & Operations – Capability Maturity Implementation Plan Performance Measurement Priority Action 1 of 2 (continued) Action Objective Establish Performance Management Policy/Plan Lead Dennis Motiani/Wasif Mirza Support Staff TSM staff, NJDOT Data Development, NJDOT Statewide Planning, NJDOT Capital Investment, MPOs, Consultants Staff Level of To be determined by TSM. Effort) Senior Leadership Support Actions Collaboration Actions and Requirements Need to be clear on how this relates to other transportation planning documents and processes and how it integrates with the project delivery process at NJDOT. Need buy-in from NJDOT senior leadership, NJ Turnpike, SJTA, NJ Transit, MPOs, NJ State Police and other key stakeholders. Potentially large group of stakeholders. Risks can be minimized through a steering/advisory committee. Do we have the appropriate technical subject matter experts involved with the plan? Access to appropriate data? Appropriate analysis tools? Plan needs to address. Technical Issues (continued on next slide) 19 Transportation Systems Management & Operations – Capability Maturity Implementation Plan Performance Measurement Priority Action 1 of 2 (continued) Establish Performance Management Policy/Plan Action Objective Key Risks Resource Requirements FHWA Support Resource Lack of buy-in from other key agencies, such as NJ Transit. Who signs? MAP-21 Final Rule on System Performance may impact the final plan. Final rule issuance is unknown. Notice of Proposed Rulemaking is expected June 2014, but notices have been delayed. Do we have appropriate staff level support? Do we have funding for consultant support? Do we have to bring a consultant on-board? FHWA funding support for performance measurement plan development? Waiting on MAP-21 rule on System Performance. Ekaraj Phomsavath Start Date November 1, 2014 End Date July 1, 2015 Completed policy/plan with clear understanding of how this plan integrates with other Success / Completion transportation planning efforts statewide and compliance with MAP-21 performance Indicator measure requirements. 20 Transportation Systems Management & Operations – Capability Maturity Implementation Plan Performance Measurement Priority Action 2 of 2 Utilize incident management performance measurement to analyze, improve and justify supportive program improvements. DOT policy document which defines a set of agreed upon performance measures for Products and Incident Management that is consistent with the Performance Management Policy/Plan Desired Outcomes and which will become a component of a Statewide TIM Strategic Plan. Action Description 1. 2. 3. Task(s) / Subtask(s) 4. By December 1, 2014, convene a Working Group including NJDOT TSM, NJSP IMU, fire, towing, EMS, NJ DEP, NJIT and MPO representatives. By December 1, 2014 Working Group should review the outcomes of MAP-21 performance measures and requirements for guidance. By February 1, 2015, Working Group should review draft of Performance Management Policy/Plan being developed as part of the CMM process and provide feedback to that project manager. By May 1, 2015, develop consensus on appropriate set of performance measures and confirm availability of accurate data for analysis. (continued on next slide) 21 Transportation Systems Management & Operations – Capability Maturity Implementation Plan Performance Measurement Priority Action 2 of 2 Action Utilize incident management performance measurement to analyze, improve and justify Description supportive program improvements. 5. By May 1, 2015, develop consensus on definitions of performance metrics and their measurement and compilation together with responsibilities for each. 6. By May 1, 2015, develop consensus on value of after-action reporting (and performance measurement) regarding strategy application improvement (field procedures, TMC, technology, etc.). 7. By August 1, 2015, define implementation approach including management, convening, meeting schedule, reporting, and approach to follow-ups involving improvements in procedures and protocols; consider MOU as appropriate. This should include coordination with the Statewide TIM Guidelines for Emergency Responders. Task(s) / Subtask(s) 8. By August 1, 2015, capitalize on new performance data to support increased resources and management attention to program. 9. By October 1, 2015, complete first draft of document. 10. By November 1, 2015, solicit feedback from Working Group and other stakeholders as required. 11. By December 1, 2015, revise and finalize the document. (continued on next slide) 22 Transportation Systems Management & Operations – Capability Maturity Implementation Plan Performance Measurement Priority Action 2 of 2 (continued) Utilize incident management performance measurement to analyze, improve and justify supportive program improvements. Lead Dennis Motiani, Sal Cowan Action Objective Support Staff TSM staff, NJDOT Data Development, NJDOT Statewide Planning, NJDOT Capital Investment, NJSP IMU Staff (Level of Approximately 300 person-hours. Effort) Senior Leadership Support Actions Collaboration Actions and Requirements Technical Issues Need to be clear on how this relates to the process to develop a Performance Management Policy/Plan and other transportation planning documents. Need buy-in from NJDOT senior leadership, NJ Turnpike, SJTA, NJ State Police and other key stakeholders. Senior Management should be exposed to the SHRP2 Senior Management Outreach Tool – CEO Slide Presentation - Organizing for Operations (L31). This process should be coordinated with the Performance Management Policy/Plan being developed as part of the CMM process. The Statewide TIM Guidelines for Emergency Responders needs to be updated and its procedures and protocols should be integrated into the performance measurements where appropriate. The development of the State’s TIM Strategic Plan should be coordinated with this effort where appropriate. This process may potentially include a large group of stakeholders. Risks can be minimized through a steering/advisory committee. Is there easy access to accurate and complete data? Are appropriate analysis tools available? (continued on next slide) 23 Transportation Systems Management & Operations – Capability Maturity Implementation Plan Performance Measurement Priority Action 2 of 2 (continued) Utilize incident management performance measurement to analyze, improve and justify Action Objective supportive program improvements. Key Risks Resource Requirements FHWA Support Resource Start Date Lack of buy-in from Senior Management and other key agencies, such as NJSP. MAP-21 Final Rule on System Performance may impact the final plan. Final rule issuance is unknown. Notice of Proposed Rulemaking is expected June 2014, but notices have been delayed. Is there appropriate staff level support? Is there funding for consultant support? Does a consultant have to be brought on-board? TIM performance measurement plans from other regions and State DOTs? MAP-21 rule on System Performance (Ekaraj Phomsavath), SHRP2 Senior Management Outreach Tool – CEO Slide Presentation - Organizing for Operations (L31) (Steve Clinger), and Travel Assistance for Identified TIM Performance Measurement Peer Exchanges December 1, 2014 End Date December 1, 2015 Completed DOT policy document which defines a set of agreed upon performance Success / Completion measures for Incident Management that is consistent with the Performance Management Indicator Policy/Plan and which will become a component of a Statewide TIM Strategic Plan. 24