SOLAR ENERGY: CHALLENGES AND OPPORTUNITIES

advertisement
MNRE Scheme on Grid-connected Rooftop PV
Systems
Rakesh Kumar
Director (PS)
Solar Energy Corporation of India
SECI- Inception and Objectives
OUR MANDATE:
A Government of India Enterprise under
the administrative control of MNRE

To assist MNRE in executing the
National Solar Mission objectives

To plan and execute an integrated
programme on development and
deployment of solar energy
Incorporated on 20th September, 2011
as a “Not for profit” Company under
Section 25 of the Companies Act, 1956
technologies to achieve
commercialization;

Authorised capital INR 2,000 Crores; Paid
up capital INR 21 Crores for FY2012-13
both grid-connected & off-grid
power stations;

7-Apr-15
To own, operate and manage,
SOLAR ENERGY CORPORATION OF INDIA
To promote R&D in Solar
2
SECI- Ongoing Activities
750 MW PV projects under JNNSM Phase II, Batch I
• 750 MW of Large scale projects (10-50 MW)
• Upto 30% VGF funding support
• Projects to be selected through reverse bidding process
• Developers to be offered tariff of Rs. 5.45 per unit
Implementation of Solar Roof-Top scheme
• To be discussed subsequently
Large scale solar plants including Ultra-mega project at Sambhar
• 1000 MW PV plant coming up through JV route; capacity to be ramped up to 4000
MW
• SECI to be major stakeholder in the project
• Upto 30% VGF funding support
7-Apr-15
SOLAR ENERGY CORPORATION OF INDIA
3
Contd…
Solar Mini/Micro Grids
• Aims to provide energy access to remote villages
• Funded through CSR of major PSUs
• To be awarded through competitive bidding
Supply of low cost solar lanterns
• High quality low-cost lanterns targeted for rural population
• Funded through CSR of major PSUs
• Cost discovered through Competitive bidding
Solar Thermal installations for water/air heating
• Covering 25 schools in remote locations
• Subsidy to be provided by MNRE
Pilot Solar Thermal Power Plants
• Large scale CSP projects with different configurations
• SECI to own these projects
7-Apr-15
SOLAR ENERGY CORPORATION OF INDIA
4
Growth of Solar Capacity in India (MW)
1809
Solar Capacity (MW)
1684
936
3
11
36
2008-09 2009-10 2010-11 2011-12 2012-13 2013-14
State
Gujarat
Rajasthan
Maharashtra
Madhya
Pradesh
Andhra
Pradesh
MWp
857.9
601.2
160
%
47.42
33.23
8.84
37.3
2.06
33.2
1.84
Uttar Pradesh
17.4
Tamil Nadu
Jharkhand
Karnataka
Orissa
Punjab
Haryana
West Bengal
A & N Island
Uttarakhand
Chhattisgarh
Delhi
17.1
16
14
13
9.3
7.8
7.1
5.1
5.1
4
2.6
Lakshadweep
0.8
0.96
0.95
0.88
0.77
0.72
0.51
0.43
0.39
0.28
0.28
0.22
0.14
0.04
Moving Towards grid parity
Source:KPMG
By 2016-17, roof top solar power cost will reach the grid parity.
7-Apr-15
SOLAR ENERGY CORPORATION OF INDIA
6
Why Rooftop PV
• On national level, reduces requirement of
land for addition of solar capacities
• For consumers, it
– Reduces the dependency on grid power
– Mitigates diesel generator dependency
– Long term reliable power source
• For Discoms, it reduces
– Day Peak load Demand
– T&D and conversion losses as power is consumed
at the point of generation
• Most suitable for commercial establishments
– Max generation during peak usage time
– Solar power cost is close to the commercial power
cost
Roof top PV potential in India
• According to 2011 Census India has:
– 330 million houses
– 166 million electrified houses
– 76 million houses use kerosene for lighting
– 1.08 million houses use solar for lighting
– 140 million houses with proper roof (Concrete or
Asbestos / metal sheet)
– 130 million houses having > 2 rooms
•
Average houses can accommodate 1-3 kWp of
solar PV system
•
Large commercial roofs can accommodate
larger capacities
•
As a conservative estimate, about 25 GW
capacity can be accommodated on roofs of
buildings having > 2 rooms alone (considering
20% roofs are available/suitable)
Rooftop PV Programmes under
JNNSM
• Small scale rooftop PV systems
–
Size: less than 100 kWp
– Implemented through MNRE Channel
Partners
– Generally in off grid mode
•Large scale rooftop PV scheme
– Size: 100 to 500 kWp grid-connected systems (without battery back up)
– Implemented through SECI through a process of competitive bidding
– 3 Phases announced; Phase I: 5.5 MW (4 cities); Phase II: 11.3 MW (6 cities);
Phase III: 10 MW (9 cities)… more to come
– Possible locations include public buildings, hospitals, educational institutions,
warehouses etc.
MNRE’s Large-scale Rooftop PV Scheme
30% subsidy available
from MNRE
Chandigarh (1)
Projects being set up in
select cities
Gurgaon (2)
Noida/Greater Noida (1.5)
New Delhi (2)
Project capacity:
Jaipur
(3.25)
Phase I: under
implementation
Phase II: Rooftop
identification in progress
Gwalior (1)
Phase III: Projects in
bidding and evaluation
stage
Legend
7-Apr-15
Phase I
Phase II
Phase III
Multiple phases
() Capacity in MW
Palatana
(1)
Kolkata (1)
Bhubaneswar (1)
Mumbai (1)
Pune (1)
Raipur
(2.05)
Hyderabad (2)
Bangalore (2)
Chennai
(4)
Coimbatore (1)
SOLAR ENERGY CORPORATION OF INDIA
11
Simple cost estimations
System size
100 kWp
System cost
0.8 -0.9 crore
Subsidy
30%
Expected electrify generation 160000 units
Payback period @ Grid
electricity cost (Rs. 6.5/ Wp)
5-6 years
Payback period with
Accelerated Depreciation
4-5 years
Pay back @ diesel power cost 3-4 years
Plant life
25 years
State
Tariff (INR)
(HT customers)
Madhya
Pradesh
4.10
Rajasthan
5.50
Andhra
Pradesh
6.08
Tamil Nadu
5.50
Karnataka
5.10
Punjab
6.26
Haryana
5.30
Gujarat
4.20
*Connectivity, fixed charges,
metering charges, Taxes will be
extra ( will add between Rs. 1-2)
SECI’s Implementation methodology
• SECI is implementing the scheme by selected developers through
competitive bidding on the project cost in for selected cities .
• SECI has prepared technical specifications to ensure quality of
installations.
• Under the scheme SECI will
– Allocate capacity to selected bidders for each city.
– Verify project proposals w.r.t. technical specifications and release
the sanction for subsidy which is linked to performance up to 2
years.
– Release initial subsidy on successful commissions as per technical
specifications. (20%).
– Release 5 % subsidy at the end of 1st and 2nd year of successful
maintenance of the project.
– Help developers for identification of projects through dissemination
workshops and to assist in resolving any issues with concerned
authorities.
Status of Implementation
Phase-I:
•
•
•
 Chennai – 2 MW
 Bangalore – 2 MW
 Delhi – 1 MW
 Gurgaon – 0.5 MW
Companies shortlisted as per their
bids for each cities against
benchmark project cost of Rs.
130/Wp
Projects allocated up to ~ Rs. 88/Wp
About 4.5 MW of projects already
identified
and
started
implementation
Phase –II:
Revised benchmark cost Rs. 90/Wp
 Jaipur – 3.1 MW
 Bhubaneswar/Cuttack - 1 MW
 Hyderabad – 2 MW
 Gurgaon – 1.5 MW
 NOIDA/ Gr. NOIDA – 1.5 MW
 Raipur – 2 MW
 The initial deadline for identification of
the Projects is 14th Nov, 2013
Experience in Bhubaneswar
• 1 MW allotted to two bidders under Phase II of Rooftop scheme
• Following developers selected:
– M&B Switchgears Ltd (500 kW)
– Photon Energy (500 kW)
• About 700 kWp of projects have already been identified
– Kalinga Institute of Social Sciences (500 kW)
– NALCO (160 kW +) - Requested for more capacities on their Angul Plant.
• Orissa government is also implementing/planning to install roof-top
projects on government buildings
• More roof-top capacities could be considered for allocation, if there is
good progress and interest of the stake holders
Main Issues in implementation
Connectivity Issues
 Electricity to be fed into grid at Voltage level below 33 KV
 No clarity on connectivity norms at these voltages
– However, CEA has published the CEA (Technical Standards for
Connectivity of Distributed Generated Resources), Regulations 2013
recently to address these issues
Metering issues
 Many states have no regulations on net metering
 No uniformity of standards, different state regulations inconsistent
– CEA has come up with draft CEA (Installation and Operation of
Meters) Amendment Regulations, 2013
– SECI working with states to bring out net metering regulations
Contd…
Business models – Tariff & PPA etc
 Confusion over contract clauses; different tariffs quoted to different
consumers
‫ ـ‬SECI has identified some key provisions to be a part of PPA for
benefit of rooftop owners and developers
‫ ـ‬SECI may assist in discovering optimum tariff structure
Project Performance
 Performance of large scale grid connected rooftops untested in India
- SECI to monitor performance and facilitate mitigation of issues
(if any)
THANK YOU
Visit us at www.seci.gov.in
States’ Initiatives for Rooftop PV
Initiatives for promotion of Rooftop PV
in Andhra Pradesh
 AP Solar Policy 2012 promoting roof top solar projects
 Only for 3 phase service consumers can setup roof top PV systems
 Net metering is allowed
 Recently announced by a committee that Rs.3.50 per unit would be
paid for exported power for 7 years
 The consumer/SPV generator also
has to set up a protection system on
their premises with “Islanding” for
events like grid failures
 Any
prevalent
subsidy
from
Government of India can be availed.
Gujarat
 Gujarat already initiated 5MW
Rooftop Project in Gandhi Nagar in
PPP model.
 Generated power is completely fed to
the grid.
 As per their model, Roof owner gets
paid lease rent (Rs.3.00 per unit) and
the project developer gets feed-intariff (Rs.11.21) for 25 years.
 Recently announced a rooftop
scheme for development of 25 MW in
5 other cities.
Kerala
•
Kerala launched its 10,000 rooftop power plants
program for 2012-2013.
•
With each applicant eligible to apply for
1 kW
only, the total capacity target is 10 MW.
•
Due to the small per capita limit; the target
audience will be only households and small
cottage industries.
•
Apart from the MNRE’s 30% capital subsidy, the
state is offering a discount of Rs. 39,000 per
system.
•
West Bengal
West Bengal has initiated a net-metering solar rooftop
model promoting self consumption.
•
Under the WBERC Regulations, grid-integrated rooftop
PV is allowed only for institutional consumers like
government departments, academic institutions, etc.
•
The system size limited to 2-100 kW, Connectivity is
allowed at Low Voltage or Medium Voltage, or 6 KV or
11 KV, of the distribution system of the licensee.
•
Solar injection is permitted only up-to 90% of the
annual electricity consumption, and the net energy
supplied by the utility would be billed as per existing
slab tariffs.
•
Solar generation would first offset consumption in the
highest tariff slab and then the lower slab.
•
Policy targets 16 MW of rooftop and small PV
Kolkata development
authority mandated all
commercial and high raise
building to install solar PV
to meet 2% of their energy
demand.
Tamil Nadu Solar Policy 2012
• Targets 3000 MW by 2015 , including 350 MW of
rooftop capacity in three phases of 100, 125 and
125 MW (per year) during 2013-2015.
• 50 MW from domestic customers who will receive
a GBI of Rs. 2/kWh for the first two years, Rs.
1/kWh for the next two and Rs. 0.5/kWh for the
subsequent two years.
• 300
MW
from
government
buildings
and
government schemes for rural and urban lighting.
• Mandates 6% SPO for HT consumers to achieve • Connectivity :
targets.
• TEDA designated as single window agency.
< 10 kW - 240 V
< 100 kW – 415 V
> 100 kW - 11 kV
Uttarakhand
• Uttarakhand Electricity Regulatory Commission released regulations for solar
roof top plants.
• Allowed roof to projects to connect at the following voltage levels
(i) Load up to 4 kW: low voltage single phase supply
(ii) Load >4 kW and up to 75 kW: low voltage three phase supply
(iii)Load >75 kW and up to 1.5 MW: at 11 kV
(iv)Load >1.5 MW and up to 3 MW: at 11/33 kV or as per site condition.
• UERC determined levelized net tariff for roof top systems as Rs.9.2 without
accelerated depreciation and Rs. 8.15 and with accelerated depreciation.
Other States/UT
• Chandigarh
–
Hon’ble
Union
Minister
inaugurated roof top PV projects on July 3,
2013.
• Punjab and Haryana are vey actively pursuing
development of roof top PV projects.
• Rajasthan expressed to develop 3.1 MW of
roof top solar plants in Jaipur.
• Chhattisgarh is also actively working on roof
top programs and submitted request for
2MW.
Download