NYHAMNA EXPANSION STATUS OG FOKUS FREMOVER Kontaktpunkt Nyhamna 10.02.2015 Stein Inge Rakvåg Interface Manager Norway Projects Februar 2015 1 LANDFALL Polarled pipeline trekkes inn i starten av mars. Dette utføres av Statoil/Halliburton og Allseas‘ største rørleggingsfartøy Solitaire Norway Projects 11. februar 2015 2 CIVIL Civil = excavations and ground work, columns, plinths, paving, cable culverts, weir boxes, u.g. piping, etc. Mesteparten av Civil-arbeid vil ferdigstilles i 2015, knapt 40% nå Mye forarbeid for å plassere nye moduler. Første kom 1.12 Neste «test» er installasjon av piperack no 4 i P35, i Mars. Ser på samtidig arbeid i perioden hvor vi har nedstengt anlegg Norway Projects 11. februar 2015 3 GRUNNARBEID, ARMERING OG STØPING Norway Projects 11. februar 2015 4 CONSTRUCTION – AREA P45 SUBSTATION S-130 Casting of roof and all walls above level 2 in Substation S-130 Concrete casting and anchoring of foundations 5 Norway Projects 5 CONSTRUCTION – AREA P35 & SLUG CATCHER AREA P 37 New Firewater & Open drain line tested and lived up Completion of last foundation for Pre TA FDR-110- completed during January Piling for extension of S-070 completed- start concrete work at S-070 Concrete casting of foundations 6 Norway Projects 6 CONSTRUCTION – AREA P46 & MEG AREA P 53 Ground work, lean concrete and form work started Casting of foundations started Demolishing work completed 7 Norway Projects 7 P35 Norway Projects 11. februar 2015 8 NYHAMNA SITE CONSTRUCTION Norway Projects 9 NYHAMNA SITE CONSTRUCTION Norway Projects 10 Nyhamna Expansion: Loadout of first module at MPG, Gdansk.... On 20 and 22 of January the first Steel pre-fabricated module ‘R45V01’ (A main pipe rack with a total weight 113 tons) was safely and successfully loaded-out at the Mostostal Pormorze (MPG) fabrication facility in Gdansk, Poland. After a 3-day transit though the Baltic and North Seas, the module arrived safely at the Kværner Stord Construction yard on the 26th of Jan. R45V01 is the Nyhamna Expasion Project’s first module to be transported from MPG to Kvaerner Stord for further outfitting i.e. piping, E&I etc and will be followed by 5 more major module structures in the coming months. Well done to the Nyhamna Expansion Module Construction Team! Offload at Kværner Stord.... M, E & I : Main activities R35HV01 R37TV01 N244V01 R37SV01 17 modules delivered Inst. of Pre-Turnaround modules (4) in P37N, P35E and U24 Installation EIT equipment : • Breakers 132kv, 22kV & 11kV in S30 • LV (690+400) switchboards in S40, S50, S60, S70, S80, S100 • Cabinets in S040 • Cable pulling to E94, in S40, U24, P37 Stick-built and welding in habitats Pipe support installation PFP, insulation, Heat tracing act. TURNAROUND 2015 – BASIS FOR NEW BASELINE Jan. All Workorders And duration In SAP Febr. Training plan established TAR3 Mar. Apr. May June July List of All tools / EQ Comm. Proc. all personnel ordered Completed Job-Pack’s PtW SJA Modules to be MC Complete in TA2015 Receive, pack and bag installation material N355V01 N336V01 Receive, and mark all piping spool’s Modules to be installed In front of TA2015 M S 6 R35HV01 Receive modules at site N244V01 Modules to be lifted in TA2015 N338V01/02 N335V01 Inst. of Pre-Turnaround modules N336V02 Measuring Prefabr. HU Spools R37TV01 M S 6 R37TV01 Pre-Turnround Work Remove insulation Remove Heat-tracing Remove PFP Scaffolding Turnaround Piping Tie-in Electro Piping Tie-in Electro Tie-in Modification Mechanical equipm. ESD / SAS system upgrading Stick-built for TA2015 (FAV75) Jan. 1 Febr. Norway Projects Mar. Apr. N337V01 May June July VOLUM TA Moduler, tanker, internals 220 tonn Rørinstallasjon 250 Piping tie-ins 151 Pipe supports 33 E,I&T tie-ins Norway Projects 11. februar 2015 14 HOVEDKOMPONENTENE Norway Projects 11. februar 2015 15