SLC PHASE 2 ST KENNETHS PRIMARY SCHOOL PARENT COUNCIL MEETING respect integrity innovation collaboration excellence ALISDAIR ELLIOT – CONSTRUCTION MANAGER 1 ST KENNETHS PRIMARY SCHOOL PARENT COUNCIL MEETING SECTION 1 1.0 Introduction and Agenda 2.0 3.0 4.0 5.0 Close Project Overview & Images BLL Project Team & Logistics Current Progress & Phase 2 / 3 Transition Q&A 2 ST KENNETHS PRIMARY SCHOOL SECTION 2 2.0 The Project 2.1 2.2 Project Overview Images 3 ST KENNETHS PRIMARY SCHOOL 2.1 Project Overview The project: This project is our fourth new-build primary school building to be constructed within Phase 2 Tranche 1 of the South Lanarkshire Primary Schools Modernisation Programme. The Client: South Lanarkshire Council The Contract: PPC 2000 (Partnering framework contract agreement) Overview: The project comprises the tandem build construction of a new two-storey 16 classroom primary school. In addition to the classrooms, the building comprises private and main stream nurseries, a double gym hall, general purpose room, library and IT Suite. The new building is located within the existing school campus, formerly the location of the existing sport pitch and car park. The works are being carried out in two phases to allow the existing school to operate whilst the new building is under construction. On completion of the new school building the users will decant from existing to new allowing progression into phase 2 where the scope is to remove asbestos from the existing school, demolish the building, complete the sports pitch and finish the hard and soft landscaping. Construction: The construction of the primary school is a steel frame structure with holorib decking topped with a concrete floor slab on pads/strip foundations. The building will have predominantly a facing brick outer leaf with areas of metal cladding and curtain walling on the elevations. The roof will be an aluminium standing seam roof throughout. Internally, underfloor heating has been incorporated throughout the building with fit out specification aligning with other projects in the programme. Externally, the scheme includes external hard and soft landscaping and lighting design scheme complete with a standard 60 x 40 metre sports pitch, car parking / pupil drop off with playground & soft play areas around the school/nursery. Building: ST KENNETHS PRIMARY SCHOOL GIFA 3569 m² 4 ST KENNETHS PRIMARY SCHOOL 2.2 Images 5 ST KENNETHS PRIMARY SCHOOL 3.0 PROJECT TEAM / SITE LOGISTICS SECTION 3 3.0 Project Team & Site Logistics 3.1 3.2 3.3 BLL Design Team BLL Construction Team Site Logistics 6 ST KENNETHS PRIMARY SCHOOL 3.1 BLL Design Team Architect Cost Consultant Structural Engineer Services Engineer This is the design team engaged upon the St Kenneth’s Primary School Project 7 DELIVERY TEAM DESIGN TEAM CORE TEAM ST KENNETHS PRIMARY SCHOOL 3.2 BLL Construction Team GORDON ANDERSON Regional Director ED PARRY Commercial Director ANDY STRONACH Framework Manager TRACEY-LEIGH FINDLAY Framework Commercial Manager BARRY O’HAGAN Framework Delivery Manager TOM CAIRNEY Framework Safety Manager Alisdair Elliot Construction Site Manager OMAR AHMED WAZIR Planning Manager Michael McMullan Construction Manager (Part) TBC Finishes Construction Manager (Part) EMMA ROBB Commercial Manager 8 ST KENNETHS PRIMARY SCHOOL 3.3 Site Logistics – Overall Phasing Diagram 9 ST KENNETHS PRIMARY SCHOOL 3.3 Site Logistics – Phase 1 Logistics 10 ST KENNETHS PRIMARY SCHOOL 3.3 Site Logistics – Phase 2 Logistics 11 ST KENNETHS PRIMARY SCHOOL 3.3 Site Logistics – Phase 3 Logistics 12 ST KENNETHS PRIMARY SCHOOL 3.0 PROJECT TEAM / SITE LOGISTICS SECTION 4 4.0 Programme 4.1 4.2 Current Progress Phase 2 / 3 Transition 13 ST KENNETHS PRIMARY SCHOOL 4.1 Current Progress PROGRESS Bovis Lend Lease are currently reporting works on programme with all works due for completion 23/07/10 Works on site at present comprise the following: External Works •External Brickwork •Curtain Walling Windows and Doors •External Cladding 14 ST KENNETHS PRIMARY SCHOOL 4.1 Current Progress Internal Works •Interior Fit Out (Joinerwork, floor finishes, suspended ceilings) • •Mechanical & Electrical Installation •Architectural Metalwork •Decoration •Gym Fit Out 15 ST KENNETHS PRIMARY SCHOOL 4.2 Phase 2 / 3 Transition Bovis Lend Lease are scheduled to take possession of the Phase 3 site on the 30 July 2010 and commence preparation works for demolition of the existing school. Demolition of the existing school is scheduled to be completed during November 2010. Following which BLL will install synthetic sports pitch and carry out further hard and soft landscaping works BLL are scheduled to complete all Phase 3 works during January 2011 BLL are intending to use the existing delivery entrance of East Mains Road to service the Phase 3 works 16 ST KENNETHS PRIMARY SCHOOL PARENT COUNCIL MEETING SECTION 5 5.0 Q&A Close 17