LOWER BAKER FLOW IMPLEMENTATION DEVELOPMENT OF UNIT 4 POWERHOUSE Jeffrey Reichmuth Consulting Engineer February 18, 2014 TOPICS OF PRESENTATION 30MW Hydroelectric Facility with Synchronous By-pass Valve and Neighboring 85MW U3 Aquatics Requirements Key to License Minimum In-Stream flow 1200cfs/1000cfs Ramping Requirements, 1inch per Hour Control Strategies – Dam, Unit 3, Unit 4, SBV Economic Dispatch Construction Started December 2010 Commissioning June 2013 Baker River Hydroelectric Project, Concrete, WA LOWER BAKER PROJECT AREA Skagit River Near Concrete Washington Skagit River USGS Gage for In-stream Flow Compliance Ramping Restrictions in effect when flow below 26,000 cfs in Skagit River Baker River USGS Gage - Minimum In-Stream Flow 1200/1000 cfs Aquatics Table Mandating Flow Aquatics Ramping Rate Figure Ramping Rate in Inches per Hour Down Ramp of Facility based on Aquatics Table SITE SELECTION PROCESS FERC License 2150 – October 17, 2008 FERC - Board of Consultants Selected Various Sites And Options Reviewed Option With Synchronous By-pass Valve Ultimately Selected Site 5 Geotechnical Baseline Report Prepared Slope Stability Exploration Plan Prepared Site 1 – Low Level Outlet in Dam Site 2 – South Portal PH in Cavern Site 3 – Old Units #1 and #2 Location Site 4 – PH South of Unit #3 Site 5 – PH 400 Feet South of Unit #3,Two Tunnel Length Options ALIGNMENT OF UNIT 4 POWER TUNNEL Geologic Perspective of Facility Arrangement SLOPE STABILITY MEASURES Slope Stability Exploration Indicated Movement Of Slope During Wet Seasons Buttress Wall Built at Main Powerhouse Excavation Soldier Pile Wall Built Near Access Road Horizontal Drains Installed Into Slope Constant Electronic Slope Monitoring Installed Evacuation Alarm Installed For Construction Subterranean Powerhouse Autodesk – Navisworks Model, Developed by Black and Veatch Section Through Powerhouse Section through Navisworks Model OWNER FURNISHED EQUIPMENT PSE Supplied the Turbine, Generator and the Station Transformer Turbine Provided by Litostroj Power, Ljubljana, Slovenia Generator Provided by Končar Generators and Motors, Zagreb, Croatia Station Transformer Provided by Waukesha Electric Systems, Waukesha, WI Generator Installation Setting the Rotor with 550T Mobile Crane Synchronous By-pass Valve Just add water…