(IDIQ) Contracting BASICS - National Contract Management

advertisement
Indefinite Delivery, Indefinite Quantity (IDIQ)
Task Order Contracts
Convenient Tool for Flexible Contracting
© Copyright 2011 - Cole Price
1
Indefinite Delivery, Indefinite Quantity (IDIQ) Contracting
What is it?
•
An IDIQ “master” or “umbrella” contract provides for the procurement of an
indefinite quantity of supplies and/or services
–
–
–
–
–
–
–
–
Facilitates the order of goods or services defined by a broad SOW
Throughout a specified period of performance
Allowing a customer to place Task Orders for individual requirements
Quantity limits may be stated as number of units or as dollar values
Customer is required to order and Seller required to furnish a minimum quantity
Contract may also specify maximum or minimum quantities
IDIQ Contract does NOT authorize work
Work authorized by Task Orders
•
Authorized by FAR 16.504 and as adapted by commercial customers
•
FAR requires customer to buy a Guaranteed Minimum Amount under the
contract but leave actual requirements to later determination
– Guaranteed Minimum is typically low
– Commitment of funds (including guaranteed minimum) does not occur until actual
orders are placed
•
Can be single award or multiple awards
© Copyright 2011 - Cole Price
2
Indefinite Delivery, Indefinite Quantity (IDIQ)
IDIQ Master Contract & Task Orders
IDIQ Master Contract with Multiple Task Orders
IDIQ
Master
Contract
Task
Order
1
Task
Order
2
Task
Order
3
© Copyright 2011 - Cole Price
Task
Order
4
Etc.
3
Indefinite Delivery, Indefinite Quantity (IDIQ) Contracting
Diverse Applications
• FFP Commercial Production – Aircraft & Space
–
–
–
–
Machine & Sheet Metal parts
Subassembly & Assembly
Tooling
Multiple Customers
•
•
•
•
Boeing
MDC LB & St. Louis
General Dynamics
Rohr Industries
•
•
•
•
CPFF Studies w/ USAF, AFRL
T&M Studies w/ USAF, AFRL
CPFF/CPIF Software Development for US Navy
CPFF Engineering Development for Commercial & US Govt
customers
• Engineering Service Contracts to address Obsolescence & Product
Improvements
• Site Construction & Maintenance
• GSA Schedule Contracts
© Copyright 2011 - Cole Price
4
Indefinite Delivery, Indefinite Quantity (IDIQ) Contracting
Master IDIQ Contract - BASICS
•Many similarities to Basic Ordering Agreements (BOA)
•“D” for IDIQ Delivery Order Contract
–F33615-11-D-2014
–“C” for Contract & “G” for BOA
•IDIQ Contract is a “contract to contract”, containing
–Cover Page (like a SF 26)
–Contract Schedule including CLIN’s, Special & General Provisions, SOW, etc.
–SOW with high level description of goods or services to be procured by TO’s
–CDRL that serves as “shopping list” for Delivery/Task Orders
–GFE, GFI, Patent & Data rights, fee, Invoicing, shipping, security
–Minimum & Maximum Quantities (usually expressed in dollars)
•IDIQ contract does not authorize any work or expenditures
–Contains “Ceiling Price(s)” limiting total of Task Orders
–Minimum Quantity that must be procured under IDIQ contract
–Task Orders authorize expenditures to accomplish specific SOW’s
•Contract Value
•Funding
© Copyright 2011 - Cole Price
5
Indefinite Delivery, Indefinite Quantity (IDIQ) Contracting
Task/Delivery Order - BASICS
• Task Orders authorize work
–
–
–
–
–
–
Cover page (like SF1155 for TO award, then SF 30 for mods)
Employs IDIQ Contract Ts&Cs by referencing contract number
Specific SOW & CDRL requirements
Contract Value
Contract Funding
TO values “count” towards IDIQ Minimum & Ceiling Price
• Task Orders each managed like a stand-alone contract
–
–
–
–
–
TO Unique Changes, Value & Funding, including Proposals & Mods
Unique SOW & CDRL requirements
Separate Accounting
Unique ACRN’s
Each Task Order is Closed individually
• Types of Work authorized may differ
– Completion
– Level-of-Effort”
© Copyright 2011 - Cole Price
6
Indefinite Delivery, Indefinite Quantity (IDIQ) Contracting
RFP’s
• RFP for IDIQ contract
– Very Comprehensive
– Pro-forma contract schedule
– Terms including Invoicing, Packaging & Marking, Inspection &
Acceptance, Ordering, shipping, etc.
– Detailed Special & General provisions
– Section L, “Instructions to Offeror”
– Section M, “Evaluation Factors”
• RFP for Task Orders
– Very Brief
– Cover Letter referencing IDIQ contract invoking schedule, including
associated terms
– SOW
– CDRL
– Terms applicable to Task Orders are in IDIQ contract
– Proposal TAT often short (5 to 15 days not uncommon)
– Proposal Certification may be required
– FAR 16.501-2(c) allows orders to be any type under Part 16
© Copyright 2011 - Cole Price
7
Indefinite Delivery, Indefinite Quantity (IDIQ) Contracting
ADVANTAGES & DISADVANTAGES
• Advantages
– It is a binding contract
– Expedites ordering of services & goods
• Reduces Procurement Lead Times
• Simplifies Ordering process
– Establishes negotiated contract terms
– Up-front selection of qualified bidders
– Long term Commitments on rates (if T&M) or fee arrangements
(CPIF/CPAF)
– Assist with medium to long range resource planning
– May establish option terms under the contract
– May award multiple contracts for the same service, but the minimum
requirement must be met with each award
– No dollar limit on individual orders (TO’s may be small or large)
– Simplified administration
– Procuring agencies can MPR money to procure goods or services
• GSA schedule contracts being used frequently
• NASA MPR money to USAF to authorize Contractors to perform studies
• Outsourcing Procurement
© Copyright 2011 - Cole Price
8
Indefinite Delivery, Indefinite Quantity (IDIQ)
Contracting
ADVANTAGES & DISADVANTAGES
• Disadvantages
– IDIQ (Master) Contract Proposal Prep costs can be considerable
– Minimum Order Quantity can be very small
• May have stated quantity limits in units or dollar values
• Example: $100K minimum & $100M Maximum/Ceiling
– Limited to a fixed period
• Ordering Period
• Period of Performance for completion of all Task Orders
– May require greater administration, depending upon terms
– Limited Competition
– Outsourcing Procurement
• Use of MPR to Govt Agency w/ IDIQ contract to procure
• Loss of Direct Control over Contractor
• Some increased costs for Procuring Agency’s Admin & Mgmt Costs
© Copyright 2011 - Cole Price
9
Indefinite Delivery, Indefinite Quantity (IDIQ) Contracting
Task/Delivery Orders
•
Multiple Awards
–
–
Preferred as a matter of policy: FAR 16.504(c)
Are mandatory for IDIQ advisory and assistance service requirements
exceeding 3 years and $12.5 million unless
•
•
•
•
•
Multiple awards are not practicable
Only one contractor can reasonably perform the work
Only one responsive, responsible Contractor
Only one offer is received
Per FAR 16.505(b)(1),“Fair Opportunity” is required for all orders
exceeding $3,000 except:
–
–
–
•
Urgent requirements;
Requirements that can be fulfilled by only one Supplier; or
Requirements that are logical follow-ons to previously ordered requirements.
Limits on Task/Delivery Orders in Excess of $100 Million
–
Prohibition on award to a single source unless agency head determines:
•
•
•
Only single source can perform work,
Firm fixed price task orders,
In the Public Interest
© Copyright 2011 - Cole Price
10
Indefinite Delivery, Indefinite Quantity (IDIQ) Contracting
Task/Delivery Orders
• DoD 2008 Authorization Act Changes for Task or DO over $5M
–
–
–
–
–
Notice of the planned task/DO
Reasonable time to respond
Disclosure of significant evaluation factors
Best value documentation
Post award debriefing
• Protests of IDIQ Task Orders
– Awards of task orders (a.k.a. “down selects”) have historically not been
protestable
– Protests of task order awards
• >$10M were authorized by 2008 DOD Appropriations Act
• TO increased the scope, period or maximum value of the IDIQ contract
– Protests of IDIQ (Master) contracts are protestable
© Copyright 2011 - Cole Price
11
Indefinite Delivery, Indefinite Quantity (IDIQ) Contracting
Drives Procurement Changes
•
New Applications for IDIQ Contracts
– Major System Development
– Software Maintenance
•
Multiple Awards
•
Task Orders are competed
•
Lowers Customer Administrative Burden on Buyer
•
Increases Administrative Burden on Contractors, so Contractors must find
leaner ways of doing business
– Develop new Processes
•
•
•
•
•
Proposal Prep Process
Co-SOW Development
Alpha Price
Obtain expeditious Subcontractor proposals
Expedite estimating, pricing & sign-off approval
© Copyright 2011 - Cole Price
12
Indefinite Delivery, Indefinite Quantity (IDIQ) Contracting
Key Contract Provisions
•
•
•
•
•
•
•
•
•
(Task/Delivery) Ordering Provision
Min & Max Order Quantities/Dollars
Guaranteed Minimum
Fee/Profit
Fixed Hourly Rates (T&M or FFP-LoE)
Order of Precedence – More likely to have conflicts between IDIQ & Task Orders
Organizational Conflict of Interest (OCI)
Delivery/Task Order Placement Procedures
Task Order Proposal Prep Cost recovery
–
–
–
•
•
•
Payment Terms
Special & General Provisions
Period of Performance
–
–
•
•
•
•
•
•
Separate CLIN
Use B&P
Recover under TO . . . If awarded
Ordering
Task Order Performance
IP Rights
Security Requirements
Key personnel
Reimbursement of Travel costs
Subcontracting – ID “approved” subs in contract
SOW & CDRL – high level shopping lists
© Copyright 2011 - Cole Price
13
Indefinite Delivery, Indefinite Quantity (IDIQ) Contracting
To bid or not to bid - Things to Consider
1. How many awards will there be?
2. If there are multiple awards by size and socio-economic categories, what will the order
of preference be for deciding the competitive category at the Task Order Level?
3. For Small Business Set-asides, does the Prime have to do 50% of the work? (Contract
Level vs. Task Order Level)
4. Can I bid as both a Prime Contractor and a Subcontractor?
a. To other Small Businesses
b. To other Large Businesses?
5. Is this a bundling of existing contracts? If so which ones?
6. If I win, can I afford to do business development?
7. Who/How to pay for proposal prep?
8. If this award is for new business, what is the projected budget by fiscal year? (Does the
customer have any money?)
8. Do I have the Subcontracting Staff and Process in place to price Task Order proposals
& administer this contract?
9. If there is only going to be a single award do the RFP Section L proposal instructions
and Section M evaluation criteria lend themselves to making a single award?
10. Contract type (CPFF, CPIF, CPAF, FFP, FFP-LoE, T&M, or ???)
11. Will provisions for Fee/Profit allow for reasonable returns (ROC, ROS, RONA)?
11. Will contract establish fixed rates or rate ceilings? If so, how long?
12. Will Key Personnel provision dedicate resources needed for other programs/pursuits?
© Copyright 2011 - Cole Price
14
Indefinite Delivery, Indefinite Quantity (IDIQ)
Acquisition Concerns
•
•
•
•
•
•
Pricing Baselines – for IDIQ & subsequent Task Orders. Need to Implement a pricing
and analysis tool that enables the development, categorization, and factoring of baseline
estimates to focus pricing analysis on high risk or competitive advantage areas.
Bid Approvals – The standard proposal governance and approval models are often not
agile enough to accommodate the timelines required for TO’s
Subcontractor Management/Collaboration – Affects Competitiveness & Time needed
to respond to Task Order RFP’s.
Strategic Variables – Need to assess high rate of complexity based on the wide range of
services and work products included under the IDIQ contract. Because each task order
SOW will vary, use of a consistent bidding strategy may not be feasible. For this reason it
is vital that a variable and configurable proposal strategy be adopted.
Subcontracting/Teaming – Speed is critical to compete and win IDIQ contracts,
including subsequent task orders. Subcontract agreements are necessary to configure a
timely response that meets customer requirements. In order to lower the “overhead”
inherent in complex teaming arrangements, a modular strategy and framework should be
established. This bid approach aligns subcontractors with services and work products in a
pre-bid “matrix” that facilitates rapid proposal TAT’s and PO placement for TO support.
Competitive Intelligence/Analysis – As competition increases, contractors will discover
that a robust competitive intelligence capability will play a key role in their success. Both
the gathering of critical competitor information (while complying with Procurement
Integrity laws) and the enablement of an analysis utility will be vital to winning
© Copyright 2011 - Cole Price
15
Download