SANDAG Update

advertisement
RELATED TO AGENDA
ITEM W1
NCTD/SANDAG Project Update
Capital Improvement Program
Bill Prey, P.E., LOSSAN Corridor Director
San Diego Association of Governments
Current Rail Projects
• 19 projects now in
development
• 11 funded through
construction
• $467 million in funding
• $915 million estimate cost
at completion
• Schedule currently
funded through 2016
2
North Coast Corridor Program
3
In Design: Batiquitos Lagoon Double Track
Batiquitos Lagoon
Double Track
$3 million
Funded through
preliminary engineering
2.7 miles of second
track
Anticipated to reach
60% design Feb. 2015
4
In Design: Elvira to Morena & SD River Bridge
Elvira to Morena
Elvira to Morena
Double Track
$78.7 million
2 miles of second track in
City of San Diego
Construction start 2015
San Diego River Bridge
San Diego River Bridge
$9.4 million
Realignment of bridge
0.9 miles of second track
5
Near Construction: Sorrento Valley Double Track
Sorrento Valley
Double Track
North of Sorrento
Valley Station
$34 million
1 mile of second track
Construction start
Late 2013/Early 2014
Sorrento Valley Double Track
6
Near Construction: San Onofre Double Track
San Onofre to
Pulgas Double
Track
Camp Pendleton area
Longest stretch of
double track
4.2 miles
$38 million
Construction start
Fall 2013
7
Near Construction: Los Peñasquitos Lagoon
Los Peñasquitos
Lagoon Bridge
Project
$25 million
Recipient of $14
million TIGER grant
from US DOT
4 wooden bridges to
be replaced with
concrete bridges
Construction begins
mid-2014 for one
year
8
Near Construction: Oceanside Transit Center
Platform
Improvement
Project
$19.5 million
Add third track and
new platform
Construction start
TBD
Level boarding
considerations
Oceanside Transit Center
9
In Construction: Santa Margarita River Bridge
Santa Margarita
River Bridge
North of Oceanside
$41 million
0.8 miles
Sorrento to Miramar 1
Deck now replaced
Est. completion
April 2014
Tecolote Crossover
10
In Construction: Sorrento to Miramar Phase 1
Sorrento to Miramar
Double Track Phase 1
South of Sorrento
Valley Station
$44 million
1.4 miles
Estimated completion
January 2014
11
Near Completion: Tecolote/Washington Crossovers
Tecolote/Washington Street
Crossovers
Facilitates trains passing north
of Downtown San Diego
$11 million
Tecolote: Completed
September 2013
Tecolote Crossover
Washington Crossover
Washington: Completion slated
in October 2013
Near Completion: San Luis Rey Transit Center
San Luis Rey Transit
Center
New bus transit center
$9 million
Santa Margarita River Bridge
Sorrento to Miramar 1 SANDAG construction
completion October 2013
NCTD communications
work through early 2014
Bus operations to begin
in February 2014
13
Other SANDAG Initiatives

Station Parking Prioritization Study

Santa Fe Depot Study – in support of
Convention Center COASTER station

Level Boarding Analysis
14
LOSSAN Coastal Rail Corridor
Capital Improvement Projects
QUESTIONS & ANSWERS
More Information: KeepSanDiegoMoving.com/LOSSAN