Keeping San Diego Moving SANDAG Capital Program Update Bill Prey, P.E., Principal Engineer, SANDAG Ramon Ruelas, PE, Principal Construction Engineer, SANDAG SANDAG Capital Program Update I-5 North Coast Corridor Program LOSSAN Coastal Rail Corridor Light Rail Projects Trolley Renewal Program Mid-Coast Corridor Trolley Project Construction Delivery Methods Doing Business with SANDAG 2 Keeping San Diego Moving SANDAG Capital Program Update I-5 North Coast Corridor Program North Coast Corridor Program A $6.5 billion integrated program that includes: • Highway, bike, and pedestrian improvements • Coastal rail and transit improvements • Environmental protections and enhancements 4 NCC Public Works Plan 5 Keeping San Diego Moving SANDAG Capital Program Update LOSSAN Coastal Rail Corridor LOSSAN Corridor in San Diego • 60 miles in SD County • 50 percent single track • Six coastal lagoons • Two right-of-way owners: NCTD and MTS • NCTD Maintains and Manages Operations • Service by: COASTER, Amtrak, Metrolink, and BNSF Railway 7 Goal: Double Tracking the Corridor 8 LOSSAN Corridor - Current Projects • 23 projects currently in the program Camp Pendleton Marine Corps Base S13 5 • 15 funded through construction • $467 million in funding • $915 million estimate cost at completion • Schedule currently funded through 2017 Oceanside 78 Carlsbad Encinitas Solana Beach Del Mar 5 8 San Diego 9 LOSSAN Corridor Schedule 10 Projects in Construction 11 Projects In Construction Santa Margarita River Bridge and Double Track $41 million - 0.8 miles Estimated Completion April 2014 Santa Margarita River Bridge Sorrento to Miramar 1 Sorrento to Miramar Double Track Phase 1 $44 million – 1.4 miles Estimated Completion January 2014 Tecolote/Washington Street Crossovers Tecolote Crossover Washington Crossover $11 million – universal and single crossovers Estimated Completion December 2013 12 LOSSAN Corridor Projects in Design • Six of 14 projects fully funded through construction 13 Projects Near Construction San Onofre to Pulgas Double Track $37.6 m - 6 miles Oceanside Transit Center San Onofre Double Track Oceanside Transit Center $19.5 m - platform and passing track Sorrento Valley Double Track $33.7 m – 1 mile Los Peñasquitos Lagoon Bridges $22.2 m – 3 bridges Sorrento Valley Double Track Los Peñasquitos Bridges 14 Projects in Design Carlsbad Village Double Track Batiquitos Double Track Carlsbad Village Double Track 1 mile, $6 M funded to date for engineering Batiquitos Lagoon Double Track 2.7 miles, $ 3 M to date for engineering San Elijo Lagoon Double Track San Elijo Double Track San Dieguito Double Track 1.5 mile, $76.7 million through construction San Dieguito Double Track and Platform 1 mile, $9.5 M funded to date for engineering 15 Station Improvements Moving Trains Through the Stations Oceanside Transit Center $19.5 M Oceanside Transit Center Poinsettia Station Poinsettia Station $13 M Sorrento Valley Station $37.7 M Del Mar Fairgrounds Platform $9.5 M Sorrento Valley Station Del Mar Fairgrounds Platform 16 Keeping San Diego Moving SANDAG Capital Program Update Light Rail Projects Trolley Renewal Project 18 Mid-Coast Trolley Project SANDAG TransNet Early Action Project Extends MTS Trolley Blue Line from Santa Fe Depot through UCSD to UTC Project features: 11 miles of LRT 4 miles aerial 9 stations Project Budget: $1.7 billion 19 Mid-Coast Project Schedule Mid-2013 Released Draft SEIS/SEIR Mid-2014 Approve Project/Record of Decision Mid-2015 Full Funding Grant Agreement Late 2015 Begin construction Late 2018 Open for service 20 Keeping San Diego Moving SANDAG Capital Program Update Construction Delivery Methods CM/GC Delivery Method Enabling CM/GC legislation for SANDAG – January 2013 SANDAG awards two-phase contract: • • • Phase 1 - QBS contract for pre-construction services input to finalize design Phase 2 - negotiated GMP contract to construct project If GMP cannot be negotiated, SANDAG competitively bids contract 22 CM/GC Delivery Method May/June 2013 - SANDAG issued RFC to solicit industry comments on RFP template SANDAG Board approved projects for CM/CG • • • Mid-Coast Trolley Project Elvira to Morena Double Track San Diego River Bridge CM/GC RFP for approved projects anticipated late August/September 2013 23 Keeping San Diego Moving SANDAG Capital Program Update Doing Business with SANDAG Ramon Ruelas, PE, Principal Construction Engineer SANDAG CM On-Call Procurement Current CM Resources 4 CM contracts executed in Mid 2009 Initial term for each contract was 3 yrs Original value for each contract was $10 M Each contract contains four 1-year option extensions Each contract contains options that could increase contract value by add’l $15 M Options have increased total value of all contracts to $81.25 M 25 SANDAG Funded Construction Activity Construction Capital Expenditures by FY 550 Forecasts Expenditures 500 450 400 Millions ($) 350 300 250 200 150 100 50 0 FY10 FY11 FY12 FY13 FY14 FY15 FY16 FY17 FY18 Fiscal Year (FY) TransNet Funded Caltrans Projects Mid-Coast Trolley Project Other SANDAG Construction Projects 26 FY19 SANDAG CM On-Call Procurement Future CM Resources Three to five on-call contracts to be awarded Estimated value of contracts - $15 to $30 M each Mid-Coast Trolley CM contract - up to $120 M Contract duration - 3 years with four 1-year options A&E Bench – resource for prime consultant candidates to include SBE and DBE firms 27 SANDAG CM On-Call Procurement Solicitation Process Board approval to issue RFQ – Late October 2013 RFQ advertisement: October/November 2013 SOQ’s due: Mid-January 2014 Interviews: March 2014 Negotiations: Commence Late March 2014 Board approval: Late June 2014 28 SANDAG CM On-Call Procurement SANDAG Considering Solicitation Options: One RFQ adv.; separate SOQ submittals Two distinct RFQ adv.; separate SOQ submittals General CM Services Mid-Coast Trolley Project CM Services General CM Services Mid-Coast Trolley Project CM Services Independent cost estimating for Mid-Coast Trolley Project Part of Mid-Coast CM Services Solicitation Separate RFQ solicitation 29 SANDAG CM On-Call Procurement Potential Scope of CM Services Construction Contract Quality Assurance/Safety Compliance Field Inspection (RE, Assistant RE, and Field Inspectors Transit Inspection Field Office Engineering (Change Orders, Daily Diaries, As-Builts, etc.) Field Office Engineering (Change Orders, Daily Diaries, As-Builts, etc.) Field Office Administration Project Scheduling Contract Dispute Assistance and Claims Resolution Materials Sampling and Testing Constructability Reviews 30 SANDAG CM On-Call Procurement Potential Scope of CM Services (cont.) Storm Water Monitoring & Research Material/Product Plant and Source Inspection (Asphalt, Concrete, Manufacturing, etc.) Surveying and Construction Staking Traffic Handling Support Systems Start-up and Testing Records and File Auditing Construction Management Software Acquisition, Training, Upgrades, and Support Hazardous/contaminated materials assessment and disposal administration 31 Doing Business with SANDAG Register your firm online: SANDAG Encourages SB & DBE Participation: www.sandag.org/index.asp?fuseaction=rfps.bench Bid opportunities on Planet Bids: www.sandag.org/organization/rfps/registerinfo.asp www.sandag.org/index.asp?fuseaction=rfps.home Online project information: KeepSanDiegoMoving.com: TransNet projects SANDAG.org: Other capital projects Oceanside Transit Center 32 Keeping San Diego Moving SANDAG Capital Program Update QUESTIONS & ANSWERS More Information: SANDAG.org and KeepSanDiegoMoving.com