Customer Service Forum 27th February 2013 Legal Notice • The information contained in this document is confidential information as per your terms and conditions with British Telecommunications plc (“BT”). Please do not forward, republish or permit unauthorised access. BT has used its reasonable efforts to ensure that the content is accurate at the time of issue but it is subject to change. • Details of any developments contained within this document are for information purposes only and do not constitute any contractual or other obligation. 1 Agenda Anna Matty / Lisa Harrington 1. Introduction 2. Ethernet Richard Foxall 3. Broadband: Trouble to Resolve Richard Marsh 4. Broadband: Lead to Cash 5. Broadband: Escalations 6. High Level Escalations 7. Q&A 2 Neil Volan Marian Thorley Sean Kiernan Agenda Anna Matty / Lisa Harrington 1. Introduction 2. Ethernet Richard Foxall 3. Broadband: Trouble to Resolve Richard Marsh 4. Broadband: Lead to Cash 5. Broadband: Escalations 6. High Level Escalations 7. Q&A 3 Neil Volan Marian Thorley Sean Kiernan Openreach Planning Regional Variation Heat Maps (Day 8) (13/01 snapshot) RAG status Red > 5% below regional glidepath target Amber < 5% below target Green – at regional glidepath target or above 4 (10/02 snapshot) Openreach Planning Regional Variation Heat Maps (Day 14) (13/01 snapshot) RAG status Red > 5% below regional glidepath target Amber < 5% below target Green – at regional glidepath target or above 5 (10/02 snapshot) Ethernet Provision Performance (Fibre & Copper) Performance summary: • On time delivery continued improving trend Enabler When RAG Proactive Order Management In Place A Delay Unblocking Trial In Place G • Percentage Calls Answered (PCA) remains strong • Cycle time for Fibre delivery remains flat around 60 day mark • Copper delivery impacted by Openreach service delays. Cycle time rose first 2 weeks of January, but starting to come back down – average for first half of February 35.7 days 6 Ethernet Provision KCI Performance Performance summary: Enabler When • KCI2 success improved recent weeks with both customer delays and Openreach delays reducing – OR failure 13% average last 3 weeks Day 8 planning recovery – OR behind glide path – seeing trend of lower failure last 3 weeks Q4 A • KCI3 Openreach failure maintained below 8% Target Day 14 planning recovery – better than target Delivered C Reduce volumes of customer delays In place through Q4 G • Latest snapshot of order status shows good progress in unblocking customer delays to get orders fluid (up from 44%) 7 RAG Ethernet Repair Performance Performance summary: • On time repair performance, although at target, slipped in January due to a number of MSO’s and weather related delays. • Percentage calls answered in 30 seconds remains above target and flat compared to previous month • Fault rate continues to fall 8 Enabler When RAG Automation of engineer tasks In Place G Reducing manual activities – 20% time reduction In Place G Portal Improvements for Ethernet PROVISION/REPAIR 9 CUSTOMER FEEDBACK PORTAL IMPROVEMENT DELIVERY Provision I want to reduce the time it takes to order ethernet circuits on eCo Plus Quick Order Templates rebranded and trained out reducing order entry time by at least 5 minutes. Nov 12 Provision I want up to date training on the ethernet product and how to order circuits via eCo Plus New podcasts and CBT introduced on the Learning Management Academy Jan 13 Provision I want to be advised of any known capacity shortfalls and be given an alternative exchange and costs at the point of order entry to reduce service delivery delays Capacity checker and alternative exchange selection introduced Jan 13 Provision I want to be able to get accurate quotes prior to order entry and for that quote to be saved to stop the double keying of information Integration of Pricing Tool and eCo Plus Planned for delivery May 13 Repair I want to be able to see changes I have made to a fault post submission Customer amendments to a fault will be visible for them to see via the portal Delivered Jan 13 Repair I want to be able to run diagnostics without having to go into the fault reporting process Standalone diagnostic testing tool introduced Delivered Feb 13 Repair I want to receive updates via my preferred contact method Ability for a customer to specify contact method i.e. email, phone Planned for delivery Mar13 Key Improvement Plans for Ethernet KPI Incorrectly Applied Deemed Consent Deemed Consent (Customer Delays) Escalation 10 ACTIVITY CUSTOMER IMPACT TARGET RAG Industry validation of previously applied Deemed Consents Ensure feedback loop to prevent incorrect usage of deemed consent and identify areas for improvement In Place C Introduction of new deemed consent codes by Openreach Improve granularity of why deemed consent has been applied In Place C Introduction of new deemed consent KCI message by BT Wholesale Improve awareness of need for timely challenge and use of appeals process In Place C Delay Unblocking Trial with Openreach Reduce volume of all delayed orders to ensure completion as quickly as possible. In Place – runs to 31Mar G Reduce volumes of customer delays with BTW customers Triage calls in place with customers and Openreach to identify actions required to unblock delays and get the orders fluid. 5% reduction in customer delays since January forum In Place – runs to 31Mar G Proactive Order Management – identify and escalate all orders that have not had appropriate update from Openreach New proactive escalation process introduced 8th January to improve and drive the management of orders with Openreach. Steady volume of escalations since introduction. In Place 8th Jan A Introduction of new KCI template New template introduced on 4th February to give customers visibility where we have taken proactive escalation into Openreach In Place 4th Feb G Agenda Anna Matty / Lisa Harrington 1. Introduction 2. Ethernet Richard Foxall 3. Broadband: Trouble to Resolve Richard Marsh 4. Broadband: Lead to Cash 5. Broadband: Escalations 6. High Level Escalations 7. Q&A 11 Neil Volan Marian Thorley Sean Kiernan Broadband T2R – contact handling performance Performance summary: Enabler When • Propensity to contact and contact volumes have started to reduce leading to improved performance on % calls answered within 30 seconds with February performance close to 80% target 20 new advisors introduced & additional 1k resources deployed in Openreach December (BTW) January (OR) • Handling times maintained, however still seeing impact from the onward need to contact Openreach as part of the contact. BTW queue dwell management so diagnostics routinely completed within 8 hours Maintain through Q4 Contact reduction programme based on fault codes and joint working initiatives Through Q4 12 RAG C G G Broadband T2R – on time repair and fault performance Performance Summary: Enabler When • Openreach performance has stated to improve, however weather related issues are still resulting in an average repair time on the SFI product between 1- 3 days but typically toward the 2.5 day level. 20 new advisors introduced to assist in maintaining low BTW queue dwells December & Q4 • Low BTW queue dwells have been maintained throughout January and February Fault reduction through self-serve pilot and triage / QAT link up with Openreach Through Q4 Driving Openreach through product recovery glide path and addressing problematic fault journeys, e.g. REIN, SDSL. Q4 • Fault volumes stable through January and showing a declining trend in February 13 RAG C G R Broadband T2R – improvement plans KPI ACTIVITY On time repair performance Improved customer experience Missed appointments Escalations CUSTOMER IMPACT Reducing lead times a key priority – daily and weekly tracking in place with OR based on SFI performance, however commitment to normal operating levels (33k fault stack Mid-Feb ’13 reducing to 16k by mid-February breached) Programme of work with OR to reduce missed appointments which focusses on Jan ’13 visibility and metrics and agreeing improved targets Prevent faults auto-closing when an open escalation has been raised One contact resolution Customer, process and agent behaviours drive to uplift to 75 by year-end Contact reduction Improved fault handling 14 TARGET RAG R A Feb ‘13 C Q4 A Jan ’13 A AN & CD code contact removal Fault code based reduction of unnecessary contact Different ways of working Customer opportunity review of better ways of working – e.g. bulk/batch updates to jointly remove contact Q4 G Looping faults Looping faults process and workflow established from 15 Jan picking up faults at 3rd loop to intercept complex faults. QAT and OR Triage team linkage. Current performance on field save visits between teams is 70%. In place A Proactive fault resolution Engineering visit -2 days – additional checks performed with coop desk resolving a certain faults in agreement with customer to save truck rolls and improve cycle time Pilot in March ‘13 G SDSL Symmetrical Digital Subscriber Line BTW working closely with OR to review the end to end SDSL process to enable better management of SDSL faults. Feb ‘13 A Repetitive Electrical Impulse Noise BTW working with our suppliers to ensure better management and diagnosis of REIN cases. Jan & Feb ’13 G PEW’s forecast information now visible online at: https://www.btwholesale.com/pages/static/Library/Network_Information/Planned_Engineering_Works/ index.htm Agenda Anna Matty / Lisa Harrington 1. Introduction 2. Ethernet Richard Foxall 3. Broadband: Trouble to Resolve Richard Marsh 4. Broadband: Lead to Cash 5. Broadband: Escalations 6. High Level Escalations 7. Q&A 15 Neil Volan Marian Thorley Sean Kiernan Broadband Provision – On Time Delivery and Cycle Times 25.0 99 Cycle Time 98 20.0 97 96 15.0 95 10.0 94 93 5.0 92 0.0 91 April May Jun July 20C CT Actual Aug Sep Oct WBC CT Actual Nov Dec Jan FTTC CT Actual Performance Summary: • • • Cycle Times increased in January due to Bank Holidays and delayed orders closing as tail volumes reduced. To date, in February, cycle times have stabilised as orders are flowing through with shorter lead times Overall cycle time has been heavily impacted by PSTN lead times which determine SIM Provide delivery timescales. On time delivery was flat through January, again impacted by tail closure . Performance will remain flat as failed orders are closed but new orders will see improved performance. FTTC on time delivery has recovered following resolution of the Faulty D-side issue in December . Performance was impacted by bad weather in January but has been on an upward trajectory through February to date. 16 Apr May June 20C Actual July Aug Sept Oct 21C Actual Nov Dec Jan FTTC Actual Enabler When Openreach Lead Time Reduction PSTN lead times have reduced – average 14.62 days. Recovery of outstanding orders continues FTTC lead times have reduced from 15.1 to 8.4 days Through Q4 BTW Jeopardy Management New processes focussing on the KCI2+ period are reducing failure volumes Through Q4 Openreach Planning Review Planning support team in place from March to overview queue performance and turnaround times Through Q4 RAG A G A FTTC – Missed Appointments Supplier Missed Appointment Rate 9.00% 8.00% 7.00% 6.00% 7.00% 6.00% 5.00% 5.00% Total Supplier Missed 4.00% 3.00% Faulty D-side Delay 2.00% Multiple Supplier Missed 1.00% 0.00% 4.00% Performance Summary: • Supplier missed appointment volumes have seen significant improvement since holiday period- FTTC has reduced from 8.5% to 5% as of mid Feb. • Faulty D-side delays due to pair quality test on installation have reduced from 165 to less than 40 per day due to an Openreach process change and the inclusion of copper line test at KCI2. • Multiple missed appointments have reduced from 7% in December to 3.5% by mid February. • Customer missed appointment rate remains relatively flat -2rd missed appts will be reviewed to understand why and to identify learning opportunities with individual CPs No Access 3.00% Customer Not Ready 2.00% 1.00% Total Customer Missed 0.00% 30th 14th 28th 11th 25th 08th Nov Dec Dec Jan Jan Feb 17 CP Missed Appointment Rate 8.00% 2nd Nov 23rd Nov 14th Dec 04th Jan 25th Jan 15th Feb Enabler When Proactive Reappointing SOR raised at CPSG forum for Openreach process to reappoint prior to and on the day. SOR will be raised at Fibre forum 27th Feb. Q2 13/14 Multiple Missed Appts Prioritisation Reduction in missed volumes but Openreach rollout of never miss a second appointment has identified issues. BTW intervention process in place to avoid multiple missed. Q4 FTTC Tentative Appt Process Tactical Fix delivering 4 hour average response – strategic fix aimed for September. Q4 Tactical Fix Q2 13/14 Strategic Fix RAG G A A Broadband L2C – Improvement Plans KPI Missed Appointments ACTIVITY Faulty D- Side Process changes in Openreach to perform copper line test pre-KCI2 to ensure correctly skilled engineer is assigned to appointment. Proactive Reappointing & Speed to Appoint Programme to introduce a process for on the day reappointing and prior to the day reappointing where its clear that appointments will be failed – expedited second appointments with CPs having direct access to the appointment books. FTTC Customer Missed Appointments Customer Experience Contact Reduction 18 CUSTOMER IMPACT Missed appointments programme, target to reduce customer missed appointments across products . Openreach initiatives to reduce incorrectly assigned supplier missed appointments TARGET RAG Jan 13 B Q2 13/14 A Q4 A Bridge Cases Improvements to Jeopardy Management of Bridge Cases and performance to SLA. Q4 G Pro-Active Jeopardy Management Review of Interception points post KCI 2 based on delay reasons to drive On Time Delivery performance – trials have delivered a 15% improvement rate Q4 G Contact Medium Review A review is underway with selected CP’s to understand the best medium for different types of contact into BT Wholesale. Q4 G Agenda Anna Matty / Lisa Harrington 1. Introduction 2. Ethernet Richard Foxall 3. Broadband: Trouble to Resolve Richard Marsh 4. Broadband: Lead to Cash 5. Broadband: Escalations 6. High Level Escalations 7. Q&A 19 Neil Volan Marian Thorley Sean Kiernan Update on escalations Portal Progress • • • • Volume – 22.13% decrease up to Jan 2013 Escalation resolution time improvement from 11 days down to 7 days. First touch KCI- in hours – Sept 26% - current 83% overall. Repeats Sept 5.6% current – 3% Escalation Management programme • Repeats Quality checks - Training programme continues offshore. • RCA on top Escalation reasons links into Richard & Johns teams to ensure right Improvement plans are in place. Business • CSP updated –IPStream- WBC & FTTC current products on portal. • CSAT survey – opens on Escalation closure – 18th March. • Escalating to next level process improvements. Advisors can now set escalation in automation to stream to next available Team Leader / manager. • Escalation portal user guides – updated BTW.com – Library- Technical documents 20 Escalation portal customer requests - action plan Current Issues Actions Impact Timescale Correct a navigation error when we click to get more notes & then back button Customers should contact- BT Wholesale System Support Helpdesk 24 hrs – 7 days a week 0800 783 5639 option 1 Individual system issues deal in real time with System Support H.D BAU process Remove the notes add in limit from 1000 characters Increase characters to 8000 Improves the communication flows between Customer and BTW Escalation handler. 18 March Allow all characters and symbols in the notes field. Remove current security limitations across cross site scripting and SQL injection . Confined to notes field nothing can be executed elsewhere. All characters and symbols can be shared on the 13 May portal RAG report split between provision and repair. Improve current RAG report to show split Provision / Repair 15 July 21 Escalation portal customer requests - action plan Current Issues Actions Customer ability to raise escalation to Team Leader - Manager level that Provide option to select to streams the escalation out to the right escalate to next level. skill set Impact Timescale Customer doesn’t need to contact us to escalate to next level 15 July Include Circuit details as part of Escalations Detail page Show KCI status and next steps on details page Provide Escalation Level Status Include additional information on details page to avoid Avoids unnecessary searching. Customer searching elsewhere for same details. Remove duplicate escalations due to escalation type . Portal recognises same circuit details. Customer can only raise one escalation per circuit avoids duplicates. 15 July Integrate with fault / order tracker Fully integrate portal to all update systems. Enables update searches to be all in one place. Business Zone integration Introduce Escalation criteria validation - look up on SI to 22 15 July Business Zone integration Agenda Anna Matty / Lisa Harrington 1. Introduction 2. Ethernet Richard Foxall 3. Broadband: Trouble to Resolve Richard Marsh 4. Broadband: Lead to Cash 5. Broadband: Escalations 6. High Level Escalations 7. Q&A 23 Neil Volan Marian Thorley Sean Kiernan High Level Escalations 100 Volume glidepath Volume and mix 90 80 80 70 70 HLE Raised (Accepted) Base Forecast 60 60 50 50 40 40 30 30 20 • 20 10 Ethernet & Jeopardy Mgt. • Escalation Sprint • Quality Assurance • Process Improvements • Openreach Recovery 10 0 0 HLE Raised Accepted (Not Inc Pan) Pan Products Accepted Base Performance summary: • Overall volumes still showing the right trend – although there was an increase post the holiday dip over the New year. • Escalation Sprint on Broadband continues to focus on quality and helps with the volume of HLEs • Focus on Ethernet improvements – established governance on critical cases. Improvements started on Business as Usual cases 24 Enabler When RAG BB Escalation Sprint – to improve BAU escalations & empower 31/03/13 G Complex Case Reviews – driving process improvements in SDSL Tactical in place; 28 Feb 2013 G Ethernet – proactive order management and In progress – Feb other process improvements 2013 A In progress – on going G Communicate and engage with customers and Accounts teams on team scope and role High Level Escalations Top 5 Drivers Cycle Time 30d 0h Provision Delays 25d 0h Missed Appointments 20d 0h 15d 0h Simple 10d 0h Drop in Connection Issues Complex 5d 0h Slow Speed 8/3/2012 8/10/2012 8/17/2012 8/24/2012 8/31/2012 9/7/2012 9/14/2012 9/21/2012 9/28/2012 10/5/2012 10/12/2012 10/19/2012 10/26/2012 11/2/2012 11/9/2012 11/16/2012 11/23/2012 11/30/2012 12/7/2012 12/14/2012 12/21/2012 12/28/2012 1/4/2013 1/11/2013 1/18/2013 1/25/2013 2/1/2013 2/8/2013 2/15/2013 0d 0h Performance summary: • Simple – regular BB, reappointing cases – no civil works or long lead times; Complex – cases with planning, civil works and longer lead times (e.g. REIN) • Cycle time for complex cases reduced since December – however still above target • Joint Root Cause Analysis sessions started across BAU and HLE Offshore and Ethernet. • Quality – second HLE survey results 25 Failed installations Enabler When RAG Better Management of REIN cases 15/02/13 G Openreach Missed Appointment Improvements In progress – Q4 A Joint Offshore & HLE RCAs and joint RCAs with Ethernet provision and Openreach Started Jan 2013 G Quality Initiatives – Training, CSAT Survey In progress through to 31/3/13 G Ethernet – twice weekly governance on critical complex cases Starts Jan 2013 G High Level Escalations – Improvement Plan KPI Volume Cycle Time Quality 26 ACTIVITY CUSTOMER IMPACT TARGET DATE RAG Broadband Escalation Sprint Improvements in BAU Escalation- BB processes – to drive down HLEs 31/03/13 G Process Improvements – SDSL Reduction in SDSL issues across BTW – tactical solution in place 28/02/13 G Ethernet – proactive order management and other process improvements Ensure proactive escalation to improve and drive the management of orders and reduce the need to escalate to high level escalation Feb 2013 A Communication & Engagement Plan across all stakeholders Better understanding of when to escalate and what constitutes a high level escalation – to enable us to add value to the real urgent cases Ongoing G Process Improvements - REIN Reduction in cycle time of REIN cases – greater clarity of communication 15/02/13 G Cross-supplier Root Cause Analysis and process improvements (BB & Ethernet) Reduction in overall resolution speeds and improvement of processes to reduce the need to escalate Starts Jan 31/03/13 A Ethernet – twice weekly governance on critical complex cases Reduction of cycle time and clarity of information and senior focus on the most critical issues Starts Jan 2013 G Training – soft skills, Product (Ethernet, L2C, FTTC Refreshers) Improved quality of communication from HLE team 31/03/13 G Monthly CSAT Survey on HLE Handling Feedback loop – will also result in overall quality improvements from Started Dec the team. January results below. 12 G BB Proactive Trial – to proactively identify Improved response and resolution times as well as improved quality In progress and address cases and ETH Proactive (by addressing problems before they become high level escalations) Order Monitoring A Agenda Anna Matty / Lisa Harrington 1. Introduction 2. Ethernet Richard Foxall 3. Broadband: Trouble to Resolve Richard Marsh 4. Broadband: Lead to Cash 5. Broadband: Escalations 6. High Level Escalations 7. Q&A 27 Neil Volan Marian Thorley Sean Kiernan