T20 - the Department of Electrical and Systems Engineering

advertisement
Team #20: ESE Sr. Des.
SteamIt
Analysis on Retrofit of Penn’s Steam Heating System
Round 2 PowerPoint Presentation
Sabrina Andrews
Michael Buzinover
Jenna Kanterman
Neha Mathur
12/4/13
Advisor: Dr. Peter Scott
1
Team #20: ESE Sr. Des.
Did you know?
About 86% of Penn’s carbon production comes
from building energy usage
If immediate action is not taken to reduce energy, Penn
will nearly double its total carbon emissions by 2050
Goal: Cut campus energy use by 17% by 2014
12/4/13
Advisor: Dr. Peter Scott
2
Team #20: ESE Sr. Des.
Roadmap
Neha
•
•
•
•
Project Description
Objectives
Overview of Penn’s Heating Systems
Stakeholders
Jenna
•
•
•
•
Model Specifications & Methodology
Schedule
Completed Tasks
Immediate Tasks
12/4/13
Advisor: Dr. Peter Scott
3
Team #20: ESE Sr. Des.
Project Description
The final product will be a quantitative model (e.g.
Matlab, Excel) and a simulation of Penn’s Heating
system where users can alter inputs of the existing
system to determine resource and cost savings.
12/4/13
4
Team #20: ESE Sr. Des.
Objectives
Design a model derived from Penn’s steam heating
system to achieve at least 5% cost and resource
savings across the following areas:
Energy Recovery
from Condensate
12/4/13
City Water Usage
Advisor: Dr. Peter Scott
Retrofit to Existing
Buildings
5
Team #20: ESE Sr. Des.
Existing System
Heating Air
I
N
P
U
T
S
Ambient Air
Steam Energy
Discarding Waste
Entering Steam
Quenching
Water
220°
70°
Entering Water 180°
Exiting Condensate
210°
Reheat Coil
Heat Exchanger
Quenching
Exiting Water 160°
O
U
T
P
U
T
S
Water
Discharged Into
Sewer
Exiting Air
75°
140°
*All Temperatures in degrees Fahrenheit
12/4/13
Advisor: Dr. Peter Scott
6
Team #20: ESE Sr. Des.
CHEM 58
Condensate
Discharge
Closed-Loop Water Entering Heat Exchanger
12/4/13
Advisor: Dr. Peter Scott
Reheat
Coils
7
Team #20: ESE Sr. Des.
Stakeholders
Stakeholders
Considerations
University of Pennsylvania
Decrease the amount that Penn
spends on steam, while not changing
comfort level in buildings
Veolia Energy Corporation
Penn consumes approximately 40% of
its output
Philadelphia Community
City water is wasted to quench the
condensate to 140oF
12/4/13
Advisor: Dr. Peter Scott
8
Team #20: ESE Sr. Des.
Model Specifications
Retrofit Variables
System Parameters
• Desired Building Temperature
• Building Specifications
• Steam Pressure Entering Heat
Exchanger
• Pressure of Purchased Steam
• 15 psi
• Calibration of Heat Exchanger
• Additional Reheat Coils
• 220 psi
• Size of Heat Exchangers
• 24’’x12’’ or 24’’x10’'
• Existing Reheat Coils
• 12 total
12/4/13
Advisor: Dr. Peter Scott
9
Team #20: ESE Sr. Des.
Model Outputs
Resource Usage
• Quantity of Steam Purchased
Cost Analysis
• Total Cost of Resources
• Quantity of Quenching Water
• $0.083/kWh
• Electricity for Hardware
• $15/1000 lb of steam
• Total Cost of Hardware
Modifications
• Incremental Cost Analysis
• Payback Period
• 5 years
12/4/13
Advisor: Dr. Peter Scott
10
Team #20: ESE Sr. Des.
Model Methodology
Develop Design Parameters
• Thermodynamic & Efficiency
Equations
• Establish Current Cost Baseline
Build Model
• Regression Model
• Clustering Model
12/4/13
Evaluate Alternatives
• Determine Selection Criteria
• Examine Costs of Variable
Manipulation
Advisor: Dr. Peter Scott
11
Team #20: ESE Sr. Des.
Schedule
Phase 1: Research and Analyze
Project Design
9/8-10/20
Review Existing
Systems
10/20-11/24
Develop Design
Parameters
10/20-11/24
Evaluate
Alternatives
11/10-11/24
Simulation
2/2-3/23
Verification and
Pilot
3/16-4/13
Phase 2: Create Model and Verify
Build Model
12/1-2/9
User Interface
1/26-2/9
Task Leader
Sabrina
Michael
Neha
Jenna
12
Team #20: ESE Sr. Des.
Completed Tasks
• Chose Project Mentors and discussed capacity of
their involvement ✓
• Selected CHEM 58 building for preliminary data
modeling ✓
• Obtained engineering design specifications for the
CHEM 58 building ✓
12/4/13
Advisor: Dr. Peter Scott
13
Team #20: ESE Sr. Des.
Completed Tasks
• Defined alternatives, then assessed each
alternative’s trade-offs and requirements ✗
• Created a project schedule ✓
• Toured the HVAC systems of various buildings on
Penn’s campus ✓
12/4/13
Advisor: Dr. Peter Scott
14
Team #20: ESE Sr. Des.
Immediate Tasks
Sabrina
• Analyze system limitations
• Verify stakeholder interests
Michael
• Identify relevant thermodynamic
equations
• Input thermo. equations into model
12/4/13
Neha
• Establish cost baseline
• Model variable interdependence
Jenna
• Review eQuest Simulator
• Enter fixed variables into model
Advisor: Dr. Peter Scott
15
Team #20: ESE Sr. Des.
Questions?
12/4/13
Advisor: Dr. Peter Scott
16
Team #20: ESE Sr. Des.
Appendix
12/4/13
Advisor: Dr. Peter Scott
17
Team #20: ESE Sr. Des.
Schedule
12/4/13
Advisor: Dr. Peter Scott
18
Download