Turkish Power System Overview 27-28 March 2012 TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS) 1 TURKISH POWER SYSTEM - NUMBER OF SUBSTATIONS LENGTH OF TRANSMISSION LINES - 400 kV 78 - 400 kV 15830 km - 220 kV 2 - 154 kV 32513 km - 154 kV 520 - 220 kV 85 km - 508 km - 66 kV TOTAL: 14 614 (103.100 MVA) 66 kV - 154 kV and 400 kV cable length - TOTAL 49.159 km 220 km 2 INSTALLED CAPACITY & PEAK LOAD INSTALLED CAPACITY (DECEMBER 2011) WIND 1687; 3,2% THERMAL HYDRO WIND OTHER RENEWABLES : 53.235 MW Renewable(hydro,wind,jeo.) : 36 % Thermal : 64% OTHERS 115; 0,2% HYDRO 17160; 32,3% Installed Capacity Peak Load (2010) : 33.392 MW Peak Load (2011 July) : 36.122 MW THERMAL 34210; 64,3% 3 GENERATION FOR 2011 Other Renewable, 1.051, 1% Wind, 2.827, 1% Fuel - Oil, 4.957, 2% Coal, 2.047, 1% Imported Coal, 14.481, 7% Lignite, 35.647, 17% Hydro, 51.518, 24% Other Thermal, 1.189, 1% Total : 229,3 TWh Thermal : 73,7 % Renewable : 26,3 % Natural Gas, 96.569, 46% 4 CONSUMPTION 1998 1999 2000 2001 2002 2003 2004 2007 2008 2009 2010 2011 Consumption 114,0 118,5 128,3 126,9 132,6 141,2 150,0 160,8 174,6 190,0 (TWh) 198,1 194,1 210,4 228 4,3 -2,0 8,4 9,0 İncrease (%) 8,1 3,9 8,3 -1,1 4,5 6,5 6,3 2005 7,2 2006 8,6 8,8 5 PEAK LOAD AND ELECTRICITY CONSUMPTION 2001-2020 70000 450000 65000 400000 60000 55000 350000 50000 MW 40000 250000 35000 GWh 300000 45000 200000 30000 25000 150000 20000 100000 15000 10000 50000 5000 0 0 2001 2002 2003 2004 2005 2006 2007 2008 2009 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 TÜKETİM (GWh) SENARYO 1 ENERJİ TALEBİ SENARYO 2 ENERJİ TALEBİ PUANT YÜK (MW) SENARYO 1 PUANT TALEP SENARYO 2 PUANT TALEP 6 INTERCONNECTIONS (Existing Situation) BULGARIA 145 km 400kV 136 km 400kV GEORGIA 28 km 220kV 160km 400kV ARMENIA GREECE 130 km 400kV 80,7 km 154kV 40 MW NAHCİVAN 87 km 154kV IRAN 73 km 154kV 100 km 400kV TÜRKİYE IRAQ 400 kV Existing 400 kV Underconstruction 220 kV Existing 154 kV Existing 42 km 400kV SYRIA 124 km 400kV KKTC 7 7 PLAN FOR 2013 BULGARIA 145 km 400kV 136 km 400kV If ENTSO-E connection will be approved GEORGIA 28 km 220kV 160km 400kV ARMENIA GREECE 130 km 400kV 80,7 km 154kV 40 MW NAHCEVAN 87 km 154kV 40 MW IRAN 73 km 154kV 100 km 400kV TÜRKİYE IRAQ 400 kV Existing 400 kV Underconstruction 220 kV Existing 154 kV Existing 42 km 400kV SYRIA 124 km 400kV KKTC 8 8 PLAN FOR 2015 BULGARIA 145 km 400kV 136 km 400kV If ENTSO-E connection will be approved GEORGIA 28 km 220kV 160km 400kV ARMENIA GREECE 130 km 400kV 80,7 km 154kV 40 MW NAHCEVAN 87 km 154kV 40 MW IRAN 73 km 154kV 100 km 400kV TÜRKİYE IRAQ 400 kV Existing 400 kV Under Construction 220 kV Existing 154 kV Existing 42 km 400kV SYRIA 124 km 400kV KKTC 9 9 UCTE/ENTSO-E • Trial Run period started with ENTSO-E on 18th of September 2010. • The first phase system stability tests approved by ENTSO-E Planary Group on 8th of February. • Without any trade Import-Export tests for the second phase found successfull by ENTSO-E. • The third phase (import-export with trade) related with the synchronous parallel operation of Turkey with European Power System started on 1th of June 2011 and it will be ended on September 2012. • Trade will be limited with 400 MW from Bulgaria and Greece to Turkey; 300 MW from Turkey to Europe via these countries. 10 POWER PLANTS CONNECTION REQUESTS( December 2011) MW HPP TPP WPP POWER PLANTS CONNECTION REQUESTS NGCCP CAPACITY APPROVED BY TEİAŞ CAPACITY HAS BEEN LICENCED BY EMRA CAPACITY HAS CONNECTION AGREEMENT BY TEİAŞ TOTAL TOTAL Other 4.741 2.528 24.250 7.838 39.357 10.114 5.066 5.765 2.715 23.660 6.473 3.464 5.715 6.391 28.267 21.328 11.058 35.730 16.944 85.060 11 INCENTIVES FOR RENEWABLE POWER PLANTS The Turkey’s Parliament approved a new law 29 December 2010, on regulating the renewable energy resources market in Turkey. The incentives which are applied for Renewable Power Plants with the new law guarantees a price of: • • • • • • • • 7.3 U.S. cents per kWh for wind energy and hydroelectric power, 10.5 US cents for geothermal energy and 13.3 US cents for energy from waste products and solar energy These prices will cover energy firms that are established between May 13, 2005 and Dec. 31, 2015. For energy purchases from companies founded later than Dec. 31, 2015, new prices defined by the Cabinet will be implemented. The prices for the new companies will not exceed the current figures, the law said. In the event that operators use local equipment and technology in renewables energy facilities, an additional support of 0.4 cents to 2.4 $ per kw will be provided for a five year term to companies that started producing energy before the end of 2015. The surplus generation from the renewables will be bought by the distribution companies for ten years guarantee with the defined energy prices. The law limits the total production of licensed solar energy with 600 MW until the year of 31 December 2013 and authorizes the cabinet to determine the limits afterwards. WPP INTEGRATION PROCESS TO THE GRID -TOTAL AVAILABLE WIND POWER CAPACITY CAN BE CONNECTED TO THE GRID? 1 NOVEMBER 2007 -EVALUATING OVERLAPPING WPP’S APPLICATION? ? SINGULAR APPLICATIONS AND LICENCE – CONNECTION TO THE GRID 3500MW CAPACITY ALLOCATED 78.000 MW TOTAL OVERLLAPPING APPLICATIONS 13 Wind Power Plants 14 WPP INTEGRATION PROCESS TO THE GRID TOTAL AVAILABLE WIND POWER CAPACITY CAN BE CONNECTED TO THE GRID? TOTAL AVAILABLE WIND POWER CAPACITY CAN BE CONNECTED TO THE NATIONAL GRID? AVAİLABLE WIND POWER CAPACITY CAN BE CONNECTED TO THE REGIONAL GRID? AVAILABLE WIND POWER CAPACITY CAN BE CONNECTED TO THE BUSBARS? THE FACTORS THAT LIMIT THE CAPACITY OF THE AVAILABLE WPP CONNECTION TO THE NATIONAL GRID • GENERATIONCONSUMPTION BALANCE • FREQUENCY RESERVE THE FACTORS THAT LIMIT THE CAPACITY OF THE AVAILABLE WPP CONNECTION TO THE REGIONAL GRID • VARIATIONS OF POWER FLOW • REGIONAL ENERGY QUALITY • ADDITIONAL INVESTMENTS FACTORS THAT LIMIT THE CAPACITY OF THE AVAILABLE WPP CONNECTION TO THE BUSBARS • ENERGY QUALITY • SHORT CIRCUIT POWER ON MEDIUM VOLTAGE LEVEL 15 WPP INTEGRATION PROCESS TO THE GRID DETERMINATION OF CONNECTABLE WİND POWER CAPACITY TO THE SYSTEM •Evaluation of the available wind power capacity can be connected to the system •Power Flow studies • Evaluation of wind variability on the effect of power flow and local grid •Planning the investment of basin substation and transmission lines 16 WPP INTEGRATION PROCESS TO THE GRID -TOTAL AVAILABLE WIND POWER CAPACITY CAN BE CONNECTED TO THE GRID? APPLIED APPROACHES IN THE WORLD -Integration to the 1/3 ratio to the demand of system minimum -Integration to the 25% ratio to the demand of system maximum APPLICATION 78.000 MW 2013 Estimated Minimum System Peak 2013 Estimated Maximum System Peak 18.703 MW 46.757 6.727 MW (1/3 of Peak ) 11.689 MW (25% of Peak) 17 WPP INTEGRATION PROCESS TO THE GRID DETERMINATION OF CONNECTABLE WİND POWER CAPACITY TO THE SYSTEM NEGATIVE EFFECTS OF WIND POWER PLANTS ON GRID - FAULT-RIDE TROUGH CAPABILITY OF WPP’S -FLICKER (Turbulence/Output Power Source) -VOLTAGE FLUCTUATION(Cause of Output Power fluctuation and insufficient of reactive power support) Figure: Variable of wind generation -HARMONICS( Cause of Power Electronic Equipments) 18 Wind Power Plants INSTALLED CAPACITY AND PEAK LOAD OF TURKEY ACCORDING TO THE YEARS AND AVAILABLE RENEWABLE CAPACITY CAN BE CONNECTED TO THE SYSTEM 120000 100000 PEAK DEMAND MW 80000 INSTALLED CAPACITY 60000 CONNECTABLE RENEWABLE CAPACITY 40000 20000 0 YEARS 19 QUEUE MANAGEMENT OF WIND POWER PLANTS • Process: 1. 2. 3. 4. 5. 6. The available capacity of substations for connecting wind powerplants are published by TEİAS. WPP applications are forwarded to TEIAS for studying connection opportunities. TEIAS gives its comment concerning the availability.If the application is alone in the substation, EMRA gives license to those applications. If there are multiple applications in one substation, compitition process is done by TEIAS to determine the owner of the capacity. After taking license the investor sign a connection agreement with TEIAS. Project will be approved by MENR. After the realization of the project System Usage Agreement will be signed by TEIAS. 20 Competitions competition organisation number of invited companies number of substations number of winner companies total connection capacity (MW) 1 27 12 16 626 2 11 5 6 281 3 26 8 8 500 4 31 3 8 395 5 30 8 9 520 6 38 8 16 289,4 7 46 6 15 427 8 54 6 12 607 9 41 3 4 74 10 37 5 9 217 11 175 16 31 1199 12 33 4 7 198 13 47 3 6 166 TOTAL 596 87 147 5500 Weighted average of the competition prices is 1,91 kurus/kwh 21 Winner prices and installed capacities Winner prices according to installed capacity 481 MW %9 0 - 0,5 krş/kWh 728 MW %13 0,5-1 krş/kWh 2215,7 MW %40 1-2 krş/kWh 2-3 krş/kWh 3-4 krş/kWh 816,6 MW %15 4-5 krş/kWh 225,5 MW %4 605,5 MW %11 427 MW %8 5krş/kWh 22 Future Problems • What will be the operation problems if ~11000 MW wind power plant will be in service ? • Wind applications are concentrated in west side of Turkey. This will cause excessive voltage changes in the region • Effective regional voltage control ; • Effective secondary reserve control • Effective ENTSO-E interconnection tie line control will be needed • All these issues can be managed by an effective wind forecast and monitoring system 23 WPP INTEGRATION PROCESS TO THE GRID FAULT RIDE THROUGH CAPABILITY of WPPS Existed regulation Annex-18 New regulation for wind 1.0 U, Line Voltage(p.u) 0.9 1 0.7 2 0.45 Wind turbines do not trip above this line 0 150 700 1500 3000 Time, milisecond 24 WPP INTEGRATION PROCESS TO THE GRID REACTIVE POWER CAPABILITY Existed regulation Annex-18 Total Active Power (pu) New regulation for wind 1 0.9 0.8 0.7 PF 0.95 capacitive 0.6 PF 0.95 enductive 0.5 0.4 0.3 0.2 PF 0.835 capacitive PF 0.835 enductive 0.1 0 -0.4 0.1 pu under output power (total active power) , Reactive power capacity is not checked. -0.3 -0.2 Under Excited Region -0.1 0 Total Reactive Power (pu) 0.1 0.2 0.3 0.4 Over Excited Region 25 WPP INTEGRATION PROCESS TO THE GRID AVAILABLE WIND POWER CAPACITY CAN BE CONNECTED TO THE BUSBARS? According to the Transmission System Supply Reliability And Quality Regulation in the third section Generation Connection Principles - Design Principles of Generation Facility Switchyards defined that “Connection of generation facility based on wind energy is permitted for a capacity up to 5 % of the system short circuit power at the connection point ” For example, A substation, minumum3 ϕ Short Circuit Power is Sk=3000 MVA Available wind power capacity for this busbar is 3000x5/100 = 150 MW - New regulation which will be published in the near future, IEC 61400 standarts are applied to determine available wind power capacity 26 Solar Energy in Turkey 27 Connection points for solar Power Plants • The capacity of 600MW for Solar Power plants has been approved by TEIAS according to regions. Regions Number of substations 1 KONYA 8 2 KONYA 5 3 VAN AĞRI 5 4 ANTALYA 6 5 ANTALYA 8 6 KARAMAN 3 7 MERSİN 7 8 KAHRAMAN MARAŞ ADIYAMAN CAPACITY(MW) 46 46 77 29 29 38 35 9 10 NİĞDE NEVŞEHİR AKSARAY 3 26 4 26 11 KAYSERİ 6 25 12 MALATYA ADIYAMAN 13 HAKKARİ 14 MUĞLA AYDIN 15 ISPARTA AFYON 16 DENİZLİ 17 BİTLİS 18 BİNGÖL TUNCELİ 19 ŞIRNAK 20 ADANA OSMANİYE 27 9 BURDUR Regions 6 22 21 MUŞ 22 SİİRT BATMAN MARDİN Number of substations 2 8 21 20 7 18 3 2 4 3 18 16 11 11 4 9 1 9 5 9 23 SİVAS 1 24 ELAZIĞ 5 25 ŞANLIURFA DİYARBAKIR 1 26 ERZURUM 3 27 ERZİNCAN 2 TOTAL CAPACITY(MW) 9 8 7 121 5 3 600 *Applications has to sellect the most nearest substation for system connection according to the regulations 28 Hydraulic Power Plants Capacities in North East Region (In Operation &Planned) 1500 MW 2500 MW 2500 MW 29 Thank you for your attention 30